CONFIRMED BIG TEN LARGE Mozambique · LNG plant
Mozambique LNG
Saipem (CCS JV leader) · McDermott (CCS JV partner) · Chiyoda (CCS JV partner)
FEED FEED: done Award EPC award: done, Jun 2019 E&P Engineering & procurement: in progress Build Construction: in progress Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Construction · 45% complete (Jul 2026) [2]
Value USD 6bn [1]
Workforce between 7,000 and 8,000 workers (TotalEnergies CEO, Q2 2026 results call) [2]
Finish 2029 [2]
Client, scope, phases, sources
Client: TotalEnergies (operator) for the Mozambique LNG Area 1 partners
Value: approximately USD 6 billion (Saipem's share of the CCS JV EPC contract, 2019) [1]
Finish: first LNG from the first train targeted for 2029 [2]
Scope
2 liquefaction trains, 12.88 Mtpa nameplate, storage tanks and export jetty [1] up to 13 Mtpa of LNG from 2029; project value USD 20 billion [2]
Phase by phase
Progress: almost 45% complete (TotalEnergies CEO, July 2026) [2]
FEED · doneEPC award · done · Jun 2019 [1] Engineering & procurement · in progressConstruction · in progressPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 lngindustry.com 2 clubofmozambique.com · checked 29 Oct 2026
CONFIRMED BIG TEN Qatar · LNG plant
North Field East & South
Chiyoda (CTJV, North Field East) · Technip Energies (CTJV on NFE; T.EN CCC JV leader on NFS) · Consolidated Contractors Company (T.EN CCC JV, North Field South)
FEED FEED: done Award EPC award: done, 9 Feb 2021 E&P Engineering & procurement: in progress Build Construction: in progress Comm. Pre-commissioning & commissioning: in progress, 7 Oct 2026 Start Start-up: not started
Now: Pre-commissioning & commissioning
Value not disclosed by the contractors;… [1]
Workforce not published
Finish 2027 [3]
Client, scope, phases, sources
Client: QatarEnergy
Value: not disclosed by the contractors; each award is 'major' for Technip Energies (NFE: over USD 1.0 bn; NFS: above EUR 1 bn of revenue) [1]
Finish: NFE: production expected to begin in H1 2027 (QatarEnergy CEO, per Reuters); first-train LNG in Q1 2027 per sources [3]
Scope
NFE: 4 mega trains x 8 Mtpa plus a large CO2 capture and sequestration facility; Qatar from 77 to 110 Mtpa [2] NFS: 2 mega trains x 8 Mtpa plus 1.5 Mtpa CO2 capture [1]
Phase by phase
FEED · doneEPC award · done · 9 Feb 2021 · NFE 9 Feb 2021; NFS 16 May 2023 [2] Engineering & procurement · in progressConstruction · in progressPre-commissioning & commissioning · in progress · 7 Oct 2026 · first NFE train reported ready to start operation in November 2026 (Reuters, sources) [3] Start-up · not started
Sources: 1 ten.com 2 ten.com 3 boereport.com · checked 29 Oct 2026
REPORTED BIG TEN LARGE Saudi Arabia · Gas processing
Jafurah
Larsen & Toubro (gas processing facilities, phase 2) · Samsung E&A (gas treatment) · Hyundai E&C (sulphur recovery, with Hyundai Engineering)
FEED FEED: done Award EPC award: done, 30 Jun 2024 E&P Engineering & procurement: in progress Build Construction: in progress Comm. Pre-commissioning & commissioning: unknown Start Start-up: in progress, Dec 2025
Now: Start-up
Value USD 12.4bn [1]
Workforce not published
Finish 2030 [2]
Client, scope, phases, sources
Client: Saudi Aramco
Value: 16 contracts totalling around USD 12.4bn (SR46.5bn) for the second phase (June 2024) [1]
Finish: 2 bscfd of sales gas targeted by 2030 (Aramco) [2]
Scope
phase 2: gas compression, pipelines, new gas processing trains, utilities, sulphur and export facilities, NGL fractionation at Jubail [1] 17,000 km2, 229 tcf of raw gas; 2 bscfd of sales gas, 420 MMscfd ethane and about 630,000 b/d liquids targeted by 2030 [2]
Phase by phase
FEED · doneEPC award · done · 30 Jun 2024 · phase 2 contracts [1] Engineering & procurement · in progressConstruction · in progressPre-commissioning & commissioning · unknownStart-up · in progress · Dec 2025 · phase 1: first shale gas produced December 2025; phase 2 under construction [2]
Sources: 1 offshore-technology.com 2 aramco.com · checked 29 Oct 2026
CONFIRMED BIG TEN LARGE OFFSHORE UAE · Gas processing
Hail & Ghasha
Saipem (offshore EPC, with NMDC Energy, formerly NPCC) · NMDC Energy (offshore EPC) · Tecnimont (MAIRE) (onshore EPC)
FEED FEED: done Award EPC award: done, 5 Oct 2023 E&P Engineering & procurement: in progress Build Construction: in progress Comm. Pre-commissioning & commissioning: unknown Start Start-up: not started
Now: Construction
Value USD 16.9bn [1]
Workforce not published
Finish 2028 [2]
Client, scope, phases, sources
Client: ADNOC
Value: USD 16.9bn (SR63.39bn) across two EPC contracts: offshore about USD 8.2bn (NPCC-Saipem), onshore USD 8.7bn (Tecnimont) [1]
Finish: onshore: completion expected during 2028 (MAIRE, 2023); first gas by the end of the decade (The National, Dec 2025) [2]
Scope
4 drilling centres and a processing plant on artificial islands; over 300 km of subsea pipelines [1] onshore: 2 gas processing units, 3 sulphur recovery sections, export pipelines [2] up to 1.8 bscfd of gas; 1.5 Mtpa CO2 capture [3]
Phase by phase
FEED · doneEPC award · done · 5 Oct 2023 [2] Engineering & procurement · in progressConstruction · in progressPre-commissioning & commissioning · unknownStart-up · not started
Sources: 1 offshore-technology.com 2 tecnimont.com 3 thenationalnews.com · checked 29 Oct 2026
CONFIRMED BIG TEN LARGE UAE · LNG plant
Ruwais LNG
Technip Energies (TJN Ruwais JV leader) · JGC (TJN Ruwais JV partner) · NMDC Energy (TJN Ruwais JV partner)
FEED FEED: done Award EPC award: done, 13 Jun 2024 E&P Engineering & procurement: in progress Build Construction: in progress Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Construction
Value USD 5.5bn [1]
Workforce not published
Finish 2028 [1]
Client, scope, phases, sources
Client: ADNOC (ADNOC Gas to hold 60%)
Value: EPC contract valued at over USD 5.5 billion (World Oil); 'major' for Technip Energies (above EUR 1 bn of revenue) [1]
Finish: train 1 on stream in H2 2028, train 2 in early 2029 (ADNOC Gas, Nov 2024) [1]
Scope
2 trains x 4.8 Mtpa = 9.6 Mtpa [1] electric-driven motors instead of gas turbines [2]
Phase by phase
FEED · doneEPC award · done · 13 Jun 2024 [2] Engineering & procurement · in progressConstruction · in progressPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 worldoil.com 2 ten.com · checked 29 Oct 2026
CONFIRMED BIG TEN Qatar · LNG plant
North Field West
Technip Energies (T.EN CCC GAC JV leader) · Consolidated Contractors Company (JV partner) · Gulf Asia Contracting (JV partner)
FEED FEED: done Award EPC award: done, 25 Feb 2026 E&P Engineering & procurement: in progress Build Construction: unknown Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Engineering & procurement
Value not disclosed; 'major' award for… [1]
Workforce not published
Finish not published
No open adverts linked today
Client, scope, phases, sources
Client: QatarEnergy
Value: not disclosed; 'major' award for Technip Energies: above EUR 1 billion of revenue [1]
Scope
2 mega trains x 8 Mtpa (about 16 Mtpa) [1] 1.1 Mtpa CO2 capture (2.2 Mtpa with NFS) [1]
Phase by phase
FEED · doneEPC award · done · 25 Feb 2026 [1] Engineering & procurement · in progressConstruction · unknownPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 ten.com · checked 29 Oct 2026
CONFIRMED BIG TEN LARGE Saudi Arabia · Gas processing
Fadhili Gas Plant Expansion
Samsung E&A (gas treatment unit, utilities and offsites) · GS Engineering & Construction (EPC package) · Nesma & Partners (EPC package)
FEED FEED: done Award EPC award: done, 2 Apr 2024 E&P Engineering & procurement: in progress Build Construction: in progress Comm. Pre-commissioning & commissioning: unknown Start Start-up: not started
Now: Construction
Value USD 7.7bn [1]
Workforce not published
Finish Nov 2027 [1]
Client, scope, phases, sources
Client: Saudi Aramco
Value: USD 7.7 billion of contracts (Aramco) [1]
Finish: expected to be completed by November 2027 (Aramco, April 2024) [1]
Scope
adds up to 1.5 bscfd of raw gas processing capacity [1] adds 2,300 t/d of sulphur production [1]
Phase by phase
FEED · doneEPC award · done · 2 Apr 2024 [1] Engineering & procurement · in progressConstruction · in progressPre-commissioning & commissioning · unknownStart-up · not started
Sources: 1 aramco.com · checked 29 Oct 2026
CONFIRMED BIG TEN LARGE Saudi Arabia · Petrochemical
Amiral
Hyundai E&C (mixed-feed cracker and utilities) · Tecnimont (MAIRE) (two polyethylene units) · Sinopec Engineering Group Saudi (tank farm and SATORP integration)
FEED FEED: done Award EPC award: done, 24 Jun 2023 E&P Engineering & procurement: in progress Build Construction: in progress Comm. Pre-commissioning & commissioning: unknown Start Start-up: not started
Now: Construction
Value USD 11bn [1]
Workforce no construction figure published; TotalEnergies: 7,000 local direct and indirect jobs (whole project, including the chemicals park) [1]
Finish 2027 [1]
Client, scope, phases, sources
Client: SATORP (Aramco 62.5%, TotalEnergies 37.5%)
Value: an investment of USD 11 billion (TotalEnergies) [1]
Finish: operational start-up planned for 2027 (TotalEnergies) [1]
Scope
mixed-feed cracker, 1.65 Mtpa of ethylene [1] two polyethylene lines of 500,000 t/y each [1]
Phase by phase
FEED · doneEPC award · done · 24 Jun 2023 · FID December 2022 [2] Engineering & procurement · in progressConstruction · in progressPre-commissioning & commissioning · unknownStart-up · not started
Sources: 1 totalenergies.com 2 totalenergies.com · checked 29 Oct 2026
CONFIRMED BIG TEN MEDIUM Oman · LNG plant
Marsa LNG
Technip Energies (EPC, LNG plant) · McDermott (CB&I) (EPC, LNG storage tank)
FEED FEED: done Award EPC award: done, 22 Apr 2024 E&P Engineering & procurement: in progress Build Construction: in progress Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Construction · 55% complete (Jun 2026) [2]
Value not disclosed; 'substantial'… [1]
Workforce not published
Finish 2028 [2]
No open adverts linked today
Client, scope, phases, sources
Client: TotalEnergies (80%) and OQ (20%)
Value: not disclosed; 'substantial' award for Technip Energies (EUR 500 million to 1 billion of revenue) [1]
Finish: start-up targeted in the first quarter of 2028 [2]
Scope
1 Mtpa liquefaction complex for ship fuelling [2] 165,000 m3 LNG storage tank [2]
Phase by phase
Progress: more than 55 per cent complete at the end of June 2026 [2]
FEED · doneEPC award · done · 22 Apr 2024 [1] Engineering & procurement · in progressConstruction · in progressPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 ten.com 2 omanobserver.om · checked 29 Oct 2026
CONFIRMED BIG TEN United States · LNG plant
Rio Grande LNG
Bechtel (EPC, all five trains)
FEED FEED: done Award EPC award: done E&P Engineering & procurement: in progress, Jun 2026 Build Construction: in progress, Jun 2026 Comm. Pre-commissioning & commissioning: in progress, Jun 2026 Start Start-up: not started
Now: Pre-commissioning & commissioning · 74% complete (Jun 2026) [1]
Value not stated in the sources read today
Workforce ~7,500 construction and trade workers during peak construction (NextDecade); FERC approved the raise from 5,225 in April 2026 [2]
Finish 2027 [1]
Client, scope, phases, sources
Client: NextDecade (Rio Grande LNG)
Value: not stated in the sources read today
Finish: first LNG from Train 1 expected in H1 2027; Phase 1 ahead of the guaranteed schedule (NextDecade, Q2 2026) [1]
Scope
Trains 1-5: about 30 Mtpa expected capacity [1] 48 Mtpa under construction and in development; site room for up to 10 trains [2]
Phase by phase
Progress: Trains 1-2: 74.0% (engineering 99.1%, procurement 97.8%, construction 58.9%, commissioning 0.6%); Train 3 50.4%; Train 4 15.5%; Train 5 9.4% [1]
FEED · doneEPC award · doneEngineering & procurement · in progress · Jun 2026 · Trains 1-2 engineering 99.1%, procurement 97.8% [1] Construction · in progress · Jun 2026 · Trains 1-2 construction 58.9% [1] Pre-commissioning & commissioning · in progress · Jun 2026 · Trains 1-2 commissioning 0.6%; first gas expected H2 2026 [1] Start-up · not started
Sources: 1 finviz.com 2 next-decade.com · checked 29 Oct 2026
CONFIRMED MEDIUM India · Refinery
HPCL Mumbai refinery: lube modernisation and bottom upgradation (LMBU)
Technip Energies (EPC)
FEED FEED: unknown Award EPC award: done, 12 Oct 2026 E&P Engineering & procurement: in progress Build Construction: unknown Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Engineering & procurement · 9.9% complete (31 Mar 2026) [1]
Value INR 57.4bn [1]
Workforce not published
Finish Mar 2028 [1]
No open adverts linked today
Client, scope, phases, sources
Client: Hindustan Petroleum Corp. (HPCL)
Value: project cost Rs 57.40 billion (US$600.4 million) at 31 Mar 2026, up from Rs 46.79 billion; Technip Energies' order: EUR 250-500 million of revenue [1]
Finish: scheduled to be fully completed in March 2028 (HPCL, May 2026) [1]
Scope
550,000 t/y integrated hydrocracker and catalytic dewaxing unit [1] 850,000 t/y solvent deasphalting unit [1]
Phase by phase
Progress: 9.9% physical completion at 31 Mar 2026 (HPCL) [1]
FEED · unknownEPC award · done · 12 Oct 2026 [2] Engineering & procurement · in progressConstruction · unknownPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 ogj.com 2 hydrocarbonengineering.com · checked 29 Oct 2026
CONFIRMED MEDIUM India · Petrochemical
BPCL Bina Petchem & Refinery Expansion: LLDPE/HDPE swing unit (2 x 575 ktpa)
L&T Energy Hydrocarbon (LSTK EPCC)
FEED FEED: unknown Award EPC award: done, 23 Dec 2025 E&P Engineering & procurement: in progress Build Construction: in progress, 29 Oct 2026 Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Construction
Value 'major' order: Rs 5,000-10,000… [1]
Workforce not published
Finish May 2028 [2]
Client, scope, phases, sources
Client: Bharat Petroleum Corp. (BPCL)
Value: 'major' order: Rs 5,000-10,000 crore band (L&T classification) [1]
Finish: BPREP scheduled for completion in May 2028 (BPCL annual report, via OGJ) [2]
Scope
LLDPE/HDPE swing unit, 2 x 575 ktpa [1] part of BPREP: refinery 7.8 to 11 Mtpa and a 1.2 Mtpa ethylene dual-feed cracker (project Rs 490 bn approved 2023) [2]
Phase by phase
FEED · unknownEPC award · done · 23 Dec 2025 [1] Engineering & procurement · in progressConstruction · in progress · 29 Oct 2026 · L&T advertises piping fabrication and erection roles at Bina [3] Pre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 larsentoubro.com 2 ogj.com 3 larsentoubrocareers.peoplestrong.com · checked 29 Oct 2026
CONFIRMED India · Petrochemical
BPCL Bina expansion: polypropylene (550 ktpa) and Butene-1 (50 ktpa) units
Technip Energies (EPCC)
FEED FEED: unknown Award EPC award: done, 7 Jan 2026 E&P Engineering & procurement: in progress Build Construction: unknown Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Engineering & procurement
Value not disclosed (described as a… [1]
Workforce not published
Finish May 2028 [2]
No open adverts linked today
Client, scope, phases, sources
Client: Bharat Petroleum Corp. (BPCL)
Value: not disclosed (described as a 'large' contract) [1]
Finish: BPREP scheduled for completion in May 2028 (BPCL annual report, via OGJ) [2]
Scope
550,000 t/y polypropylene and 50,000 t/y Butene-1 [1] part of BPREP (Bina refinery to 11 Mtpa, 1.2 Mtpa ethylene cracker) [2]
Phase by phase
FEED · unknownEPC award · done · 7 Jan 2026 [1] Engineering & procurement · in progressConstruction · unknownPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 hydrocarbonengineering.com 2 ogj.com · checked 29 Oct 2026
CONFIRMED India · Refinery
BPCL Mumbai refinery: 3 Mtpa petro resid FCC (PRFCC), India's first
Technip Energies (EPsCm: engineering, procurement, construction management)
FEED FEED: unknown Award EPC award: done, 7 Jan 2026 E&P Engineering & procurement: in progress Build Construction: unknown Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Engineering & procurement
Value not disclosed (described as a… [1]
Workforce not published
Finish not published
No open adverts linked today
Client, scope, phases, sources
Client: Bharat Petroleum Corp. (BPCL)
Value: not disclosed (described as a 'large' contract) [1]
Scope
3 Mtpa petro resid fluidised catalytic cracker (PRFCC), Mumbai refinery [1]
Phase by phase
FEED · unknownEPC award · done · 7 Jan 2026 [1] Engineering & procurement · in progressConstruction · unknownPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 hydrocarbonengineering.com · checked 29 Oct 2026
CONFIRMED India · Terminal & storage
Petronet LNG Dahej: 170,000 m3 LNG/ethane tank, 140,000 m3 propane tank, handling for the PDH-PP plant
L&T Energy Hydrocarbon (LSTK EPCC)
FEED FEED: unknown Award EPC award: done, 16 Jan 2026 E&P Engineering & procurement: in progress Build Construction: unknown Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Engineering & procurement
Value 'large' order: Rs 2,500-5,000… [1]
Workforce not published
Finish 'within the agreed timelines'… [1]
No open adverts linked today
Client, scope, phases, sources
Client: Petronet LNG
Value: 'large' order: Rs 2,500-5,000 crore band (L&T classification) [1]
Finish: 'within the agreed timelines' (L&T); no date published [1]
Scope
170,000 m3 LNG/ethane double-wall tank [1] 140,000 m3 propane double-wall tank, for the Dahej PDH-PP complex [1]
Phase by phase
FEED · unknownEPC award · done · 16 Jan 2026 [1] Engineering & procurement · in progressConstruction · unknownPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 larsentoubro.com · checked 29 Oct 2026
CONFIRMED MEDIUM OFFSHORE India · Offshore platform
ONGC west coast: Pipeline Replacement Project PRP-X and four wellhead platforms
L&T Energy Hydrocarbon Offshore (EPCIC)
FEED FEED: unknown Award EPC award: done, 10 Aug 2026 E&P Engineering & procurement: in progress Build Construction: unknown Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Engineering & procurement
Value between Rs 50bn (US$525.2m) and… [1]
Workforce not published
Finish not published
No open adverts linked today
Client, scope, phases, sources
Client: ONGC
Value: between Rs 50bn (US$525.2m) and Rs 100bn (US$1.05bn), L&T band [1]
Scope
Pipeline Replacement Project PRP-X: several subsea pipeline segments [1] four wellhead platforms, EPCIC [1]
Phase by phase
FEED · unknownEPC award · done · 10 Aug 2026 [1] Engineering & procurement · in progressConstruction · unknownPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 offshore-technology.com · checked 29 Oct 2026
CONFIRMED OFFSHORE India · Offshore platform
ONGC Additional Development of Ratna-I (ADR-I) and NLM-14: 3 wellhead + 1 riser platform, subsea pipelines
L&T Energy Hydrocarbon Offshore (EPCIC)
FEED FEED: unknown Award EPC award: done, 9 Sep 2026 E&P Engineering & procurement: in progress Build Construction: unknown Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Engineering & procurement
Value 'large' order: Rs 2,500-5,000… [1]
Workforce not published
Finish not published
No open adverts linked today
Client, scope, phases, sources
Client: ONGC
Value: 'large' order: Rs 2,500-5,000 crore band (L&T classification) [1]
Scope
3 wellhead platforms + 1 riser platform, subsea pipelines (Ratna-I and NLM-14) [1]
Phase by phase
FEED · unknownEPC award · done · 9 Sep 2026 [1] Engineering & procurement · in progressConstruction · unknownPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 nsearchives.nseindia.com · checked 29 Oct 2026
CONFIRMED LARGE India · Refinery
IOCL Panipat refinery expansion, 15 to 25 Mtpa (+ polybutadiene rubber plant)
Contractors: not named in the sources we read
FEED FEED: done Award EPC award: done E&P Engineering & procurement: unknown Build Construction: in progress, 30 Jun 2026 Comm. Pre-commissioning & commissioning: not started, Dec 2026 Start Start-up: not started
Now: Construction · 94% complete (30 Jun 2026) [1]
Value INR 382.3bn [1]
Workforce not published
Finish Dec 2026 [1]
No open adverts linked today
Client, scope, phases, sources
Client: Indian Oil Corp. (IOCL)
Value: Rs 382.31 billion invested at 30 Jun 2026 (initially budgeted Rs 329.46 bn) [1]
Finish: commissioning scheduled for December 2026 (IOC filing, 31 Jul 2026) [1]
Scope
15 to 25 Mtpa crude capacity (+ polybutadiene rubber plant) [1]
Phase by phase
Progress: 94% physical completion at 30 Jun 2026 (IOC) [1]
FEED · doneEPC award · doneEngineering & procurement · unknownConstruction · in progress · 30 Jun 2026 [1] Pre-commissioning & commissioning · not started · Dec 2026 · planned date [1] Start-up · not started
Sources: 1 ogj.com · checked 29 Oct 2026
CONFIRMED MEDIUM India · Refinery
IOCL Koyali (Gujarat) refinery expansion, 13.7 to 18 Mtpa (+ PP and lube base stock)
Contractors: not named in the sources we read
FEED FEED: done Award EPC award: done E&P Engineering & procurement: unknown Build Construction: in progress, 30 Jun 2026 Comm. Pre-commissioning & commissioning: not started, Nov 2026 Start Start-up: not started
Now: Construction · 89.2% complete (30 Jun 2026) [1]
Value INR 189.4bn [1]
Workforce not published
Finish Nov 2026 [1]
No open adverts linked today
Client, scope, phases, sources
Client: Indian Oil Corp. (IOCL)
Value: about Rs 189.36 billion overall cost (originally Rs 178.25 bn) [1]
Finish: commissioning planned for November 2026 (IOC filing, 31 Jul 2026) [1]
Scope
13.7 to 18 Mtpa crude capacity (+ polypropylene and lube base stock) [1]
Phase by phase
Progress: 89.2% physical completion at 30 Jun 2026 (IOC) [1]
FEED · doneEPC award · doneEngineering & procurement · unknownConstruction · in progress · 30 Jun 2026 [1] Pre-commissioning & commissioning · not started · Nov 2026 · planned date [1] Start-up · not started
Sources: 1 ogj.com · checked 29 Oct 2026
CONFIRMED MEDIUM India · Refinery
IOCL Barauni refinery expansion, 6 to 9 Mtpa
Contractors: not named in the sources we read
FEED FEED: done Award EPC award: done E&P Engineering & procurement: unknown Build Construction: in progress, 30 Jun 2026 Comm. Pre-commissioning & commissioning: not started, Dec 2026 Start Start-up: not started
Now: Construction · 91.6% complete (30 Jun 2026) [1]
Value INR 181.1bn [1]
Workforce not published
Finish Dec 2026 [1]
No open adverts linked today
Client, scope, phases, sources
Client: Indian Oil Corp. (IOCL)
Value: Rs 181.13 billion invested (previously budgeted Rs 148 bn) [1]
Finish: commissioning targeted for December 2026 (IOC filing, 31 Jul 2026) [1]
Scope
6 to 9 Mtpa crude capacity [1]
Phase by phase
Progress: 91.6% physical completion at 30 Jun 2026 (IOC) [1]
FEED · doneEPC award · doneEngineering & procurement · unknownConstruction · in progress · 30 Jun 2026 [1] Pre-commissioning & commissioning · not started · Dec 2026 · planned date [1] Start-up · not started
Sources: 1 ogj.com · checked 29 Oct 2026
REPORTED LARGE OFFSHORE India · Subsea
ONGC KG-DWN-98/2 deepwater block (Cluster 2), Krishna-Godavari basin
Afcons Infrastructure (current offshore piping work, named in its advert)
FEED FEED: done Award EPC award: done E&P Engineering & procurement: done Build Construction: done Comm. Pre-commissioning & commissioning: done Start Start-up: done, Jan 2024
Last step done: Start-up
Value USD 5bn [1]
Workforce not published
Finish producing since January 2024;… [1]
Client, scope, phases, sources
Client: ONGC
Value: USD 5 billion deep-water project (Outlook Business headline, Jan 2024) [1]
Finish: producing since January 2024; ramp-up [1]
Scope
Cluster 2 deep-water development, Krishna-Godavari basin [1]
Phase by phase
FEED · doneEPC award · doneEngineering & procurement · doneConstruction · donePre-commissioning & commissioning · doneStart-up · done · Jan 2024 · first oil January 2024; ramp-up and further work ongoing [1]
Sources: 1 outlookbusiness.com · checked 29 Oct 2026
CONFIRMED OFFSHORE UAE · Gas compression
ADNOC Offshore Umm Shaif gas cap and pressure boosting, package 1 (30,000 t gas compression)
L&T Energy Hydrocarbon Offshore (consortium leader) · Lamprell (consortium partner)
FEED FEED: done Award EPC award: done, 4 Aug 2026 E&P Engineering & procurement: in progress Build Construction: unknown Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Engineering & procurement
Value 'ultra-mega' order (above Rs 150… [1]
Workforce not published
Finish 2030 [1]
No open adverts linked today
Client, scope, phases, sources
Client: ADNOC Offshore
Value: 'ultra-mega' order (above Rs 150 bn, L&T band); the three EPC packages total USD 5.1bn; FID USD 6.2bn [1]
Finish: production expected by 2030 (MEED) [1]
Scope
30,000-tonne gas compression system (package 1) [1] 600 MMcfd of gas [1]
Phase by phase
FEED · doneEPC award · done · 4 Aug 2026 · FID July 2026 [1] Engineering & procurement · in progressConstruction · unknownPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 guest.meed.com · checked 29 Oct 2026
CONFIRMED OFFSHORE UAE · Gas compression
ADNOC Umm Shaif integrated gas cap and surface pressure boosting, package 4 (jacket + topside)
McDermott (EPCI) · Qingdao McDermott Wuchuan (QMW) (consortium, fabrication yard)
FEED FEED: done Award EPC award: done, 24 Aug 2026 E&P Engineering & procurement: in progress Build Construction: unknown Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Engineering & procurement
Value more than USD 1 billion ('mega'… [1]
Workforce not published
Finish 2030 [2]
No open adverts linked today
Client, scope, phases, sources
Client: ADNOC
Value: more than USD 1 billion ('mega' award, McDermott; exact value not disclosed) [1]
Finish: production from the Umm Shaif gas cap development expected by 2030 (MEED) [2]
Scope
new surface pressure boosting facility: jacket, topside, brownfield modifications [1] fabrication at QMW yard, Qingdao (China) [1]
Phase by phase
FEED · doneEPC award · done · 24 Aug 2026 [1] Engineering & procurement · in progressConstruction · unknownPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 worldoil.com 2 guest.meed.com · checked 29 Oct 2026
REPORTED MEDIUM OFFSHORE UAE · Offshore platform
ADNOC SARB deep gas development (Ghasha concession): wellhead tower, 4 wells, tie-in to Das Island
McDermott (EPC)
FEED FEED: done Award EPC award: done, Jan 2026 E&P Engineering & procurement: in progress Build Construction: in progress, 16 Oct 2026 Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Construction
Value USD 500m [1]
Workforce not published
Finish production 'later this decade'… [2]
No open adverts linked today
Client, scope, phases, sources
Client: ADNOC
Value: estimated USD 500 million (MEED) [1]
Finish: production 'later this decade' (World Oil, Jan 2026) [2]
Scope
200 MMscfd from four wells, about 120 km offshore [2] wellhead tower tied in to Das Island [1]
Phase by phase
FEED · doneEPC award · done · Jan 2026 · FID 7 Jan 2026 [1] Engineering & procurement · in progressConstruction · in progress · 16 Oct 2026 · steel cut [1] Pre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 meed.com 2 worldoil.com · checked 29 Oct 2026
CONFIRMED LARGE UAE · Gas processing
ADNOC Gas Rich Gas Development phase 2: new gas processing train at Habshan
Wison Engineering (EPC)
FEED FEED: done Award EPC award: done, 10 Aug 2026 E&P Engineering & procurement: in progress Build Construction: unknown Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Engineering & procurement
Value USD 3.9bn [1]
Workforce not published
Finish not published
No open adverts linked today
Client, scope, phases, sources
Client: ADNOC Gas
Value: USD 3.9 billion EPC contract [1]
Scope
new gas processing train at the Habshan complex [1]
Phase by phase
FEED · doneEPC award · done · 10 Aug 2026 [1] Engineering & procurement · in progressConstruction · unknownPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 worldoil.com · checked 29 Oct 2026
CONFIRMED LARGE UAE · Gas processing
ADNOC Gas Rich Gas Development phase 3: new NGL fractionation train at Ruwais
Tecnimont (MAIRE) (EPC)
FEED FEED: done Award EPC award: done, 10 Aug 2026 E&P Engineering & procurement: in progress Build Construction: unknown Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Engineering & procurement
Value USD 4.3bn [1]
Workforce not published
Finish not published
No open adverts linked today
Client, scope, phases, sources
Client: ADNOC Gas
Value: USD 4.3 billion EPC contract [1]
Scope
new NGL fractionation train at Ruwais [1]
Phase by phase
FEED · doneEPC award · done · 10 Aug 2026 [1] Engineering & procurement · in progressConstruction · unknownPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 worldoil.com · checked 29 Oct 2026
REPORTED MEDIUM UAE · Onshore oil field
ADNOC Onshore Bab and North East Bab one tie-in project (well tie-ins, mini-pad, well bays)
Robt Stone Middle East · Jereh Group
FEED FEED: unknown Award EPC award: in progress, 27 Oct 2026 E&P Engineering & procurement: not started Build Construction: not started Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: EPC award
Value USD 1.2bn [1]
Workforce not published
Finish not published
No open adverts linked today
Client, scope, phases, sources
Client: ADNOC Onshore
Value: estimated USD 1.2bn (MEED) [1]
Scope
well tie-ins, mini-pad and well bays, Bab and North East Bab fields [1]
Phase by phase
FEED · unknownEPC award · in progress · 27 Oct 2026 · contractors selected and notified; kick-off not yet held [1] Engineering & procurement · not startedConstruction · not startedPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 guest.meed.com · checked 29 Oct 2026
ON THE RADAR UAE · Onshore oil field
ADNOC Onshore Rumaitha and Shanayel field facilities (North East Bab), 45,000 b/d
Contractors: bidders not named
FEED FEED: unknown Award EPC award: in progress, 20 Oct 2026 E&P Engineering & procurement: not started Build Construction: not started Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: EPC award
Value not disclosed [1]
Workforce not published
Finish not published
No open adverts linked today
Client, scope, phases, sources
Client: ADNOC Onshore
Value: not disclosed [1]
Scope
field facilities for 45,000 b/d (Rumaitha and Shanayel, North East Bab) [1]
Phase by phase
FEED · unknownEPC award · in progress · 20 Oct 2026 · tender: technical bids in 5 Aug, commercial bids in preparation [1] Engineering & procurement · not startedConstruction · not startedPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 guest.meed.com · checked 29 Oct 2026
CONFIRMED MEDIUM OFFSHORE Saudi Arabia · Offshore platform
Saudi Aramco: three offshore EPC projects (names and locations not disclosed)
NMDC Energy (EPC)
FEED FEED: unknown Award EPC award: done, 23 Oct 2026 E&P Engineering & procurement: not started Build Construction: not started Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Last step done: EPC award
Value AED 2.8bn [1]
Workforce not published
Finish 18 to 23 months from award [1]
No open adverts linked today
Client, scope, phases, sources
Client: Saudi Aramco
Value: AED 2.8 billion (about USD 763 million) [1]
Scope
three offshore EPC projects; names and locations not disclosed [1]
Phase by phase
FEED · unknownEPC award · done · 23 Oct 2026 · letter of award [1] Engineering & procurement · not startedConstruction · not startedPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 thenationalnews.com · checked 29 Oct 2026
CONFIRMED MEDIUM Saudi Arabia · Gas compression
Aramco Shedgum-Uthmaniyah gas compression: Uthmaniyah compression plant package
Saipem (SNSH JV, contract share EUR 900m) · Nasser Saeed Al-Hajri & Partners Contracting (SNSH JV)
FEED FEED: done Award EPC award: done, Jun 2026 E&P Engineering & procurement: in progress, 12 Aug 2026 Build Construction: not started Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Engineering & procurement
Value USD 1.2bn [1]
Workforce not published
Finish EPC works run for 42 months (from… [1]
No open adverts linked today
Client, scope, phases, sources
Client: Saudi Aramco
Value: about USD 1.24bn (sources, MEED); Saipem share EUR 900m (USD 1.04bn) [1]
Finish: EPC works run for 42 months (from the August 2026 kick-off) [1]
Scope
new compression plant for the non-associated Uthmaniyah gas field (now about 1.2 bcfd of Khuff raw gas) [1] one of nine EPC packages of the Shedgum-Uthmaniyah programme [1]
Phase by phase
FEED · doneEPC award · done · Jun 2026 [1] Engineering & procurement · in progress · 12 Aug 2026 · EPC work kicked off [1] Construction · not startedPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 guest.meed.com · checked 29 Oct 2026
CONFIRMED Saudi Arabia · Pipeline
Ghazlan 1: sales gas delivery system
GAS Arabian Services (EPC)
FEED FEED: unknown Award EPC award: done, 9 Oct 2026 E&P Engineering & procurement: in progress Build Construction: not started Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Engineering & procurement
Value SAR 288m [1]
Workforce not published
Finish not published
No open adverts linked today
Client, scope, phases, sources
Client: Saudi Power Procurement Company
Value: above SAR 288 million (about USD 76.8m) [1]
Scope
sales gas delivery system to the Ghazlan 1 power plant [1]
Phase by phase
FEED · unknownEPC award · done · 9 Oct 2026 [1] Engineering & procurement · in progressConstruction · not startedPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 tradearabia.com · checked 29 Oct 2026
CONFIRMED LARGE Saudi Arabia · Fertiliser
SABIC Agri-Nutrients SAN-7, Jubail: gas-based ammonia (3,500 t/d) and urea (7,700 t/d)
Samsung E&A (sole EPC)
FEED FEED: unknown Award EPC award: done, 9 Sep 2026 E&P Engineering & procurement: in progress Build Construction: not started Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Engineering & procurement
Value KRW 4700bn [1]
Workforce EPC Radar estimate est. 8,500-38,900 at peak how?
Finish 2030 [1]
No open adverts linked today
Client, scope, phases, sources
Client: SABIC Agri-Nutrients
Value: KRW 4.7 trillion (about USD 3.5 billion) [1]
Finish: completion scheduled for 2030 [1]
Workforce estimate (low confidence): EPC Radar estimate from 2 published refinery, petrochemical and fertiliser plants projects in this tracker, 2.4-11.1 workers per USD million of declared value (id-rdmp-balikpapan, ar-fertil-pampa), applied to contract value: about USD 3,515 m
Scope
3,500 t/d ammonia [1] 7,700 t/d urea [1]
Phase by phase
FEED · unknownEPC award · done · 9 Sep 2026 [1] Engineering & procurement · in progressConstruction · not startedPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 hydrocarbonprocessing.com · checked 29 Oct 2026
ON THE RADAR Saudi Arabia · Gas processing
Aramco Alhada gas processing plant expansion (3 trains, sulphur recovery, utilities)
Contractors: not yet selected (3 EPC packages)
FEED FEED: unknown Award EPC award: not started, 30 Sep 2026 E&P Engineering & procurement: not started Build Construction: not started Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Before the EPC award
Value not disclosed [1]
Workforce not published
Finish not published
No open adverts linked today
Client, scope, phases, sources
Client: Saudi Aramco
Value: not disclosed [1]
Scope
3 gas processing trains, sulphur recovery, utilities [1]
Phase by phase
FEED · unknownEPC award · not started · 30 Sep 2026 · expressions of interest received; main tender next [1] Engineering & procurement · not startedConstruction · not startedPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 guest.meed.com · checked 29 Oct 2026
CONFIRMED LARGE Nigeria · LNG plant
Nigeria LNG Train 7, Bonny Island (22 to 30 Mtpa)
Saipem (SCD JV) · Chiyoda (SCD JV) · Daewoo E&C (SCD JV)
FEED FEED: done Award EPC award: done, 2020 E&P Engineering & procurement: unknown Build Construction: in progress, 3 Aug 2026 Comm. Pre-commissioning & commissioning: in progress, May 2026 Start Start-up: not started
Now: Pre-commissioning & commissioning · 93% complete (Aug 2026) [2]
Value USD 5bn [1]
Workforce over 13,000 Nigerians employed on Train 7 at peak construction (NLNG project director, ThisDay, May 2026); NLNG's CEO cited 16,000 direct jobs on site [1]
Finish 2027 [3]
Client, scope, phases, sources
Client: Nigeria LNG (NNPC, Shell, TotalEnergies, Eni)
Value: USD 5 billion project (ThisDay, May 2026) [1]
Finish: plans to commission the new facility in 2027 (NLNG CEO) [3]
Scope
NLNG capacity from 22 to 30 Mtpa (+35%) [2] Bonny Island, Rivers State [2]
Phase by phase
Progress: 93 per cent completion (NLNG Facts and Figures 2026, 3 Aug 2026) [2]
FEED · doneEPC award · done · 2020 [2] Engineering & procurement · unknownConstruction · in progress · 3 Aug 2026 · 93% overall [2] Pre-commissioning & commissioning · in progress · May 2026 · systems completion and pre-commissioning [1] Start-up · not started
Sources: 1 thisdaylive.com 2 shippingposition.com.ng 3 leadership.ng · checked 29 Oct 2026
CONFIRMED MEDIUM OFFSHORE Nigeria · Subsea
Shell Bonga North deepwater tie-back to the Bonga FPSO
Saipem (leader, share close to USD 900m) · KOA Oil & Gas · AVEON Offshore
FEED FEED: done Award EPC award: done, 19 Dec 2024 E&P Engineering & procurement: in progress Build Construction: in progress Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Construction
Value USD 1bn [1]
Workforce not published
Finish 2030 [2]
No open adverts linked today
Client, scope, phases, sources
Client: Shell Nigeria Exploration and Production Co. (SNEPCo)
Value: about USD 1 billion; Saipem share close to USD 900 million [1]
Finish: first oil 'by the end of the decade' (Shell FID, Dec 2024) [2]
Scope
16 wells (8 production, 8 water injection); peak 110,000 b/d of oil; over 300 MMboe [2] subsea tie-back 130 km offshore to the Bonga FPSO [1]
Phase by phase
FEED · doneEPC award · done · 19 Dec 2024 · FID 16 Dec 2024 [1] Engineering & procurement · in progressConstruction · in progressPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 offshore-mag.com 2 ogj.com · checked 29 Oct 2026
ON THE RADAR LARGE Nigeria · Refinery
Dangote refinery expansion, Lekki: 650,000 to 1.4 million b/d
Engineers India (EIL) (PMC and EPCM, USD 350m) · construction contractors not yet named
FEED FEED: unknown Award EPC award: in progress, 20 Jan 2026 E&P Engineering & procurement: unknown Build Construction: unknown Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: EPC award
Value USD 14.3bn [1]
Workforce about 95,000 skilled workers expected on site at the peak of construction (Aliko Dangote, 24 Apr 2026) [3]
Finish 2029 [1]
No open adverts linked today
Client, scope, phases, sources
Client: Dangote Industries
Value: USD 14.3 billion expansion plan (IPO documents, Sep 2026); EIL PMC/EPCM contract USD 350m [1]
Finish: due to be complete by 2029 (IPO prospectus, Reuters via Hydrocarbon Processing) [1]
Scope
refinery from 700,000 to 1.4 million b/d [1]
Phase by phase
FEED · unknownEPC award · in progress · 20 Jan 2026 · PMC/EPCM appointed; construction contractors not named [2] Engineering & procurement · unknownConstruction · unknownPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 hydrocarbonprocessing.com 2 industrialinfo.com 3 financialedge.com.ng · checked 29 Oct 2026
ON THE RADAR MEDIUM OFFSHORE Nigeria · Offshore platform
Ima gas project (OMLs 112/117): offshore platform + 22 km pipeline to NLNG
Contractors: not named yet; packages earmarked for Nigerian contractors
FEED FEED: done Award EPC award: unknown E&P Engineering & procurement: not started Build Construction: not started Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Last step done: FEED
Value USD 800m [1]
Workforce not published
Finish 2028 [1]
No open adverts linked today
Client, scope, phases, sources
Client: TotalEnergies (operator, 40%) and AMNI International (60%)
Value: around USD 800 million (Nigerian government); TotalEnergies' share more than USD 600 million [1]
Finish: first gas targeted for 2028 [1]
Scope
about 350 MMscfd of gas at plateau [1] offshore platform + 22 km pipeline to Nigeria LNG [1]
Phase by phase
FEED · doneEPC award · unknown · FID September 2026; contractors not named Engineering & procurement · not startedConstruction · not startedPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 chemanalyst.com · checked 29 Oct 2026
CONFIRMED OFFSHORE Mozambique · Floating LNG (FLNG)
Coral Norte FLNG (3.6 Mtpa), Area 4 offshore
Technip Energies (EPCIC) · JGC (EPCIC partner) · Samsung Heavy Industries (EPCIC partner, hull)
FEED FEED: done Award EPC award: done, 11 Jun 2026 E&P Engineering & procurement: in progress Build Construction: in progress Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Construction
Value not disclosed [1]
Workforce not published
Finish 2028 [2]
Client, scope, phases, sources
Client: Mozambique Rovuma Venture (Eni with CNPC, ENH, XRG, KOGAS)
Value: not disclosed [1]
Finish: on track to start production by 2028 (Eni, Oct 2026) [2]
Scope
FLNG of about 3.6 Mtpa, doubling the Coral hub to 7 Mtpa [1] up to six development wells drilled from November 2026 [2]
Phase by phase
FEED · doneEPC award · done · 11 Jun 2026 [1] Engineering & procurement · in progressConstruction · in progress · hull built in Korea [1] Pre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 hydrocarbonprocessing.com 2 oedigital.com · checked 29 Oct 2026
ON THE RADAR Mozambique · LNG plant
Rovuma LNG phase 1, onshore: 12 modular trains, 18.6 Mtpa (Afungi)
Saipem (SMDC JV) · McDermott (SMDC JV) · Daewoo E&C (SMDC JV) · CPECC (SMDC JV)
FEED FEED: unknown Award EPC award: in progress, 10 Aug 2026 E&P Engineering & procurement: in progress Build Construction: not started Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Engineering & procurement
Value not disclosed [1]
Workforce not published for the plant alone; ExxonMobil: about 7,500 Mozambicans in the Rovuma LNG construction phase (see upstream entry) [2]
Finish 2031 [1]
No open adverts linked today
Client, scope, phases, sources
Client: Area 4 partners (ExxonMobil for Mozambique Rovuma Venture)
Value: not disclosed [1]
Finish: start-up anticipated in 2031 (ExxonMobil) [1]
Scope
12 modular liquefaction modules, 18.6 Mtpa [1]
Phase by phase
FEED · unknownEPC award · in progress · 10 Aug 2026 · letter of intent for limited engineering and procurement; FID expected 2026 [1] Engineering & procurement · in progressConstruction · not startedPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 corporate.exxonmobil.com 2 corporate.exxonmobil.com · checked 29 Oct 2026
ON THE RADAR OFFSHORE Mozambique · Subsea
Rovuma LNG upstream: 18 wells, subsea pipelines and manifolds; Pemba shorebase
Saipem (upstream EPCI consortium, LOI) · Jan De Nul (upstream EPCI consortium, LOI) · CFML Logistic (Pemba shorebase land and infrastructure) · Alistair Group Mozambique (shorebase logistics)
FEED FEED: unknown Award EPC award: in progress, 10 Sep 2026 E&P Engineering & procurement: in progress Build Construction: not started Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Engineering & procurement
Value not disclosed (ExxonMobil cites… [1]
Workforce approximately 7,500 Mozambicans during the construction phase (ExxonMobil, 10 Sep 2026) [1]
Finish 2031 [2]
No open adverts linked today
Client, scope, phases, sources
Client: Area 4 partners (ExxonMobil for Mozambique Rovuma Venture)
Value: not disclosed (ExxonMobil cites about USD 6 billion of economic activity in Mozambique) [1]
Finish: Rovuma LNG start-up anticipated in 2031 (ExxonMobil) [2]
Scope
18 wells, subsea pipelines and manifolds [1] shorebase at the Pemba Bulk Terminal [1]
Phase by phase
FEED · unknownEPC award · in progress · 10 Sep 2026 · letter of intent; final award after FID [1] Engineering & procurement · in progressConstruction · not startedPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 corporate.exxonmobil.com 2 corporate.exxonmobil.com · checked 29 Oct 2026
CONFIRMED LARGE OFFSHORE Indonesia · FPSO
Kutei North Hub (Geng North, Gehem) FPSO, off East Kalimantan
PT Saipem Indonesia (EPCI JV) · PT Tripatra Engineers and Constructors (EPCI JV)
FEED FEED: done Award EPC award: done, 8 Jul 2026 E&P Engineering & procurement: in progress Build Construction: unknown Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Engineering & procurement
Value USD 2bn [1]
Workforce not published
Finish EPCI duration about 48 months… [1]
Client, scope, phases, sources
Client: Eni North Ganal (Searah: Eni + Petronas)
Value: about USD 2 billion for Saipem's share [1]
Finish: EPCI duration about 48 months from July 2026 [1]
Scope
FPSO for the Geng North and Gehem fields, off East Kalimantan [1]
Phase by phase
FEED · doneEPC award · done · 8 Jul 2026 [1] Engineering & procurement · in progressConstruction · unknownPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 ogj.com · checked 29 Oct 2026
CONFIRMED MEDIUM OFFSHORE Indonesia · Offshore platform
Tangguh Ubadari CCUS and compression (UCC), Papua Barat: 3 platforms, 90 km pipelines
Saipem (EPCI, share about USD 1bn) · PT Meindo Elang Indah (EPCI partner)
FEED FEED: done Award EPC award: done, 27 Nov 2024 E&P Engineering & procurement: in progress Build Construction: in progress Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Construction
Value USD 1.2bn [1]
Workforce not published
Finish 2028 [2]
No open adverts linked today
Client, scope, phases, sources
Client: BP Berau
Value: approximately USD 1.2bn; Saipem share around USD 1bn (project USD 7 billion) [1]
Finish: Ubadari production should start in 2028 (bp, FID Nov 2024) [2]
Scope
2 wellhead production platforms + 1 CO2 reinjection platform; about 90 km of pipelines [1] about 15 Mt of CO2 sequestered in the first phase; Ubadari about 3 tcf [2]
Phase by phase
FEED · doneEPC award · done · 27 Nov 2024 [1] Engineering & procurement · in progressConstruction · in progress · platforms fabricated at Saipem Karimun yard [1] Pre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 offshore-technology.com 2 offshore-mag.com · checked 29 Oct 2026
ON THE RADAR OFFSHORE Indonesia · LNG plant
Abadi LNG, Masela block: onshore LNG, FPSO, SURF, export pipeline
Saipem (FEED) · Tripatra (FEED) · McDermott (FEED) · Technip (FEED) · JGC (FEED) · KBR Indonesia (FEED) · Adhi Karya (FEED) · Samsung E&A (FEED) · Worley (FEED) · dual FEED: the winning group gets the EPC
FEED FEED: done, 27 Oct 2026 Award EPC award: not started E&P Engineering & procurement: not started Build Construction: unknown, Jul 2026 Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Last step done: FEED
Value not disclosed [1]
Workforce estimated around 12,000 direct workers during construction (Antara, Jul 2026) [2]
Finish first gas 2029-2030 (Dunia… [1]
No open adverts linked today
Client, scope, phases, sources
Client: INPEX Masela
Value: not disclosed [1]
Finish: first gas 2029-2030 (Dunia Energi, Oct 2026) [1]
Scope
onshore LNG of 9.5 Mtpa, plus FPSO, SURF and export pipeline [2]
Phase by phase
FEED · done · 27 Oct 2026 [1] EPC award · not started · FID by end of January 2027 [1] Engineering & procurement · not startedConstruction · unknown · Jul 2026 · groundbreaking held July 2026; main EPC not awarded [2] Pre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 dunia-energi.com 2 en.antaranews.com · checked 29 Oct 2026
CONFIRMED LARGE Indonesia · Refinery
Pertamina RDMP Balikpapan refinery upgrade, 260,000 to 360,000 b/d
Hyundai Engineering (EPC, 2019 contract)
FEED FEED: done Award EPC award: done, 17 Sep 2019 E&P Engineering & procurement: done Build Construction: done Comm. Pre-commissioning & commissioning: done Start Start-up: in progress, 12 Jan 2026
Now: Start-up
Value USD 2.2bn [1]
Workforce the number of workers involved reached 24 thousand people at peak construction (Pertamina, Nov 2025) [2]
Finish Jan 2026 [1]
No open adverts linked today
Client, scope, phases, sources
Client: Pertamina (PT Kilang Pertamina Balikpapan)
Value: EPC USD 2.17bn (2019); project Rp 123 trillion [1]
Finish: inaugurated 12 January 2026; ramp-up under way [1]
Scope
refinery from 260,000 to 360,000 b/d [1]
Phase by phase
FEED · doneEPC award · done · 17 Sep 2019 [3] Engineering & procurement · doneConstruction · donePre-commissioning & commissioning · doneStart-up · in progress · 12 Jan 2026 · inaugurated 12 Jan 2026; ramp-up [1]
Sources: 1 hydrocarbonengineering.com 2 kpb.pertamina.com 3 ogj.com · checked 29 Oct 2026
CONFIRMED LARGE China · Petrochemical
Sinopec Maoming refinery transformation and ethylene upgrade (ethylene 1.0 to 1.64 Mtpa)
Sinopec Engineering (SEI) (design lead; 3 Mtpa catalytic cracker and 1 Mtpa ethylene unit) · Sinopec Nanjing Engineering · Sinopec Shanghai Engineering · Sinopec Guangzhou Engineering · Sinopec Ningbo Engineering · Maoming Ruipai Petrochemical Engineering
FEED FEED: done Award EPC award: done E&P Engineering & procurement: in progress Build Construction: in progress, Jun 2026 Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Construction · 63% complete (Jun 2026) [1]
Value CNY 30bn [1]
Workforce not published
Finish not published
No open adverts linked today
Client, scope, phases, sources
Client: Sinopec Maoming
Value: over RMB 30 billion (project) [1]
Scope
ethylene from 1.0 to 1.64 Mtpa [1] 3 Mtpa catalytic cracker and 1 Mtpa ethylene unit [1]
Phase by phase
Progress: 63% overall; 103 of 107 main units started, 9 mechanically complete (Jun 2026) [1]
FEED · doneEPC award · doneEngineering & procurement · in progressConstruction · in progress · Jun 2026 · all heavy lifts done [1] Pre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 t.cj.sina.com.cn · checked 29 Oct 2026
CONFIRMED LARGE China · Refinery
Huajin Aramco Petrochemical (HAPCO), Panjin: 15 Mtpa refinery + 1.65 Mtpa ethylene; coal-to-hydrogen unit
China Chemical Engineering Second Construction (coal-to-hydrogen unit)
FEED FEED: done Award EPC award: done E&P Engineering & procurement: done Build Construction: done, 28 Apr 2026 Comm. Pre-commissioning & commissioning: in progress, 15 Oct 2026 Start Start-up: not started
Now: Pre-commissioning & commissioning
Value CNY 83.7bn [1]
Workforce not published
Finish start of operations not dated;… [2]
No open adverts linked today
Client, scope, phases, sources
Client: Huajin Aramco Petrochemical (Norinco, Aramco, Panjin Xincheng)
Value: RMB 83.7 billion (project) [1]
Finish: start of operations not dated; complex in pre-production preparation (Oct 2026) [2]
Scope
300,000 b/d refinery and 1.65 Mtpa ethylene [2] coal-to-hydrogen unit handed over 28 Apr 2026 [1]
Phase by phase
FEED · doneEPC award · doneEngineering & procurement · doneConstruction · done · 28 Apr 2026 · coal-to-hydrogen unit handover [1] Pre-commissioning & commissioning · in progress · 15 Oct 2026 · pre-production preparation; first Arabian crude arrived 9 Oct 2026 [2] Start-up · not started
Sources: 1 mtz.china.com 2 hydrocarbonengineering.com · checked 29 Oct 2026
CONFIRMED China · Refinery
Northern Huajin Union Petrochemical: 2.6 Mtpa product refining unit (Panjin)
China Chemical Engineering No.16 Construction (4th branch) (construction)
FEED FEED: done Award EPC award: done E&P Engineering & procurement: done Build Construction: done, 2 Jul 2026 Comm. Pre-commissioning & commissioning: unknown Start Start-up: not started
Last step done: Construction
Value not disclosed [1]
Workforce not published
Finish not published
No open adverts linked today
Client, scope, phases, sources
Client: Northern Huajin Union Petrochemical
Value: not disclosed [1]
Scope
2.6 Mtpa product refining unit, Panjin [1]
Phase by phase
FEED · doneEPC award · doneEngineering & procurement · doneConstruction · done · 2 Jul 2026 · intermediate handover [1] Pre-commissioning & commissioning · unknownStart-up · not started
Sources: 1 cn.chinadaily.com.cn · checked 29 Oct 2026
CONFIRMED LARGE China · Petrochemical
SABIC Fujian petrochemical complex, Gulei: 1.8 Mtpa ethylene, 16 derivative units
Contractors: not named in the sources we read
FEED FEED: done Award EPC award: done E&P Engineering & procurement: done Build Construction: done Comm. Pre-commissioning & commissioning: in progress, 26 Oct 2026 Start Start-up: not started
Now: Pre-commissioning & commissioning · 87% complete (30 Sep 2025) [1]
Value USD 6.4bn [1]
Workforce not published
Finish 2026 [2]
No open adverts linked today
Client, scope, phases, sources
Client: SABIC with Fujian Energy Petrochemical
Value: about USD 6.4 billion (project) [1]
Finish: on track for full startup during Q4 2026 (SABIC CEO, 26 Oct 2026) [2]
Scope
1.8 Mtpa ethylene and 16 derivative units, Gulei [1]
Phase by phase
Progress: 87% at end of Q3 2025 (SABIC) [1]
FEED · doneEPC award · doneEngineering & procurement · doneConstruction · donePre-commissioning & commissioning · in progress · 26 Oct 2026 · three PE/PP plants completed trial runs [2] Start-up · not started
Sources: 1 argaam.com 2 arabnews.pk · checked 29 Oct 2026
CONFIRMED LARGE OFFSHORE Qatar · Offshore platform
QatarEnergy Bul Hanine offshore redevelopment: 60+ facilities, 40 subsea pipelines and cables
COOEC (China Offshore Oil Engineering) (EPIC)
FEED FEED: done Award EPC award: done, 2025 E&P Engineering & procurement: in progress Build Construction: in progress, 15 Sep 2026 Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Construction
Value USD 4bn [1]
Workforce not published
Finish not published
No open adverts linked today
Client, scope, phases, sources
Client: QatarEnergy
Value: approximately USD 4 billion [1]
Scope
more than 60 offshore facilities and 40 subsea pipelines and cables [1]
Phase by phase
FEED · doneEPC award · done · 2025 [1] Engineering & procurement · in progressConstruction · in progress · 15 Sep 2026 · fabrication started in Qingdao [1] Pre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 constructionreviewonline.com · checked 29 Oct 2026
REPORTED LARGE OFFSHORE Kuwait / Saudi Arabia · Offshore platform
Dorra offshore gas field (Al-Khafji Joint Operations)
McDermott (offshore package 2A) · L&T Energy Hydrocarbon (package 2B with Saipem; package 1) · Saipem (package 2B with L&T) · Tecnicas Reunidas (onshore package 3, lowest bidder)
FEED FEED: done Award EPC award: in progress, 12 Aug 2026 E&P Engineering & procurement: in progress Build Construction: unknown Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Engineering & procurement
Value package 2A about USD 1.5bn… [1]
Workforce not published
Finish not published
No open adverts linked today
Client, scope, phases, sources
Client: Al-Khafji Joint Operations (Aramco Gulf Operations + Kuwait Gulf Oil Co.)
Value: package 2A about USD 1.5bn (McDermott); package 2B about USD 3.7bn (L&T + Saipem), MEED [1]
Scope
1 bcfd of gas produced jointly by Saudi Arabia and Kuwait [1]
Phase by phase
FEED · doneEPC award · in progress · 12 Aug 2026 · offshore packages awarded; onshore pending [1] Engineering & procurement · in progressConstruction · unknownPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 guest.meed.com · checked 29 Oct 2026
CONFIRMED MEDIUM Iraq · Gas processing
Ratawi gas processing complex (Gas Growth Integrated Project), 300 MMcf/d
CPECC (EPC, May 2025) · KBR (FEED)
FEED FEED: done Award EPC award: done, May 2025 E&P Engineering & procurement: in progress Build Construction: in progress, 21 May 2026 Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Construction
Value USD 1.6bn [1]
Workforce not published
Finish not published
No open adverts linked today
Client, scope, phases, sources
Client: TotalEnergies (operator) with Basra Oil Co. and QatarEnergy
Value: USD 1.61bn project [1]
Scope
300 MMcfd gas processing [1]
Phase by phase
FEED · doneEPC award · done · May 2025 [1] Engineering & procurement · in progressConstruction · in progress · 21 May 2026 · foundations under construction [1] Pre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 guest.meed.com · checked 29 Oct 2026
CONFIRMED Oman · Onshore oil field
PDO Block 6 EPC framework: Raba hub, Wadi Umairi, Rabab Harweel tranche 2, Bout, Dulaima, Makarem, Amal South-East, Hawqa Hasirah
L&T Energy Hydrocarbon Onshore (one of four framework contractors) · other three not named
FEED FEED: unknown Award EPC award: done, 31 Jul 2026 E&P Engineering & procurement: unknown Build Construction: unknown Comm. Pre-commissioning & commissioning: unknown Start Start-up: unknown
Last step done: EPC award
Value USD 6bn [1]
Workforce not published
Finish framework runs 6 years from July… [1]
No open adverts linked today
Client, scope, phases, sources
Client: Petroleum Development Oman (PDO)
Value: up to USD 6bn for the framework [1]
Finish: framework runs 6 years from July 2026 [1]
Scope
6-year EPC framework: Raba hub, Wadi Umairi, Rabab Harweel tranche 2, Bout, Dulaima, Makarem, Amal South-East, Hawqa Hasirah [1]
Phase by phase
FEED · unknownEPC award · done · 31 Jul 2026 · framework agreed; projects tendered inside the pool [1] Engineering & procurement · unknownConstruction · unknownPre-commissioning & commissioning · unknownStart-up · unknown
Sources: 1 guest.meed.com · checked 29 Oct 2026
CONFIRMED OFFSHORE Ivory Coast · FPSO
Baleine Phase 3: new FPSO + subsea (150,000 b/d oil, 200 MMscf/d gas field total)
Saipem (SURF EPCI) · Wison New Energies (FPSO EPCIC, owner Altera)
FEED FEED: done Award EPC award: done, 29 Jul 2026 E&P Engineering & procurement: in progress Build Construction: unknown Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Engineering & procurement
Value Saipem: about USD 930 million of… [1]
Workforce not published
Finish offshore construction expected to… [1]
No open adverts linked today
Client, scope, phases, sources
Client: Eni (with Petroci, Vitol)
Value: Saipem: about USD 930 million of new Eni contracts led by Baleine Phase 3; project value not disclosed [1]
Finish: offshore construction expected to take about three years (Jul 2026) [1]
Scope
new FPSO + subsea production infrastructure, flowlines, risers, umbilicals [1] field total 150,000 b/d oil, 200 MMscfd gas [1]
Phase by phase
FEED · doneEPC award · done · 29 Jul 2026 · FID May 2026 [1] Engineering & procurement · in progressConstruction · unknownPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 worldoil.com · checked 29 Oct 2026
REPORTED LARGE OFFSHORE Angola · FPSO
TotalEnergies Kaminho (Cameia, Golfinho), Block 20/11: converted FPSO, 70,000 b/d
Saipem (FPSO, named in Saipem/GPS AG adverts)
FEED FEED: done Award EPC award: done, 2024 E&P Engineering & procurement: in progress Build Construction: in progress, 22 Apr 2025 Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Construction
Value USD 6bn [1]
Workforce not published
Finish 2028 [1]
Client, scope, phases, sources
Client: TotalEnergies (40%), Petronas (40%), Sonangol (20%)
Value: USD 6 billion (project) [1]
Finish: production planned for 2028 [1]
Scope
converted FPSO, 70,000 b/d (Cameia and Golfinho, Block 20/11) [1]
Phase by phase
FEED · doneEPC award · done · 2024 · FID May 2024 [2] Engineering & procurement · in progressConstruction · in progress · 22 Apr 2025 · FPSO conversion in Nantong, China [1] Pre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 inspenet.com 2 offshore-technology.com · checked 29 Oct 2026
CONFIRMED OFFSHORE Cyprus · Subsea
Eni Cronos gas development, Block 6 (to Zohr and Damietta LNG, Egypt), 500 MMscf/d
McDermott (subsea, USD 500-750m) · other contractors not named by Eni
FEED FEED: done Award EPC award: done, 8 Sep 2026 E&P Engineering & procurement: in progress, 26 Oct 2026 Build Construction: not started Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Engineering & procurement
Value not disclosed by Eni; McDermott… [1]
Workforce not published
Finish 2028 [2]
No open adverts linked today
Client, scope, phases, sources
Client: Eni Cyprus (50%) with TotalEnergies
Value: not disclosed by Eni; McDermott subsea award USD 500-750 million [1]
Finish: first gas H1 2028 (Eni) [2]
Scope
500 MMscfd, Block 6, gas processed via Zohr and Damietta LNG (Egypt) [2]
Phase by phase
FEED · doneEPC award · done · 8 Sep 2026 · FID 28 Jul 2026 [1] Engineering & procurement · in progress · 26 Oct 2026 · execution phase launched [2] Construction · not startedPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 worldoil.com 2 eni.com · checked 29 Oct 2026
CONFIRMED OFFSHORE Romania · Offshore platform
Neptun Deep, Black Sea: Neptun Alpha platform, 10 wells, 160 km pipeline
Saipem (EPCIC: jacket, topsides, installation, pipeline)
FEED FEED: done Award EPC award: done E&P Engineering & procurement: done Build Construction: in progress, 10 Oct 2026 Comm. Pre-commissioning & commissioning: unknown Start Start-up: not started
Now: Construction
Value not stated in the source [1]
Workforce not published
Finish 2027 [1]
Client, scope, phases, sources
Client: OMV Petrom (50%) and Romgaz (50%)
Value: not stated in the source [1]
Finish: first gas H1 2027 [1]
Scope
Neptun Alpha platform, 10 wells, 160 km pipeline to shore [1]
Phase by phase
FEED · doneEPC award · doneEngineering & procurement · doneConstruction · in progress · 10 Oct 2026 · platform installed Jul 2026; 7 of 10 wells done [1] Pre-commissioning & commissioning · unknownStart-up · not started
Sources: 1 offshore-mag.com · checked 29 Oct 2026
ON THE RADAR OFFSHORE Norway · FPSO
Equinor Wisting (Barents Sea): FPSO topsides
Aibel (FEED for FPSO topsides, option for engineering, procurement and project management)
FEED FEED: in progress, 22 Oct 2026 Award EPC award: not started E&P Engineering & procurement: not started Build Construction: not started Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: FEED
Value not disclosed [1]
Workforce approximately 250 people will be involved (Aibel, FEED contract) [1]
Finish not published
No open adverts linked today
Client, scope, phases, sources
Client: Equinor (42.5%) with Aker BP, Petoro, INPEX Idemitsu
Value: not disclosed [1]
Scope
FEED for the topsides of the production vessel (Barents Sea) [1]
Phase by phase
FEED · in progress · 22 Oct 2026 [1] EPC award · not started · investment decision planned for late 2027 [1] Engineering & procurement · not startedConstruction · not startedPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 equinor.com · checked 29 Oct 2026
CONFIRMED LARGE Kazakhstan · Petrochemical
Silleno polyethylene plant, Atyrau: 1.25 Mtpa
Tecnimont (MAIRE) (polymerisation and offsites EPC, with Sinopec Shanghai Engineering) · Sinopec Shanghai Engineering (with Tecnimont) · pyrolysis unit contractor not named
FEED FEED: done Award EPC award: done, 2 Sep 2025 E&P Engineering & procurement: in progress Build Construction: in progress, 30 Sep 2026 Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Construction · 39% complete (Sep 2026) [1]
Value USD 7.7bn [1]
Workforce not published
Finish completion 2028-2029 (Trend, Sep… [1]
Client, scope, phases, sources
Client: Silleno LLP (KazMunayGas 40%, SIBUR 30%, Sinopec 30%)
Value: about USD 7.7bn (project) [1]
Finish: completion 2028-2029 (Trend, Sep 2026) [1]
Scope
1.25 Mtpa polyethylene, Atyrau [1]
Phase by phase
Progress: construction above 39% (Sep 2026) [1]
FEED · doneEPC award · done · 2 Sep 2025 [2] Engineering & procurement · in progressConstruction · in progress · 30 Sep 2026 [1] Pre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 trend.az 2 hydrocarbonprocessing.com · checked 29 Oct 2026
CONFIRMED LARGE Canada · LNG plant
LNG Canada Phase 2, Kitimat: 2 trains + 1 tank (to about 28 Mtpa)
Fluor Canada (JGC Fluor BC LNG II JV, 50%) · JGC Constructors (JGC Fluor BC LNG II JV, 50%)
FEED FEED: done Award EPC award: done, 1 Oct 2026 E&P Engineering & procurement: in progress Build Construction: not started Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Engineering & procurement
Value USD 7.5bn [1]
Workforce more than 4,000 direct jobs in the construction phase alone (Government of Canada, 29 Sep 2026) [2]
Finish not published
No open adverts linked today
Client, scope, phases, sources
Client: LNG Canada (Shell 40%, Petronas 25%, PetroChina 15%, Mitsubishi 15%, KOGAS 5%)
Value: Fluor's share USD 7.5 billion of a multibillion-dollar contract; project USD 33 billion (Government of Canada) [1]
Scope
2 liquefaction trains + 1 storage tank, terminal to about 28 Mtpa [1]
Phase by phase
FEED · doneEPC award · done · 1 Oct 2026 · FID 29 Sep 2026; notice to proceed [1] Engineering & procurement · in progressConstruction · not startedPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 energy-pedia.com 2 pm.gc.ca · checked 29 Oct 2026
CONFIRMED Canada · Gas compression
Coastal GasLink Phase 2: 5 compressor stations (pipeline capacity doubled)
TR Canada E&C (Tecnicas Reunidas) (EPCM)
FEED FEED: unknown Award EPC award: done, 21 Oct 2026 E&P Engineering & procurement: in progress Build Construction: not started Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Engineering & procurement
Value EUR 200m [1]
Workforce CGL Phase 2 expected to create over 2,000 jobs (Government of Canada, 29 Sep 2026) [2]
Finish execution from early 2027, over 4… [1]
No open adverts linked today
Client, scope, phases, sources
Client: LNG Canada (execution manager); Coastal GasLink owner
Value: above EUR 200 million (about USD 225m) [1]
Finish: execution from early 2027, over 4 years (OGJ) [1]
Scope
5 compressor stations, pipeline capacity doubled [1]
Phase by phase
FEED · unknownEPC award · done · 21 Oct 2026 [1] Engineering & procurement · in progressConstruction · not startedPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 ogj.com 2 pm.gc.ca · checked 29 Oct 2026
ON THE RADAR LARGE United States · Pipeline
Kinder Morgan Southeast Connector: about 470 miles, up to 2.6 bcf/d
Contractors: construction contractors not named
FEED FEED: unknown Award EPC award: not started E&P Engineering & procurement: not started Build Construction: not started Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Before the EPC award
Value USD 3.1bn [1]
Workforce not published
Finish 2030 [1]
No open adverts linked today
Client, scope, phases, sources
Client: Southern Natural Gas (Kinder Morgan)
Value: USD 3.1 billion (project) [1]
Finish: service expected to begin in phases from Q4 2030, subject to permits [1]
Scope
about 470 miles of new pipeline [1] up to 2.6 bcfd [1]
Phase by phase
FEED · unknownEPC award · not started · FID 22 Oct 2026; contractors not named [1] Engineering & procurement · not startedConstruction · not startedPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 ogj.com · checked 29 Oct 2026
CONFIRMED OFFSHORE Brazil · FPSO
Petrobras Buzios FPSOs P-80 and P-82 (+450,000 b/d together)
Seatrium (turnkey FPSOs)
FEED FEED: done Award EPC award: done E&P Engineering & procurement: done Build Construction: done, 27 Aug 2026 Comm. Pre-commissioning & commissioning: in progress Start Start-up: not started
Now: Pre-commissioning & commissioning
Value not stated in the source [1]
Workforce not published
Finish 2027 [1]
No open adverts linked today
Client, scope, phases, sources
Client: Petrobras
Value: not stated in the source [1]
Finish: production in 2027 [1]
Scope
two FPSOs, +450,000 b/d together, Buzios pre-salt [1]
Phase by phase
FEED · doneEPC award · doneEngineering & procurement · doneConstruction · done · 27 Aug 2026 · christened in Singapore; P-80 and P-82 sailed Sep-Oct 2026 [1] Pre-commissioning & commissioning · in progressStart-up · not started
Sources: 1 worldoil.com · checked 29 Oct 2026
CONFIRMED LARGE OFFSHORE Guyana · FPSO
ExxonMobil Whiptail (Stabroek block, 6th project): 250,000 b/d, FPSO Jaguar
Saipem (subsea) · EnerMech (pre-commissioning subcontract) · FPSO builder not named in the sources we read
FEED FEED: done Award EPC award: done E&P Engineering & procurement: in progress Build Construction: in progress, 13 Jan 2026 Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Construction
Value USD 12.7bn [1]
Workforce not published
Finish 2027 [1]
Client, scope, phases, sources
Client: ExxonMobil Guyana
Value: USD 12.7 billion (project) [1]
Finish: start-up targeted by end of 2027 [1]
Scope
250,000 b/d, FPSO Jaguar, Stabroek block [1]
Phase by phase
FEED · doneEPC award · doneEngineering & procurement · in progressConstruction · in progress · 13 Jan 2026 · subsea installation [1] Pre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 worldoil.com · checked 29 Oct 2026
CONFIRMED MEDIUM Argentina · Fertiliser
Fertil Pampa urea complex, Bahia Blanca: ammonia + 2 urea trains (6,000 t/d)
Tecnimont (MAIRE) (engineering, procurement, commissioning, start-up) · Nextchem (technology, EUR 140m) · SACDE (construction)
FEED FEED: done Award EPC award: done, 20 Jul 2026 E&P Engineering & procurement: in progress Build Construction: not started Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Engineering & procurement
Value EUR 1.3bn [1]
Workforce more than 3,500 direct jobs at peak construction (MAIRE) [1]
Finish completion expected in 41 months… [1]
Client, scope, phases, sources
Client: Fertil Pampa (Pampa Energia)
Value: approximately EUR 1.3 billion, of which EUR 140 million Nextchem technology [1]
Finish: completion expected in 41 months (from July 2026) [1]
Scope
ammonia plant + 2 urea trains, 6,000 t/d (2.1 Mtpa) [1]
Phase by phase
FEED · doneEPC award · done · 20 Jul 2026 [1] Engineering & procurement · in progressConstruction · not startedPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 hydrocarbonprocessing.com · checked 29 Oct 2026
CONFIRMED MEDIUM Vietnam · Refinery
Dung Quat refinery upgrade and expansion, 148,000 to 171,000 b/d
China Chengda Engineering (EPC consortium) · Beijing Petrochemical Engineering (EPC consortium) · Wood (PMC, with Petrovietnam Engineering) · Petrovietnam Engineering (PMC)
FEED FEED: done Award EPC award: done, Aug 2026 E&P Engineering & procurement: in progress Build Construction: unknown Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Engineering & procurement
Value USD 1.5bn [1]
Workforce not published
Finish 2028 [1]
No open adverts linked today
Client, scope, phases, sources
Client: Binh Son Refining and Petrochemical (BSR, Petrovietnam)
Value: USD 1.489bn [1]
Finish: commercial operation 2028 [1]
Scope
refinery from 148,000 to 171,000 b/d [1] EPC duration 37 months [1]
Phase by phase
FEED · doneEPC award · done · Aug 2026 [1] Engineering & procurement · in progressConstruction · unknownPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 ogj.com · checked 29 Oct 2026
CONFIRMED OFFSHORE Brazil · FPSO
Petrobras Buzios 11: FPSO P-83 (225,000 b/d)
Seatrium (FPSO newbuild)
FEED FEED: done Award EPC award: done E&P Engineering & procurement: done Build Construction: in progress Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Construction
Value not published
Workforce not published
Finish 2027 [1]
No open adverts linked today
Client, scope, phases, sources
Client: Petrobras (88.99%) with Buzios partners
Value: not published
Finish: start-up 2027 (Petrobras 2Q26 report) [1]
Scope
FPSO, 225,000 b/d oil, Buzios field, Santos Basin pre-salt; start-up 2027 [1] in Seatrium's order book with P-78, P-80 and P-82 (Petrobras FPSO newbuilds) [2]
Phase by phase
FEED · doneEPC award · doneEngineering & procurement · doneConstruction · in progressPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 sec.gov 2 links.sgx.com · checked 29 Oct 2026
CONFIRMED LARGE OFFSHORE Brazil · FPSO
Petrobras Atapu 2 and Sepia 2: FPSOs P-84 and P-85 (225,000 b/d each)
Seatrium (FPSO newbuild, both units)
FEED FEED: done Award EPC award: done, 25 May 2024 E&P Engineering & procurement: in progress Build Construction: in progress, 2025 Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Construction
Value SGD 11bn [1]
Workforce not published
Finish 2030 [2]
No open adverts linked today
Client, scope, phases, sources
Client: Petrobras, operator of the Atapu and Sepia consortia
Value: approximately SGD 11 billion (both FPSOs) [1]
Finish: P-84 start-up 2029, P-85 2030 (Petrobras 2Q26) [2]
Scope
two FPSOs, 225,000 b/d oil and 10 million m3/d gas each; all-electric, zero routine flaring [1] modules (60,000 t) built in Seatrium yards in Brazil, China and Singapore; integration in Singapore [1] start-up: P-84 (Atapu) 2029, P-85 (Sepia) 2030 [2]
Phase by phase
FEED · doneEPC award · done · 25 May 2024 · contracts signed [1] Engineering & procurement · in progressConstruction · in progress · 2025 · construction to start Q1 2025 (Seatrium) [1] Pre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 links.sgx.com 2 sec.gov · checked 29 Oct 2026
CONFIRMED OFFSHORE Brazil · FPSO
Petrobras SEAP I and II (Sergipe-Alagoas deepwater): FPSOs P-81 and P-87, 120,000 b/d each
SBM Offshore (design, build and operate both FPSOs (BOT))
FEED FEED: done Award EPC award: done, 29 May 2026 E&P Engineering & procurement: in progress Build Construction: not started Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Engineering & procurement
Value not published
Workforce not published
Finish 2031 [1]
No open adverts linked today
Client, scope, phases, sources
Client: Petrobras-led consortia
Value: not published
Finish: SEAP-II delivery 2030, SEAP-I 2031 [1]
Scope
two Fast4Ward FPSOs, 120,000 b/d oil each, about 2,500 m water depth [1] SEAP-II delivery 2030, SEAP-I 2031; SBM operates for an initial 6.5 years [1]
Phase by phase
FEED · doneEPC award · done · 29 May 2026 · contracts signed [1] Engineering & procurement · in progressConstruction · not startedPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 worldoil.com 2 sec.gov · checked 29 Oct 2026
CONFIRMED LARGE OFFSHORE Brazil · FPSO
Equinor Raia (BM-C-33), Campos Basin pre-salt: gas FPSO, 16 million m3/d
MODEC (FPSO, lump-sum turnkey EPCI) · TechnipFMC (subsea EPCI (SURF))
FEED FEED: done Award EPC award: done, 10 May 2023 E&P Engineering & procurement: in progress Build Construction: in progress Comm. Pre-commissioning & commissioning: in progress, 1 Jul 2026 Start Start-up: not started
Now: Pre-commissioning & commissioning
Value USD 9bn [1]
Workforce not published
Finish 2028 [2]
No open adverts linked today
Client, scope, phases, sources
Client: Equinor (35%, operator), Repsol Sinopec Brasil (35%), Petrobras (30%)
Value: about USD 9 billion (project investment) [1]
Finish: operations from 2028 [2]
Scope
FPSO with about 126,000 b/d of oil/condensate and 16 million m3/d gas export [1] FPSO accommodation commissioning completed July 2026 [2]
Phase by phase
FEED · doneEPC award · done · 10 May 2023 [1] Engineering & procurement · in progressConstruction · in progressPre-commissioning & commissioning · in progress · 1 Jul 2026 · accommodation modules commissioned [2] Start-up · not started
Sources: 1 equinor.com 2 tagdlaw.com.br · checked 29 Oct 2026
ON THE RADAR OFFSHORE Brazil · FPSO
Petrobras Albacora revitalisation: FPSO P-88 (120,000 b/d), BOT tender
Yinson (lowest bidder, USD 2.29 bn; award not confirmed)
FEED FEED: done Award EPC award: unknown E&P Engineering & procurement: unknown Build Construction: not started Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Last step done: FEED
Value lowest bid USD 2.29 billion… [1]
Workforce not published
Finish first oil after 2031 [1]
No open adverts linked today
Client, scope, phases, sources
Client: Petrobras
Value: lowest bid USD 2.29 billion (Yinson); contract not signed [1]
Scope
FPSO, 120,000 b/d oil and up to 4.3 million m3/d gas, build-operate-transfer [1] bids: Yinson 2.29, COOEC 2.84, Shapoorji 2.9, MISC 3.05, BW 3.19 (USD bn) [1]
Phase by phase
FEED · doneEPC award · unknownEngineering & procurement · unknownConstruction · not startedPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 agenciainfra.com · checked 29 Oct 2026
CONFIRMED LARGE OFFSHORE Guyana · FPSO
ExxonMobil Uaru (Stabroek, 5th project): FPSO Errea Wittu, 250,000 b/d
MODEC (FPSO Errea Wittu)
FEED FEED: done Award EPC award: done E&P Engineering & procurement: done Build Construction: done, 21 Aug 2026 Comm. Pre-commissioning & commissioning: in progress Start Start-up: not started
Now: Pre-commissioning & commissioning
Value USD 12.7bn [1]
Workforce not published
Finish first oil expected in Q4 2026 [2]
Client, scope, phases, sources
Client: ExxonMobil Guyana (45%, operator), Chevron (30%), CNOOC (25%)
Value: USD 12.7 billion (project) [1]
Scope
FPSO Errea Wittu, up to 250,000 b/d, about 2 million bbl storage [1] FPSO arrived in Guyana in August 2026; final preparations for start-up [2]
Phase by phase
FEED · doneEPC award · doneEngineering & procurement · doneConstruction · done · 21 Aug 2026 · FPSO arrived in Guyanese waters [1] Pre-commissioning & commissioning · in progressStart-up · not started
Sources: 1 energynow.tt 2 industrialinfo.com · checked 29 Oct 2026
CONFIRMED LARGE OFFSHORE Guyana · FPSO
ExxonMobil Hammerhead (Stabroek, 7th project): FPSO 150,000 b/d
MODEC (FPSO)
FEED FEED: done Award EPC award: done, 24 Sep 2025 E&P Engineering & procurement: done Build Construction: in progress Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Construction
Value USD 6.8bn [1]
Workforce not published
Finish 2029 [1]
No open adverts linked today
Client, scope, phases, sources
Client: ExxonMobil Guyana (45%, operator), Hess (30%), CNOOC (25%)
Value: USD 6.8 billion (field development) [1]
Finish: first oil 2029 [1]
Scope
FPSO 150,000 b/d, 1.6 million bbl storage, 18 production and injection wells [1] construction under way (Oct 2026) [2]
Phase by phase
FEED · doneEPC award · done · 24 Sep 2025 · FID [1] Engineering & procurement · doneConstruction · in progressPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 jpt.spe.org 2 industrialinfo.com · checked 29 Oct 2026
ON THE RADAR OFFSHORE Guyana · FPSO
ExxonMobil Longtail (Stabroek, 8th project): gas-condensate FPSO, approval pending
Contractors: FPSO contractor not announced
FEED FEED: in progress Award EPC award: unknown E&P Engineering & procurement: unknown Build Construction: not started Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: FEED
Value not published
Workforce not published
Finish not published
No open adverts linked today
Client, scope, phases, sources
Client: ExxonMobil Guyana (operator)
Value: not published
Scope
development of the Longtail, Tripletail and Turbot discoveries; gas and condensate with reinjection [1] development plan submitted March 2026; approval targeted before end-2026 [1]
Phase by phase
FEED · in progressEPC award · unknownEngineering & procurement · unknownConstruction · not startedPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 industrialinfo.com · checked 29 Oct 2026
REPORTED OFFSHORE Saudi Arabia · Offshore platform
Aramco Marjan offshore development: CRPO 166 structures (EPCI)
McDermott (EPCI, single-sourced change order)
FEED FEED: done Award EPC award: done E&P Engineering & procurement: done Build Construction: done Comm. Pre-commissioning & commissioning: in progress Start Start-up: unknown
Now: Pre-commissioning & commissioning
Value not published
Workforce not published
Finish not published
No open adverts linked today
Client, scope, phases, sources
Client: Saudi Aramco
Value: not published
Scope
EPCI of structures carved out of the USD 15 bn Marjan offshore development [1] McDermott nearing completion of the EPCI works (Jan 2026) [1]
Phase by phase
FEED · doneEPC award · doneEngineering & procurement · doneConstruction · donePre-commissioning & commissioning · in progressStart-up · unknown
Sources: 1 guest.meed.com · checked 29 Oct 2026
CONFIRMED MEDIUM OFFSHORE Saudi Arabia · Pipeline
Aramco Safaniya: 48-inch trunkline, 65 km offshore + 12 km onshore (CRPO 156)
Saipem (EPCI under the long-term agreement)
FEED FEED: done Award EPC award: done, 25 Feb 2026 E&P Engineering & procurement: in progress Build Construction: unknown Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Engineering & procurement
Value USD 500m [1]
Workforce not published
Finish not published
No open adverts linked today
Client, scope, phases, sources
Client: Saudi Aramco
Value: approximately USD 500 million [1]
Scope
48-inch trunkline (about 65 km offshore, 12 km onshore) and subsea facilities, Safaniya field [1] fabrication at Saipem's Dammam yard; offshore work by Saipem vessels in the region [1]
Phase by phase
FEED · doneEPC award · done · 25 Feb 2026 [1] Engineering & procurement · in progressConstruction · unknownPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 pgjonline.com · checked 29 Oct 2026
REPORTED LARGE OFFSHORE Saudi Arabia · Offshore platform
Aramco Zuluf offshore expansion: CRPOs 145-148 (jackets, decks, pipelines)
Larsen & Toubro Energy Hydrocarbon (CRPO 145 (likely award)) · Subsea7 (CRPOs 146 and 148 (frontrunner)) · Lamprell (CRPO 147 (frontrunner))
FEED FEED: done Award EPC award: in progress E&P Engineering & procurement: unknown Build Construction: unknown Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: EPC award
Value about USD 5.8 billion for the… [1]
Workforce not published
Finish not published
No open adverts linked today
Client, scope, phases, sources
Client: Saudi Aramco
Value: about USD 5.8 billion for the four packages (MEED estimate) [1]
Scope
29 slipover jackets and decks, tie-in platforms, subsea cables and about 110 km of pipelines incl. a 48-inch trunkline [1] L&T announced an 'ultra-mega' offshore order (above INR 150 bn) in July 2025, likely CRPO 145 [2]
Phase by phase
FEED · doneEPC award · in progressEngineering & procurement · unknownConstruction · unknownPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 guest.meed.com 2 guest.meed.com · checked 29 Oct 2026
REPORTED OFFSHORE Saudi Arabia · Offshore platform
Aramco Arabiyah, Hasbah and Karan: four offshore gas jackets (CRPO 161)
COOEC (China Offshore Oil Engineering) (selected; formal award pending)
FEED FEED: done Award EPC award: in progress E&P Engineering & procurement: not started Build Construction: not started Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: EPC award
Value not published
Workforce not published
Finish not published
No open adverts linked today
Client, scope, phases, sources
Client: Saudi Aramco
Value: not published
Scope
EPCI of four gas jackets at the Arabiyah, Hasbah and Karan fields [1]
Phase by phase
FEED · doneEPC award · in progressEngineering & procurement · not startedConstruction · not startedPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 guest.meed.com · checked 29 Oct 2026
CONFIRMED LARGE OFFSHORE Qatar · Gas compression
QatarEnergy LNG North Field Production Sustainability COMP5: two offshore compression complexes
Saipem (EPCI, share about USD 3.1 bn) · COOEC (China Offshore Oil Engineering) (partner)
FEED FEED: done Award EPC award: done, 22 Dec 2025 E&P Engineering & procurement: in progress Build Construction: not started Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Engineering & procurement
Value USD 4bn [1]
Workforce not published
Finish contract duration about five… [1]
No open adverts linked today
Client, scope, phases, sources
Client: QatarEnergy LNG
Value: about USD 4 billion (Saipem share about USD 3.1 billion) [1]
Finish: contract duration about five years; installation 2029 and 2030 [1]
Scope
two complexes: compression platform, living quarters, flare platform and bridges, about 68,000 t each [1] offshore installation 2029-2030 by Saipem's De He; COMP2 and COMP3 already in execution, COMP4 to Technip Energies [1]
Phase by phase
FEED · doneEPC award · done · 22 Dec 2025 [1] Engineering & procurement · in progressConstruction · not startedPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 offshore-technology.com · checked 29 Oct 2026
CONFIRMED OFFSHORE Australia · Offshore platform
Woodside Scarborough: floating production unit + Pluto LNG Train 2 (5 Mtpa)
McDermott (FPU design, fabrication, integration, installation) · Bechtel (Pluto Train 2 EPC)
FEED FEED: done Award EPC award: done E&P Engineering & procurement: done Build Construction: done, 13 Jan 2026 Comm. Pre-commissioning & commissioning: in progress Start Start-up: not started
Now: Pre-commissioning & commissioning · 91% complete (Jan 2026) [1]
Value not published
Workforce not published
Finish 2026 [1]
No open adverts linked today
Client, scope, phases, sources
Client: Woodside (operator)
Value: not published
Finish: first LNG targeted for the second half of 2026 [1]
Scope
semi-submersible FPU, about 30,000 t topsides (QMW yard, Qingdao) + 37,000 t hull, up to 1.8 Bcf/d [1] about 433 km pipeline to Pluto LNG Train 2 (about 5 Mtpa) [1]
Phase by phase
Progress: 91% complete (Woodside, January 2026) [1]
FEED · doneEPC award · doneEngineering & procurement · doneConstruction · done · 13 Jan 2026 · FPU on location [1] Pre-commissioning & commissioning · in progressStart-up · not started
Sources: 1 jpt.spe.org · checked 29 Oct 2026
CONFIRMED LARGE OFFSHORE Mexico · Offshore platform
Woodside-Pemex Trion (Mexican Gulf deepwater): FPU 100,000 b/d + FSO
HD Hyundai Heavy Industries (FPU EPC, Ulsan) · SBM Offshore (FPU and FSO installation)
FEED FEED: done Award EPC award: done E&P Engineering & procurement: done Build Construction: in progress, 13 Nov 2024 Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Construction
Value USD 7.2bn [1]
Workforce not published
Finish 2028 [2]
No open adverts linked today
Client, scope, phases, sources
Client: Woodside (60%, operator), Pemex (40%)
Value: estimated USD 7.2 billion (investment) [1]
Finish: first oil targeted for 2028 [2]
Scope
semi-submersible FPU 100,000 b/d linked to a 950,000 bbl FSO [1] FPU steel cut in Ulsan in November 2024 [2]
Phase by phase
FEED · doneEPC award · doneEngineering & procurement · doneConstruction · in progress · 13 Nov 2024 · FPU steel cutting [2] Pre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 jpt.spe.org 2 energy-pedia.com · checked 29 Oct 2026
CONFIRMED OFFSHORE United States · Offshore platform
bp Kaskida (US Gulf, Paleogene): FPU 80,000 b/d
Seatrium (FPU EPC and onshore commissioning)
FEED FEED: done Award EPC award: done, 24 Dec 2024 E&P Engineering & procurement: in progress Build Construction: unknown Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Engineering & procurement
Value not published
Workforce not published
Finish not published
No open adverts linked today
Client, scope, phases, sources
Client: bp
Value: not published
Scope
semi-submersible FPU, 80,000 b/d from six wells in phase 1 [1]
Phase by phase
FEED · doneEPC award · done · 24 Dec 2024 [1] Engineering & procurement · in progressConstruction · unknownPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 bairdmaritime.com · checked 29 Oct 2026
CONFIRMED OFFSHORE United Kingdom · FPSO
Rosebank (West of Shetland, UK): FPSO Rosebank (ex-Knarr), hook-up and commissioning
Contractors: contractors not named in the source read today
FEED FEED: done Award EPC award: done E&P Engineering & procurement: done Build Construction: done, Jun 2026 Comm. Pre-commissioning & commissioning: in progress Start Start-up: not started
Now: Pre-commissioning & commissioning
Value not published
Workforce not published
Finish start-up targeted for the first… [1]
No open adverts linked today
Client, scope, phases, sources
Client: Adura (Equinor-Shell JV, operator) and Ithaca Energy
Value: not published
Finish: start-up targeted for the first half of 2027 [1]
Scope
FPSO Rosebank (formerly on Knarr, Norway) moored on location June 2026; hook-up and commissioning under way [1] start-up subject to final UK government approval, expected by end-2026 [1]
Phase by phase
FEED · doneEPC award · doneEngineering & procurement · doneConstruction · done · Jun 2026 · FPSO moored on location [1] Pre-commissioning & commissioning · in progressStart-up · not started
Sources: 1 offshore-mag.com · checked 29 Oct 2026
ON THE RADAR OFFSHORE Namibia · FPSO
TotalEnergies Venus (Block 2913B, Orange Basin): FPSO 150,000-200,000 b/d, pre-FID
Hanwha Ocean (FPSO bidder) · SBM Offshore (FPSO bidder)
FEED FEED: done Award EPC award: unknown E&P Engineering & procurement: unknown Build Construction: not started Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Last step done: FEED
Value initial phase up to USD 10… [1]
Workforce not published
Finish 2030 [1]
No open adverts linked today
Client, scope, phases, sources
Client: TotalEnergies (operator)
Value: initial phase up to USD 10 billion (industry estimate) [1]
Finish: first oil targeted for 2030 [1]
Scope
FPSO for 150,000-200,000 b/d; subsea package at least USD 2.5 bn [1]
Phase by phase
FEED · doneEPC award · unknownEngineering & procurement · unknownConstruction · not startedPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 republikein.com.na · checked 29 Oct 2026
CONFIRMED LARGE OFFSHORE Angola · FPSO
Azule Energy Greater PAJ (Blocks 31 and 31/21): new FPSO 95,000 b/d
CIMC Raffles (FPSO, Haiyang yard) · Saipem (transport and installation) · TechnipFMC (risers and flowlines) · Baker Hughes (subsea production systems) · OneSubsea (umbilicals) · Vallourec (rigid pipes)
FEED FEED: done Award EPC award: done, 23 Jun 2026 E&P Engineering & procurement: done Build Construction: in progress Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Construction
Value USD 5.1bn [1]
Workforce not published
Finish 2029 [1]
No open adverts linked today
Client, scope, phases, sources
Client: Azule Energy (bp-Eni JV)
Value: USD 5.1 billion (FID investment) [1]
Finish: first oil expected in the first half of 2029 [1]
Scope
new FPSO 95,000 b/d linking Block 31 production with Block 31/21 discoveries [1] FPSO topsides steel cut at CIMC Raffles Haiyang, July 2026 [1]
Phase by phase
FEED · doneEPC award · done · 23 Jun 2026 · FID and six main contracts [1] Engineering & procurement · doneConstruction · in progressPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 oedigital.com · checked 29 Oct 2026
CONFIRMED OFFSHORE China · Fabrication yard
Fabrication yard: Qingdao McDermott Wuchuan (QMW), Qingdao
McDermott (JV yard)
FEED FEED: unknown Award EPC award: unknown E&P Engineering & procurement: unknown Build Construction: in progress Comm. Pre-commissioning & commissioning: in progress Start Start-up: unknown
Now: Pre-commissioning & commissioning
Value not published
Workforce not published
Finish not published
Client, scope, phases, sources
Client: McDermott-Wuchuan joint venture (yard owner)
Value: not published
Scope
60 ha yard, 300 m skidway (50,000 t load-out), up to 90,000 t a year [1] now fabricating: jacket and topside for ADNOC Umm Shaif package 4 (awarded Aug 2026) [2] built the Scarborough FPU topsides (about 30,000 t) [3]
Phase by phase
FEED · unknownEPC award · unknownEngineering & procurement · unknownConstruction · in progressPre-commissioning & commissioning · in progressStart-up · unknown
Sources: 1 mcdermott.com 2 worldoil.com 3 jpt.spe.org · checked 29 Oct 2026
CONFIRMED OFFSHORE Indonesia · Fabrication yard
Fabrication yard: McDermott Batam (Indonesia)
McDermott (yard)
FEED FEED: unknown Award EPC award: unknown E&P Engineering & procurement: unknown Build Construction: unknown Comm. Pre-commissioning & commissioning: unknown Start Start-up: unknown
Phases not published
Value not published
Workforce not published
Finish not published
Client, scope, phases, sources
Client: McDermott (yard owner)
Value: not published
Scope
120 ha yard, 817 m quay, up to 60,000 t a year: fixed and floating offshore structures, LNG modules, subsea structures [1]
Phase by phase
FEED · unknownEPC award · unknownEngineering & procurement · unknownConstruction · unknownPre-commissioning & commissioning · unknownStart-up · unknown
Sources: 1 mcdermott.com · checked 29 Oct 2026
CONFIRMED OFFSHORE UAE · Fabrication yard
Fabrication yard: McDermott Jebel Ali (Dubai)
McDermott (yard)
FEED FEED: unknown Award EPC award: unknown E&P Engineering & procurement: unknown Build Construction: unknown Comm. Pre-commissioning & commissioning: unknown Start Start-up: unknown
Phases not published
Value not published
Workforce not published
Finish not published
Client, scope, phases, sources
Client: McDermott (yard owner)
Value: not published
Scope
53 ha yard, up to 50,000 t a year: pipe fabrication, cladding, girders for the Middle East and India [1]
Phase by phase
FEED · unknownEPC award · unknownEngineering & procurement · unknownConstruction · unknownPre-commissioning & commissioning · unknownStart-up · unknown
Sources: 1 mcdermott.com · checked 29 Oct 2026
REPORTED OFFSHORE UAE · Fabrication yard
Fabrication yard: NMDC Energy Mussafah (Abu Dhabi)
NMDC Energy (yard)
FEED FEED: unknown Award EPC award: unknown E&P Engineering & procurement: unknown Build Construction: unknown Comm. Pre-commissioning & commissioning: unknown Start Start-up: unknown
Phases not published
Value not published
Workforce not published
Finish not published
No open adverts linked today
Client, scope, phases, sources
Client: NMDC Energy (yard owner)
Value: not published
Scope
fabricated the first jackets of ADNOC's Hail and Ghasha offshore gas project (load-out July 2025) [1]
Phase by phase
FEED · unknownEPC award · unknownEngineering & procurement · unknownConstruction · unknownPre-commissioning & commissioning · unknownStart-up · unknown
Sources: 1 meed.com · checked 29 Oct 2026
CONFIRMED OFFSHORE Saudi Arabia · Fabrication yard
Fabrication yard: NMDC Energy Ras Al Khair (Saudi Arabia)
NMDC Energy (yard)
FEED FEED: unknown Award EPC award: unknown E&P Engineering & procurement: unknown Build Construction: unknown Comm. Pre-commissioning & commissioning: unknown Start Start-up: unknown
Phases not published
Value AED 200m [1]
Workforce more than 1,800 experienced employees moved from Abu Dhabi to the yard [1]
Finish not published
No open adverts linked today
Client, scope, phases, sources
Client: NMDC Energy (yard owner)
Value: AED 200 million (yard investment) [1]
Scope
400,000 m2 yard; nine offshore jackets for Aramco in production at opening [1]
Phase by phase
FEED · unknownEPC award · unknownEngineering & procurement · unknownConstruction · unknownPre-commissioning & commissioning · unknownStart-up · unknown
Sources: 1 nmdc-group.com · checked 29 Oct 2026
CONFIRMED OFFSHORE India · Fabrication yard
Fabrication yard: L&T Kattupalli modular yard (near Chennai)
Larsen & Toubro (yard)
FEED FEED: unknown Award EPC award: unknown E&P Engineering & procurement: unknown Build Construction: unknown Comm. Pre-commissioning & commissioning: unknown Start Start-up: unknown
Phases not published
Value not published
Workforce not published
Finish not published
No open adverts linked today
Client, scope, phases, sources
Client: Larsen & Toubro (yard owner)
Value: not published
Scope
delivered 110 modules (about 64,000 t) for Project CERES, Western Australia (Sep 2026) [1] L&T modular capacity about 200,000 t a year across Kattupalli, Hazira and Oman [1]
Phase by phase
FEED · unknownEPC award · unknownEngineering & procurement · unknownConstruction · unknownPre-commissioning & commissioning · unknownStart-up · unknown
Sources: 1 kotakneo.com · checked 29 Oct 2026
CONFIRMED OFFSHORE Singapore · Fabrication yard
Fabrication yard: Seatrium Tuas Boulevard (Singapore) and Brazil yards
Seatrium (yard)
FEED FEED: unknown Award EPC award: unknown E&P Engineering & procurement: unknown Build Construction: unknown Comm. Pre-commissioning & commissioning: unknown Start Start-up: unknown
Phases not published
Value not published
Workforce not published
Finish not published
No open adverts linked today
Client, scope, phases, sources
Client: Seatrium (yard owner)
Value: not published
Scope
P-80 and P-82 FPSOs completed at Tuas Boulevard (2026); modules from BrasFELS and Aracruz (Brazil) [1] P-84 and P-85 integration in Singapore, modules from Brazil, China and Singapore [2] bp Kaskida FPU (EPC) [3]
Phase by phase
FEED · unknownEPC award · unknownEngineering & procurement · unknownConstruction · unknownPre-commissioning & commissioning · unknownStart-up · unknown
Sources: 1 ogj.com 2 links.sgx.com 3 bairdmaritime.com · checked 29 Oct 2026
CONFIRMED OFFSHORE China · Fabrication yard
Fabrication yard: COOEC Qingdao base
COOEC (China Offshore Oil Engineering) (yard)
FEED FEED: unknown Award EPC award: unknown E&P Engineering & procurement: unknown Build Construction: unknown Comm. Pre-commissioning & commissioning: unknown Start Start-up: unknown
Phases not published
Value not published
Workforce not published
Finish not published
No open adverts linked today
Client, scope, phases, sources
Client: COOEC (yard owner)
Value: not published
Scope
fabrication for QatarEnergy Bul Hanine (BH-EPIC1 and 2, more than 130,000 t of steel) started 15 Sep 2026 [1]
Phase by phase
FEED · unknownEPC award · unknownEngineering & procurement · unknownConstruction · unknownPre-commissioning & commissioning · unknownStart-up · unknown
Sources: 1 equalocean.com · checked 29 Oct 2026
CONFIRMED OFFSHORE Saudi Arabia · Fabrication yard
Fabrication yard: Saipem Taqa Al-Rushaid Fabricators (Dammam)
Saipem (yard)
FEED FEED: unknown Award EPC award: unknown E&P Engineering & procurement: unknown Build Construction: unknown Comm. Pre-commissioning & commissioning: unknown Start Start-up: unknown
Phases not published
Value not published
Workforce not published
Finish not published
No open adverts linked today
Client, scope, phases, sources
Client: Saipem Taqa Al-Rushaid Fabricators (yard owner)
Value: not published
Scope
fabrication for the Aramco Safaniya 48-inch trunkline contract (Feb 2026) [1]
Phase by phase
FEED · unknownEPC award · unknownEngineering & procurement · unknownConstruction · unknownPre-commissioning & commissioning · unknownStart-up · unknown
Sources: 1 pgjonline.com · checked 29 Oct 2026
CONFIRMED OFFSHORE Nigeria · Fabrication yard
Fabrication yard: Dorman Long Engineering, Naval Dockyard (Lagos)
Dorman Long Engineering (yard)
FEED FEED: unknown Award EPC award: unknown E&P Engineering & procurement: unknown Build Construction: unknown Comm. Pre-commissioning & commissioning: unknown Start Start-up: unknown
Phases not published
Value not published
Workforce not published
Finish not published
No open adverts linked today
Client, scope, phases, sources
Client: Dorman Long Engineering (yard owner)
Value: not published
Scope
built the 1,300 t Madu conductor support platform at the Nigerian Naval Dockyard; modular separators for NAOC Irri [1]
Phase by phase
FEED · unknownEPC award · unknownEngineering & procurement · unknownConstruction · unknownPre-commissioning & commissioning · unknownStart-up · unknown
Sources: 1 techeconomy.ng · checked 29 Oct 2026
CONFIRMED Algeria · Onshore oil field
Sonatrach-PTTEP Hassi Bir Rekaiz phase 2: crude processing unit 31,500 b/d
Petrojet (EPC consortium) · Arkad (EPC consortium)
FEED FEED: done Award EPC award: done, 5 May 2026 E&P Engineering & procurement: in progress Build Construction: unknown Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Engineering & procurement
Value more than USD 1 billion (EPC… [1]
Workforce not published
Finish commissioning within 39 months [1]
No open adverts linked today
Client, scope, phases, sources
Client: Sonatrach and PTTEP (field partners)
Value: more than USD 1 billion (EPC contract) [1]
Scope
new crude processing unit 31,500 b/d with associated gas and produced-water treatment [1]
Phase by phase
FEED · doneEPC award · done · 5 May 2026 · EPC contract signed [1] Engineering & procurement · in progressConstruction · unknownPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 financialafrik.com · checked 29 Oct 2026
CONFIRMED LARGE Algeria · Refinery
Sonatrach Hassi Messaoud (Haoud El-Hamra) grassroots refinery, 5 Mtpa
Tecnicas Reunidas (EPC, 51%) · Sinopec (EPC, 49%) · Shaanxi Huajian Engineering (erection subcontract, package PK4 (CCR))
FEED FEED: done Award EPC award: done E&P Engineering & procurement: in progress Build Construction: in progress, 24 Feb 2025 Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Construction
Value USD 4bn [1]
Workforce EPC Radar estimate est. 9,600-44,300 at peak how?
Finish first refining units from… [1]
No open adverts linked today
Client, scope, phases, sources
Client: Sonatrach
Value: about USD 4 billion (EPC contract) [1]
Finish: first refining units from end-2027; 65-month construction [1]
Workforce estimate (low confidence): EPC Radar estimate from 2 published refinery, petrochemical and fertiliser plants projects in this tracker, 2.4-11.1 workers per USD million of declared value (id-rdmp-balikpapan, ar-fertil-pampa), applied to contract value: about USD 4,000 m
Scope
refinery of about 5 million t/yr of crude; CCR unit 1.35 Mt/yr in package PK4 [1] first stone laid 24 Feb 2025; construction period 65 months [1]
Phase by phase
FEED · doneEPC award · doneEngineering & procurement · in progressConstruction · in progress · 24 Feb 2025 · first stone [1] Pre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 algerie-eco.com · checked 29 Oct 2026
CONFIRMED LARGE Algeria · Gas compression
Sonatrach Hassi R'Mel boosting phase III: three compression stations
Baker Hughes - Nuovo Pignone International (EPC consortium) · Tecnimont (EPC consortium)
FEED FEED: done Award EPC award: done, 23 May 2024 E&P Engineering & procurement: done Build Construction: in progress Comm. Pre-commissioning & commissioning: in progress Start Start-up: not started
Now: Pre-commissioning & commissioning · 51% complete (Jul 2025) [2]
Value USD 2.3bn [1]
Workforce not published
Finish Apr 2027 [2]
No open adverts linked today
Client, scope, phases, sources
Client: Sonatrach
Value: USD 2.3 billion (EPC contract) [1]
Finish: compression units commissioning Oct 2026, Jan 2027 and Apr 2027 [2]
Scope
three gas-boosting stations, 20 compression trains, upgrade of 300+ km of gathering lines; about 188 million m3/d [1]
Phase by phase
Progress: 51% complete (Sonatrach, July 2025) [2]
FEED · doneEPC award · done · 23 May 2024 [2] Engineering & procurement · doneConstruction · in progressPre-commissioning & commissioning · in progressStart-up · not started
Sources: 1 offshore-technology.com 2 sonatrach.com · checked 29 Oct 2026
CONFIRMED Algeria · Fertiliser
Sonatrach Projet Phosphates Integre, phase 1: Bled El Hadba mine + Oued El-Kebrit fertiliser units
Saipem (EPC phase 1 (limited notice to proceed))
FEED FEED: done Award EPC award: done, 12 Aug 2026 E&P Engineering & procurement: in progress Build Construction: not started Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Engineering & procurement
Value EUR 500m [1]
Workforce not published
Finish not published
No open adverts linked today
Client, scope, phases, sources
Client: Sonatrach
Value: about EUR 500 million (limited notice to proceed) [1]
Scope
phosphate mining infrastructure at Bled El Hadba; fertiliser process units, utilities and logistics at Oued El-Kebrit [1]
Phase by phase
FEED · doneEPC award · done · 12 Aug 2026 · limited notice to proceed [1] Engineering & procurement · in progressConstruction · not startedPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 chemxplore.com · checked 29 Oct 2026
CONFIRMED Egypt · Gas processing
Eni/Agiba Meleiha Phase 2 (Western Desert): gas plant 100 MMscfd + 200 km pipelines
Petrojet (main EPC contract)
FEED FEED: done Award EPC award: done E&P Engineering & procurement: done Build Construction: done Comm. Pre-commissioning & commissioning: in progress Start Start-up: in progress, 21 Oct 2026
Now: Start-up
Value not published
Workforce not published
Finish not published
No open adverts linked today
Client, scope, phases, sources
Client: Agiba Petroleum (Eni-EGPC JV)
Value: not published
Scope
gas processing up to 100 MMscfd, sweetening and recovery units, 200 km of pipeline, 28 wells [1] Eni started bringing the plant online (Oct 2026) [1]
Phase by phase
FEED · doneEPC award · doneEngineering & procurement · doneConstruction · donePre-commissioning & commissioning · in progressStart-up · in progress · 21 Oct 2026 · start-up under way [1]
Sources: 1 guest.meed.com · checked 29 Oct 2026
CONFIRMED OFFSHORE Egypt · Subsea
Burullus West Delta Deep Marine: subsea umbilical and 2 km TCP flowline replacement
Oceaneering (integrated transport, installation and commissioning)
FEED FEED: done Award EPC award: done, 21 May 2026 E&P Engineering & procurement: in progress Build Construction: in progress Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Construction
Value not published
Workforce not published
Finish not published
No open adverts linked today
Client, scope, phases, sources
Client: Burullus Gas Company
Value: not published
Scope
refurbished subsea umbilical + 2,000 m thermoplastic composite flowline, ROV and survey support [1]
Phase by phase
FEED · doneEPC award · done · 21 May 2026 [1] Engineering & procurement · in progressConstruction · in progressPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 worldoil.com · checked 29 Oct 2026
CONFIRMED LARGE OFFSHORE Libya · Offshore platform
Mellitah Complex Expansion & CO2 Management (Structures A & E, NC 41 offshore)
Rosetti Marino (offshore EPC consortium, 33%) · Kerry Project Logistics (offshore EPC consortium) · Gruppo Antonini (offshore EPC consortium)
FEED FEED: done Award EPC award: done E&P Engineering & procurement: in progress Build Construction: in progress Comm. Pre-commissioning & commissioning: unknown Start Start-up: unknown
Now: Construction
Value USD 8bn [1]
Workforce not published
Finish not published
No open adverts linked today
Client, scope, phases, sources
Client: Mellitah Oil & Gas (NOC-Eni JV)
Value: about USD 8 billion (project); offshore EPC EUR 1.2 billion (June 2024) [1]
Scope
wellhead platform A (96 m water) and production platform E (220 m), Sabratha modifications, onshore Mellitah upgrades [1] EPIC tender for subsea pipelines (about USD 3 bn): prequalification due 5 Nov 2026 [1]
Phase by phase
FEED · doneEPC award · doneEngineering & procurement · in progressConstruction · in progressPre-commissioning & commissioning · unknownStart-up · unknown
Sources: 1 guest.meed.com · checked 29 Oct 2026
ON THE RADAR MEDIUM OFFSHORE Morocco · Terminal & storage
Morocco Nador West Med: FSRU LNG terminal + national gas pipeline corridor (tenders)
Contractors: tenders open; no award published
FEED FEED: unknown Award EPC award: not started E&P Engineering & procurement: not started Build Construction: not started Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Before the EPC award
Value about USD 954 million first phase… [1]
Workforce not published
Finish 2027 [1]
No open adverts linked today
Client, scope, phases, sources
Client: Ministry of Energy Transition (Morocco)
Value: about USD 954 million first phase (FSRU about USD 273 m + pipelines about USD 681 m, estimates) [1]
Finish: terminal service target 2027 [1]
Scope
FSRU lease at Nador West Med connected to the GME pipeline; PPP pipeline to Kenitra and Mohammedia [1]
Phase by phase
FEED · unknownEPC award · not startedEngineering & procurement · not startedConstruction · not startedPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 italpress.com · checked 29 Oct 2026
CONFIRMED Sweden · CCS / BECCS
Stockholm Exergi BECCS, Vartan: 800,000 t/yr CO2 capture
Saipem (design, procurement and construction) · Skanska (ground, foundations and quay, phase 2)
FEED FEED: done Award EPC award: done E&P Engineering & procurement: in progress Build Construction: in progress, Apr 2025 Comm. Pre-commissioning & commissioning: in progress Start Start-up: not started
Now: Pre-commissioning & commissioning
Value SEK 990m [1]
Workforce not published
Finish 2028 [2]
No open adverts linked today
Client, scope, phases, sources
Client: Stockholm Exergi
Value: about SEK 990 million (Skanska phase 2 groundworks) [1]
Finish: operations planned for 2028 [2]
Scope
capture up to 800,000 t/yr of biogenic CO2 at the Vartan CHP plant [2] Skanska groundworks started April 2025, completion during 2028 [1]
Phase by phase
FEED · doneEPC award · doneEngineering & procurement · in progressConstruction · in progress · Apr 2025 · groundworks start [1] Pre-commissioning & commissioning · in progressStart-up · not started
Sources: 1 skanska.com 2 stockholmexergi.se · checked 29 Oct 2026
CONFIRMED Denmark · CCS / BECCS
Orsted Kalundborg CO2 Hub BECCS (Asnaes + Avedore): 430,000 t/yr
Aker Carbon Capture (five Just Catch capture units (2023 plan))
FEED FEED: done Award EPC award: done E&P Engineering & procurement: done Build Construction: in progress, 25 Feb 2025 Comm. Pre-commissioning & commissioning: unknown Start Start-up: unknown
Now: Construction
Value not published
Workforce not published
Finish 2026 [2]
No open adverts linked today
Client, scope, phases, sources
Client: Orsted
Value: not published
Finish: expected operational in early 2026 (Orsted, Feb 2025) [2]
Scope
430,000 t/yr of biogenic CO2 from Asnaes (wood chips) and Avedore (straw), shipped to Northern Lights [1] absorbers, desorbers and coolers lifted in place at both plants, Feb 2025 [2]
Phase by phase
FEED · doneEPC award · doneEngineering & procurement · doneConstruction · in progress · 25 Feb 2025 · key components installed [2] Pre-commissioning & commissioning · unknownStart-up · unknown
Sources: 1 power-technology.com 2 energy-pedia.com · checked 29 Oct 2026
CONFIRMED United Kingdom · CCS / BECCS
Net Zero Teesside Power: 742 MW gas power plant with carbon capture (2 Mt/yr)
Technip Energies (lead EPC) · GE Vernova (power island) · Balfour Beatty (construction, GBP 833 m)
FEED FEED: done Award EPC award: done, Dec 2024 E&P Engineering & procurement: in progress Build Construction: in progress Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Construction
Value GBP 833m [1]
Workforce not published
Finish not published
No open adverts linked today
Client, scope, phases, sources
Client: Net Zero Teesside Power (bp-Equinor JV)
Value: GBP 833 million (Balfour Beatty construction contract) [1]
Scope
742 MW combined-cycle plant with post-combustion capture of up to 2 Mt CO2 a year, stored by the Northern Endurance Partnership [1]
Phase by phase
FEED · doneEPC award · done · Dec 2024 · FID [1] Engineering & procurement · in progressConstruction · in progressPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 theconstructionindex.co.uk · checked 29 Oct 2026
CONFIRMED MEDIUM OFFSHORE Norway · CCS / BECCS
Northern Lights phase 2 (Oygarden): CO2 storage expansion to 5 Mt/yr
Aker Solutions (EPC onshore facilities) · Subsea7 (EPC 5 km CO2 pipeline and subsea)
FEED FEED: done Award EPC award: done, 31 Mar 2025 E&P Engineering & procurement: in progress Build Construction: in progress Comm. Pre-commissioning & commissioning: in progress Start Start-up: not started
Now: Pre-commissioning & commissioning
Value NOK 7.5bn [1]
Workforce not published
Finish 2028 [1]
No open adverts linked today
Client, scope, phases, sources
Client: Northern Lights JV (Equinor, Shell, TotalEnergies)
Value: NOK 7.5 billion (phase 2 investment) [1]
Finish: commissioning scheduled for 2028 [1]
Scope
capacity from 1.5 to 5 Mt CO2 a year; new onshore tanks, jetty and a 5 km pipeline [1] Aker Solutions works at Stord, Fornebu and Mumbai 2025-2028; Subsea7 offshore work 2026-2027 [1]
Phase by phase
FEED · doneEPC award · done · 31 Mar 2025 [1] Engineering & procurement · in progressConstruction · in progressPre-commissioning & commissioning · in progressStart-up · not started
Sources: 1 constructionreviewonline.com · checked 29 Oct 2026
CONFIRMED OFFSHORE Netherlands · CCS / BECCS
Porthos CCS, Port of Rotterdam: CO2 compressor station, 30 km pipeline, P18 storage (2.5 Mt/yr)
Bonatti (EPC compressor station)
FEED FEED: done Award EPC award: done E&P Engineering & procurement: done Build Construction: in progress, 2024 Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Construction
Value not published
Workforce not published
Finish completion planned for 2026 (May… [2]
No open adverts linked today
Client, scope, phases, sources
Client: Porthos (Gasunie, EBN, Port of Rotterdam)
Value: not published
Finish: completion planned for 2026 (May 2024 plan; not reconfirmed in a source read today) [2]
Scope
2.5 Mt CO2 a year for 15 years; three compressors up to 130 bar; onshore pipeline sized for 10 Mt [1] Bonatti: design, procurement, construction and pre-commissioning of the compressor station [2]
Phase by phase
FEED · doneEPC award · doneEngineering & procurement · doneConstruction · in progress · 2024 · construction start [2] Pre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 hellenicshippingnews.com 2 iploca.com · checked 29 Oct 2026
CONFIRMED LARGE OFFSHORE Suriname · FPSO
TotalEnergies GranMorgu (Block 58, Suriname): FPSO 220,000 b/d
SBM Offshore (Fast4Ward FPSO hull reserved, with Technip Energies)
FEED FEED: done Award EPC award: done, 1 Oct 2024 E&P Engineering & procurement: done Build Construction: in progress Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Construction
Value USD 10.5bn [1]
Workforce not published
Finish 2028 [2]
No open adverts linked today
Client, scope, phases, sources
Client: TotalEnergies (50%, operator), APA (50%); Staatsolie option up to 20%
Value: USD 10.5 billion (project, at FID) [1]
Finish: first oil 2028 [2]
Scope
FPSO 220,000 b/d on the Sapakara and Krabdagu fields, subsea wells [1] construction advancing; first oil 2028 (Aug 2026) [2]
Phase by phase
FEED · doneEPC award · done · 1 Oct 2024 · FID [1] Engineering & procurement · doneConstruction · in progressPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 jpt.spe.org 2 worldoil.com · checked 29 Oct 2026
CONFIRMED OFFSHORE Equatorial Guinea · Subsea
Chevron Aseng gas monetisation (Equatorial Guinea): subsea tieback to Alen platform
Subsea7 (subsea installation (EPCI))
FEED FEED: done Award EPC award: done, 1 Apr 2026 E&P Engineering & procurement: in progress Build Construction: unknown Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Engineering & procurement
Value USD 150-300 million… [1]
Workforce not published
Finish offshore operations expected to… [1]
No open adverts linked today
Client, scope, phases, sources
Client: Noble Energy EG (Chevron)
Value: USD 150-300 million ('substantial', Subsea7 band) [1]
Finish: offshore operations expected to start in 2026 [1]
Scope
single-well tieback: about 19 km rigid flowline and 20 km umbilicals in about 800 m of water [1]
Phase by phase
FEED · doneEPC award · done · 1 Apr 2026 [1] Engineering & procurement · in progressConstruction · unknownPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 worldoil.com · checked 29 Oct 2026
CONFIRMED Uganda / Tanzania · Pipeline
East African Crude Oil Pipeline (EACOP), Uganda-Tanzania, + Tilenga/Kingfisher feed station
Contractors: contractors not named in the source read today
FEED FEED: done Award EPC award: done E&P Engineering & procurement: done Build Construction: in progress Comm. Pre-commissioning & commissioning: in progress Start Start-up: not started
Now: Pre-commissioning & commissioning · 91% complete (Aug 2026) [1]
Value not published
Workforce not published
Finish 2026 [1]
No open adverts linked today
Client, scope, phases, sources
Client: EACOP Ltd (TotalEnergies, UNOC, TPDC, CNOOC)
Value: not published
Finish: first oil expected before the end of 2026 [1]
Scope
pipeline 91% complete; Pump Station One (fed by Tilenga and Kingfisher) 83% complete (Aug 2026) [1]
Phase by phase
Progress: 91% complete (EACOP deputy MD, 5 Aug 2026) [1]
FEED · doneEPC award · doneEngineering & procurement · doneConstruction · in progressPre-commissioning & commissioning · in progressStart-up · not started
Sources: 1 monitor.co.ug · checked 29 Oct 2026
CONFIRMED Kenya · Refinery
Dangote Lamu refinery and petrochemical complex (Kenya), 700,000 b/d
Engineers India (EIL) (PMC and EPCM consultant)
FEED FEED: unknown Award EPC award: done, 22 Sep 2026 E&P Engineering & procurement: in progress Build Construction: not started Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Engineering & procurement
Value USD 450m [1]
Workforce not published
Finish construction to begin… [1]
No open adverts linked today
Client, scope, phases, sources
Client: Dangote Group
Value: more than USD 450 million (EIL PMC/EPCM contract) [1]
Finish: construction to begin end-September 2026; completion in about three years (Dangote) [1]
Scope
greenfield 700,000 b/d refinery and petrochemical plant at Lamu [1]
Phase by phase
FEED · unknownEPC award · done · 22 Sep 2026 · EIL PMC/EPCM contract [1] Engineering & procurement · in progressConstruction · not startedPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 nairametrics.com · checked 29 Oct 2026
ON THE RADAR LARGE Papua New Guinea · LNG plant
Papua LNG (Elk-Antelope, Gulf Province): 5.6 Mtpa, pre-FID
Contractors: EPC tender complete; award recommendations await partner approval
FEED FEED: done Award EPC award: unknown E&P Engineering & procurement: unknown Build Construction: not started Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Last step done: FEED
Value USD 14bn [1]
Workforce EPC Radar estimate est. 9,800-36,400 at peak how?
Finish not published
No open adverts linked today
Client, scope, phases, sources
Client: ExxonMobil (operator, 34.1%), Santos, Kumul/MRDC, TotalEnergies, ENEOS Xplora
Value: about USD 14 billion (capex) [1]
Workforce estimate (low confidence): EPC Radar estimate from 2 published onshore LNG projects in this tracker, 0.7-2.6 workers per USD million of declared value (ng-nlng-train7, Golden Pass LNG), applied to project value: about USD 14,000 m
Scope
5.6 Mtpa of LNG from the Elk and Antelope fields [1]
Phase by phase
FEED · doneEPC award · unknownEngineering & procurement · unknownConstruction · not startedPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 worldoil.com · checked 29 Oct 2026
CONFIRMED Turkmenistan · Gas processing
Turkmengaz Galkynysh gas field development, phase IV (turnkey)
CNPC Amudarya Petroleum Company (turnkey construction)
FEED FEED: unknown Award EPC award: done, 17 Apr 2026 E&P Engineering & procurement: in progress Build Construction: unknown Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Engineering & procurement
Value not published
Workforce not published
Finish not published
No open adverts linked today
Client, scope, phases, sources
Client: Turkmengaz
Value: not published
Scope
turnkey construction contract for phase IV of Galkynysh development, signed 17 Apr 2026 [1]
Phase by phase
FEED · unknownEPC award · done · 17 Apr 2026 [1] Engineering & procurement · in progressConstruction · unknownPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 interfax.kz · checked 29 Oct 2026
CONFIRMED OFFSHORE Brunei · Subsea
PETRONAS Carigali Brunei: six-well subsea development to a floating production unit + gas export pipeline
McDermott (EPCIC subsea system and export pipeline)
FEED FEED: done Award EPC award: done, 9 Dec 2025 E&P Engineering & procurement: in progress Build Construction: unknown Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Engineering & procurement
Value not published
Workforce not published
Finish not published
No open adverts linked today
Client, scope, phases, sources
Client: PETRONAS Carigali Brunei
Value: not published
Scope
umbilicals, risers and flowlines for six wells to a floating production unit; export pipeline to Brunei LNG [1]
Phase by phase
FEED · doneEPC award · done · 9 Dec 2025 [1] Engineering & procurement · in progressConstruction · unknownPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 pgjonline.com · checked 29 Oct 2026
CONFIRMED OFFSHORE Israel · Offshore platform
Chevron Leviathan expansion (Eastern Mediterranean): new modules on the Leviathan platform
Hanwha Ocean (module fabrication)
FEED FEED: done Award EPC award: done, 5 Mar 2026 E&P Engineering & procurement: in progress Build Construction: unknown Comm. Pre-commissioning & commissioning: not started Start Start-up: not started
Now: Engineering & procurement
Value not published
Workforce not published
Finish not published
No open adverts linked today
Client, scope, phases, sources
Client: Chevron Mediterranean (operator)
Value: not published
Scope
module fabrication for integration on the existing Leviathan offshore platform [1]
Phase by phase
FEED · doneEPC award · done · 5 Mar 2026 · module fabrication contract [1] Engineering & procurement · in progressConstruction · unknownPre-commissioning & commissioning · not startedStart-up · not started
Sources: 1 worldoil.com · checked 29 Oct 2026