Project tracker · page updated 26 Nov 2026 · each project shows the day we last checked it

Every project we track, phase by phase

Oil and gas projects from FEED to start-up: who is building them, how far along they are, when they finish and where the open jobs are.

152projects (10 in the Top 10, 142 smaller)
49countries
61in construction or commissioning
314openings in 129 adverts, outside the US
Illustration: EPC Radar

Projects by phase now

Before the EPC award7FEED2EPC award14Engineering & procurement52Construction44Pre-commissioning & commissioning18Start-up6

9 without a published phase

Countries with the most projects

Method: published figures only, each with its source, never added up. Two labelled exceptions: the size class (Large from USD 2 bn, Medium USD 300 m to 2 bn, Small below USD 300 m, from the declared value at fixed ECB rates of 29 Oct 2026) and workforce ranges marked "EPC Radar estimate" (how we estimate).

Filters and sort
152 of 152 projects

Phase bar: dark = done, amber = in progress, grey = not started, dotted = not publishedE&P = engineering & procurement · Comm. = commissioning

No project matches these filters

Clear a filter or search for a contractor name.

CONFIRMEDMEDIUMOFFSHORESaudi Arabia · Subsea

Aramco offshore: CRPO 168 and 170, seven production deck manifolds (Abu Safah, Safaniyah, Manifa, Berri, Marjan)

Saipem (EPCI under the long-term agreement (two CRPOs))
  1. FEED: FEED: unknown
  2. Award: EPC award: done, 25 Nov 2026
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: not started
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Engineering & procurement
Value
USD 650m [1]
Workforce
not published
Finish
not published
No open adverts linked today
Client, scope, phases, sources

Client: Saudi Aramco

Value: about USD 650 million (both contracts) [1]

Scope
  • CRPO 168: EPCI of 4 production deck manifolds, about 14 km of 12-16 inch pipeline and about 24 km of 15 kV cables, subsea facilities for Abu Safah, Safaniyah, Manifa and Berri; onshore tie-in at the Manifa drill site [1]
  • CRPO 170: EPCI of 3 production deck manifolds, about 25 km of 12-16 inch pipeline and about 17 km of 15 kV cables, subsea facilities at Marjan [1]
  • fabrication at Saipem's Saudi yard (Saipem Taqa Al-Rushaid Fabricators); offshore work by Saipem construction vessels already in the region [1]
Phase by phase
  • FEED · unknown
  • EPC award · done · 25 Nov 2026 [1]
  • Engineering & procurement · in progress
  • Construction · not started
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 saipem.com · checked 26 Nov 2026

REPORTEDOFFSHOREQatar · Offshore platform

Maydan Mahzam redevelopment, MM-EPIC2: subsea pipelines, power cables and umbilicals

COOEC (Offshore Oil Engineering Co.) (EPIC contractor for package 2 (MM-EPIC2))
  1. FEED: FEED: done
  2. Award: EPC award: done, 20 Nov 2026
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: not started
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Engineering & procurement
Value
USD million 0.0008m [1]
Workforce
not published
Finish
66-month contract [1]
No open adverts linked today
Client, scope, phases, sources

Client: QatarEnergy

Value: about $800 million (QR2.9 billion), as reported [1]

Scope
  • over 100 km of subsea pipelines, power cables and umbilicals offshore Qatar; scope from project management and detailed engineering to procurement, construction, transport, offshore installation and pre-commissioning; 66-month contract [1]
Phase by phase
  • FEED · done
  • EPC award · done · 20 Nov 2026 · COOEC, MM-EPIC2 contract signed (award first announced in October 2026) [1]
  • Engineering & procurement · in progress
  • Construction · not started
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 shippingherald.com 2 oilandgasmiddleeast.com 3 saudigulfprojects.com · checked 23 Nov 2026

CONFIRMEDTOP 10LARGEMozambique · LNG plant

Mozambique LNG

Saipem (CCS JV leader) · McDermott (CCS JV partner) · Chiyoda (CCS JV partner)
  1. FEED: FEED: done
  2. Award: EPC award: done, Jun 2019
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: in progress
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Construction · 45% complete (Jul 2026) [2]
45%
Value
USD 6bn [1]
Workforce
between 7,000 and 8,000 workers (TotalEnergies CEO, Q2 2026 results call) [2]
Finish
2029 [2]
Open jobs today · 5 open adverts
See them on the Top 10 projects page ›
Client, scope, phases, sources

Client: TotalEnergies (operator) for the Mozambique LNG Area 1 partners

Value: approximately USD 6 billion (Saipem's share of the CCS JV EPC contract, 2019) [1]

Finish: first LNG from the first train targeted for 2029 [2]

Scope
  • 2 liquefaction trains, 12.88 Mtpa nameplate, storage tanks and export jetty [1]
  • up to 13 Mtpa of LNG from 2029; project value USD 20 billion [2]
Phase by phase

Progress: almost 45% complete (TotalEnergies CEO, July 2026) [2]

  • FEED · done
  • EPC award · done · Jun 2019 [1]
  • Engineering & procurement · in progress
  • Construction · in progress
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 lngindustry.com 2 clubofmozambique.com · checked 29 Oct 2026

CONFIRMEDTOP 10Qatar · LNG plant

North Field East & South

Chiyoda (CTJV, North Field East) · Technip Energies (CTJV on NFE; T.EN CCC JV leader on NFS) · Consolidated Contractors Company (T.EN CCC JV, North Field South)
  1. FEED: FEED: done
  2. Award: EPC award: done, 9 Feb 2021
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: in progress
  5. Comm.: Pre-commissioning & commissioning: in progress, 7 Oct 2026
  6. Start: Start-up: not started
Now: Pre-commissioning & commissioning
Value
not disclosed by the contractors;… [1]
Workforce
not published
Finish
2027 [3]
No open adverts linked today
Client, scope, phases, sources

Client: QatarEnergy

Value: not disclosed by the contractors; each award is 'major' for Technip Energies (NFE: over USD 1.0 bn; NFS: above EUR 1 bn of revenue) [1]

Finish: NFE: production expected to begin in H1 2027 (QatarEnergy CEO, per Reuters); first-train LNG in Q1 2027 per sources [3]

Scope
  • NFE: 4 mega trains x 8 Mtpa plus a large CO2 capture and sequestration facility; Qatar from 77 to 110 Mtpa [2]
  • NFS: 2 mega trains x 8 Mtpa plus 1.5 Mtpa CO2 capture [1]
Phase by phase
  • FEED · done
  • EPC award · done · 9 Feb 2021 · NFE 9 Feb 2021; NFS 16 May 2023 [2]
  • Engineering & procurement · in progress
  • Construction · in progress
  • Pre-commissioning & commissioning · in progress · 7 Oct 2026 · first NFE train reported ready to start operation in November 2026 (Reuters, sources) [3]
  • Start-up · not started

Sources: 1 ten.com 2 ten.com 3 boereport.com · checked 29 Oct 2026

REPORTEDTOP 10LARGESaudi Arabia · Gas processing

Jafurah

Larsen & Toubro (gas processing facilities, phase 2) · Samsung E&A (gas treatment) · Hyundai E&C (sulphur recovery, with Hyundai Engineering) · Hyundai Engineering (sulphur recovery, with Hyundai E&C)
  1. FEED: FEED: done
  2. Award: EPC award: done, 30 Jun 2024
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: in progress
  5. Comm.: Pre-commissioning & commissioning: unknown
  6. Start: Start-up: in progress, Dec 2025
Now: Start-up
Value
USD 12.4bn [1]
Workforce
not published
Finish
2030 [2]
Open jobs today · 186 openings in 1 adverts
See them on the Top 10 projects page ›
Client, scope, phases, sources

Client: Saudi Aramco

Value: 16 contracts totalling around USD 12.4bn (SR46.5bn) for the second phase (June 2024) [1]

Finish: 2 bscfd of sales gas targeted by 2030 (Aramco) [2]

Scope
  • phase 2: gas compression, pipelines, new gas processing trains, utilities, sulphur and export facilities, NGL fractionation at Jubail [1]
  • 17,000 km2, 229 tcf of raw gas; 2 bscfd of sales gas, 420 MMscfd ethane and about 630,000 b/d liquids targeted by 2030 [2]
Phase by phase
  • FEED · done
  • EPC award · done · 30 Jun 2024 · phase 2 contracts [1]
  • Engineering & procurement · in progress
  • Construction · in progress
  • Pre-commissioning & commissioning · unknown
  • Start-up · in progress · Dec 2025 · phase 1: first shale gas produced December 2025; phase 2 under construction [2]

Sources: 1 offshore-technology.com 2 aramco.com · checked 26 Nov 2026

CONFIRMEDTOP 10LARGEOFFSHOREUAE · Gas processing

Hail & Ghasha

Saipem (offshore EPC, with NMDC Energy, formerly NPCC) · NMDC Energy (offshore EPC) · Tecnimont (MAIRE) (onshore EPC)
  1. FEED: FEED: done
  2. Award: EPC award: done, 5 Oct 2023
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: in progress
  5. Comm.: Pre-commissioning & commissioning: unknown
  6. Start: Start-up: not started
Now: Construction
Value
USD 16.9bn [1]
Workforce
not published
Finish
2028 [2]
Open jobs today · 19 open adverts
See them on the Top 10 projects page ›
Client, scope, phases, sources

Client: ADNOC

Value: USD 16.9bn (SR63.39bn) across two EPC contracts: offshore about USD 8.2bn (NPCC-Saipem), onshore USD 8.7bn (Tecnimont) [1]

Finish: onshore: completion expected during 2028 (MAIRE, 2023); first gas by the end of the decade (The National, Dec 2025) [2]

Scope
  • 4 drilling centres and a processing plant on artificial islands; over 300 km of subsea pipelines [1]
  • onshore: 2 gas processing units, 3 sulphur recovery sections, export pipelines [2]
  • up to 1.8 bscfd of gas; 1.5 Mtpa CO2 capture [3]
Phase by phase
  • FEED · done
  • EPC award · done · 5 Oct 2023 [2]
  • Engineering & procurement · in progress
  • Construction · in progress
  • Pre-commissioning & commissioning · unknown
  • Start-up · not started

Sources: 1 offshore-technology.com 2 tecnimont.com 3 thenationalnews.com · checked 29 Oct 2026

CONFIRMEDTOP 10LARGEUAE · LNG plant

Ruwais LNG

Technip Energies (TJN Ruwais JV leader) · JGC (TJN Ruwais JV partner) · NMDC Energy (TJN Ruwais JV partner)
  1. FEED: FEED: done
  2. Award: EPC award: done, 13 Jun 2024
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: in progress
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Construction
Value
USD 5.5bn [1]
Workforce
not published
Finish
2028 [1]
Open jobs today · 1 open advert
See them on the Top 10 projects page ›
Client, scope, phases, sources

Client: ADNOC (ADNOC Gas to hold 60%)

Value: EPC contract valued at over USD 5.5 billion (World Oil); 'major' for Technip Energies (above EUR 1 bn of revenue) [1]

Finish: train 1 on stream in H2 2028, train 2 in early 2029 (ADNOC Gas, Nov 2024) [1]

Scope
  • 2 trains x 4.8 Mtpa = 9.6 Mtpa [1]
  • electric-driven motors instead of gas turbines [2]
Phase by phase
  • FEED · done
  • EPC award · done · 13 Jun 2024 [2]
  • Engineering & procurement · in progress
  • Construction · in progress
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 worldoil.com 2 ten.com · checked 29 Oct 2026

CONFIRMEDTOP 10Qatar · LNG plant

North Field West

Technip Energies (T.EN CCC GAC JV leader) · Consolidated Contractors Company (JV partner) · Gulf Asia Contracting (JV partner)
  1. FEED: FEED: done
  2. Award: EPC award: done, 25 Feb 2026
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: unknown
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Engineering & procurement
Value
not disclosed; 'major' award for… [1]
Workforce
not published
Finish
not published
No open adverts linked today
Client, scope, phases, sources

Client: QatarEnergy

Value: not disclosed; 'major' award for Technip Energies: above EUR 1 billion of revenue [1]

Scope
  • 2 mega trains x 8 Mtpa (about 16 Mtpa) [1]
  • 1.1 Mtpa CO2 capture (2.2 Mtpa with NFS) [1]
Phase by phase
  • FEED · done
  • EPC award · done · 25 Feb 2026 [1]
  • Engineering & procurement · in progress
  • Construction · unknown
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 ten.com · checked 29 Oct 2026

CONFIRMEDTOP 10LARGESaudi Arabia · Gas processing

Fadhili Gas Plant Expansion

Samsung E&A (gas treatment unit, utilities and offsites) · GS Engineering & Construction (EPC package) · Nesma & Partners (EPC package)
  1. FEED: FEED: done
  2. Award: EPC award: done, 2 Apr 2024
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: in progress
  5. Comm.: Pre-commissioning & commissioning: unknown
  6. Start: Start-up: not started
Now: Construction
Value
USD 7.7bn [1]
Workforce
not published
Finish
Nov 2027 [1]
No open adverts linked today
Client, scope, phases, sources

Client: Saudi Aramco

Value: USD 7.7 billion of contracts (Aramco) [1]

Finish: expected to be completed by November 2027 (Aramco, April 2024) [1]

Scope
  • adds up to 1.5 bscfd of raw gas processing capacity [1]
  • adds 2,300 t/d of sulphur production [1]
Phase by phase
  • FEED · done
  • EPC award · done · 2 Apr 2024 [1]
  • Engineering & procurement · in progress
  • Construction · in progress
  • Pre-commissioning & commissioning · unknown
  • Start-up · not started

Sources: 1 aramco.com · checked 26 Nov 2026

CONFIRMEDTOP 10LARGESaudi Arabia · Petrochemical

Amiral

Hyundai E&C (mixed-feed cracker and utilities) · Tecnimont (MAIRE) (two polyethylene units) · Sinopec Engineering Group Saudi (tank farm and SATORP integration)
  1. FEED: FEED: done
  2. Award: EPC award: done, 24 Jun 2023
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: in progress
  5. Comm.: Pre-commissioning & commissioning: unknown
  6. Start: Start-up: not started
Now: Construction
Value
USD 11bn [1]
Workforce
no construction figure published; TotalEnergies: 7,000 local direct and indirect jobs (whole project, including the chemicals park) [1]
Finish
2027 [1]
Open jobs today · 2 open adverts
See them on the Top 10 projects page ›
Client, scope, phases, sources

Client: SATORP (Aramco 62.5%, TotalEnergies 37.5%)

Value: an investment of USD 11 billion (TotalEnergies) [1]

Finish: operational start-up planned for 2027 (TotalEnergies) [1]

Scope
  • mixed-feed cracker, 1.65 Mtpa of ethylene [1]
  • two polyethylene lines of 500,000 t/y each [1]
Phase by phase
  • FEED · done
  • EPC award · done · 24 Jun 2023 · FID December 2022 [2]
  • Engineering & procurement · in progress
  • Construction · in progress
  • Pre-commissioning & commissioning · unknown
  • Start-up · not started

Sources: 1 totalenergies.com 2 totalenergies.com · checked 26 Nov 2026

CONFIRMEDTOP 10MEDIUMOman · LNG plant

Marsa LNG

Technip Energies (EPC, LNG plant) · McDermott (CB&I) (EPC, LNG storage tank)
  1. FEED: FEED: done
  2. Award: EPC award: done, 22 Apr 2024
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: in progress
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Construction · 55% complete (Jun 2026) [2]
55%
Value
not disclosed; 'substantial'… [1]
Workforce
not published
Finish
2028 [2]
No open adverts linked today
Client, scope, phases, sources

Client: TotalEnergies (80%) and OQ (20%)

Value: not disclosed; 'substantial' award for Technip Energies (EUR 500 million to 1 billion of revenue) [1]

Finish: start-up targeted in the first quarter of 2028 [2]

Scope
  • 1 Mtpa liquefaction complex for ship fuelling [2]
  • 165,000 m3 LNG storage tank [2]
Phase by phase

Progress: more than 55 per cent complete at the end of June 2026 [2]

  • FEED · done
  • EPC award · done · 22 Apr 2024 [1]
  • Engineering & procurement · in progress
  • Construction · in progress
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 ten.com 2 omanobserver.om · checked 29 Oct 2026

CONFIRMEDTOP 10United States · LNG plant

Rio Grande LNG

Bechtel (EPC, all five trains)
  1. FEED: FEED: done
  2. Award: EPC award: done
  3. E&P: Engineering & procurement: in progress, Jun 2026
  4. Build: Construction: in progress, Jun 2026
  5. Comm.: Pre-commissioning & commissioning: in progress, Jun 2026
  6. Start: Start-up: not started
Now: Pre-commissioning & commissioning · 74% complete (Jun 2026) [1]
74%
Value
not stated in the sources read today
Workforce
~7,500 construction and trade workers during peak construction (NextDecade); FERC approved the raise from 5,225 in April 2026 [2]
Finish
2027 [1]
Open jobs today · 13 open adverts · US work authorisation needed
See them on the Top 10 projects page ›
Client, scope, phases, sources

Client: NextDecade (Rio Grande LNG)

Value: not stated in the sources read today

Finish: first LNG from Train 1 expected in H1 2027; Phase 1 ahead of the guaranteed schedule (NextDecade, Q2 2026) [1]

Scope
  • Trains 1-5: about 30 Mtpa expected capacity [1]
  • 48 Mtpa under construction and in development; site room for up to 10 trains [2]
Phase by phase

Progress: Trains 1-2: 74.0% (engineering 99.1%, procurement 97.8%, construction 58.9%, commissioning 0.6%); Train 3 50.4%; Train 4 15.5%; Train 5 9.4% [1]

  • FEED · done
  • EPC award · done
  • Engineering & procurement · in progress · Jun 2026 · Trains 1-2 engineering 99.1%, procurement 97.8% [1]
  • Construction · in progress · Jun 2026 · Trains 1-2 construction 58.9% [1]
  • Pre-commissioning & commissioning · in progress · Jun 2026 · Trains 1-2 commissioning 0.6%; first gas expected H2 2026 [1]
  • Start-up · not started

Sources: 1 finviz.com 2 next-decade.com · checked 29 Oct 2026

CONFIRMEDMEDIUMIndia · Refinery

HPCL Mumbai refinery: lube modernisation and bottom upgradation (LMBU)

Technip Energies (EPC)
  1. FEED: FEED: unknown
  2. Award: EPC award: done, 12 Oct 2026
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: unknown
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Engineering & procurement · 9.9% complete (31 Mar 2026) [1]
9.9%
Value
INR 57.4bn [1]
Workforce
not published
Finish
Mar 2028 [1]
No open adverts linked today
Client, scope, phases, sources

Client: Hindustan Petroleum Corp. (HPCL)

Value: project cost Rs 57.40 billion (US$600.4 million) at 31 Mar 2026, up from Rs 46.79 billion; Technip Energies' order: EUR 250-500 million of revenue [1]

Finish: scheduled to be fully completed in March 2028 (HPCL, May 2026) [1]

Scope
  • 550,000 t/y integrated hydrocracker and catalytic dewaxing unit [1]
  • 850,000 t/y solvent deasphalting unit [1]
Phase by phase

Progress: 9.9% physical completion at 31 Mar 2026 (HPCL) [1]

  • FEED · unknown
  • EPC award · done · 12 Oct 2026 [2]
  • Engineering & procurement · in progress
  • Construction · unknown
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 ogj.com 2 hydrocarbonengineering.com · checked 26 Nov 2026

CONFIRMEDMEDIUMIndia · Petrochemical

BPCL Bina Petchem & Refinery Expansion: LLDPE/HDPE swing unit (2 x 575 ktpa)

L&T Energy Hydrocarbon (LSTK EPCC)
  1. FEED: FEED: unknown
  2. Award: EPC award: done, 23 Dec 2025
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: in progress, 29 Oct 2026
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Construction
Value
'major' order: Rs 5,000-10,000… [1]
Workforce
not published
Finish
May 2028 [2]
Open jobs today · 1 open advert
All open jobs on this project ›
Client, scope, phases, sources

Client: Bharat Petroleum Corp. (BPCL)

Value: 'major' order: Rs 5,000-10,000 crore band (L&T classification) [1]

Finish: BPREP scheduled for completion in May 2028 (BPCL annual report, via OGJ) [2]

Scope
  • LLDPE/HDPE swing unit, 2 x 575 ktpa [1]
  • part of BPREP: refinery 7.8 to 11 Mtpa and a 1.2 Mtpa ethylene dual-feed cracker (project Rs 490 bn approved 2023) [2]
Phase by phase
  • FEED · unknown
  • EPC award · done · 23 Dec 2025 [1]
  • Engineering & procurement · in progress
  • Construction · in progress · 29 Oct 2026 · L&T advertises piping fabrication and erection roles at Bina [3]
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 larsentoubro.com 2 ogj.com 3 larsentoubrocareers.peoplestrong.com · checked 26 Nov 2026

CONFIRMEDIndia · Petrochemical

BPCL Bina expansion: polypropylene (550 ktpa) and Butene-1 (50 ktpa) units

Technip Energies (EPCC)
  1. FEED: FEED: unknown
  2. Award: EPC award: done, 7 Jan 2026
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: unknown
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Engineering & procurement
Value
not disclosed (described as a… [1]
Workforce
not published
Finish
May 2028 [2]
No open adverts linked today
Client, scope, phases, sources

Client: Bharat Petroleum Corp. (BPCL)

Value: not disclosed (described as a 'large' contract) [1]

Finish: BPREP scheduled for completion in May 2028 (BPCL annual report, via OGJ) [2]

Scope
  • 550,000 t/y polypropylene and 50,000 t/y Butene-1 [1]
  • part of BPREP (Bina refinery to 11 Mtpa, 1.2 Mtpa ethylene cracker) [2]
Phase by phase
  • FEED · unknown
  • EPC award · done · 7 Jan 2026 [1]
  • Engineering & procurement · in progress
  • Construction · unknown
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 hydrocarbonengineering.com 2 ogj.com · checked 26 Nov 2026

CONFIRMEDIndia · Refinery

BPCL Mumbai refinery: 3 Mtpa petro resid FCC (PRFCC), India's first

Technip Energies (EPsCm: engineering, procurement, construction management)
  1. FEED: FEED: unknown
  2. Award: EPC award: done, 7 Jan 2026
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: unknown
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Engineering & procurement
Value
not disclosed (described as a… [1]
Workforce
not published
Finish
not published
No open adverts linked today
Client, scope, phases, sources

Client: Bharat Petroleum Corp. (BPCL)

Value: not disclosed (described as a 'large' contract) [1]

Scope
  • 3 Mtpa petro resid fluidised catalytic cracker (PRFCC), Mumbai refinery [1]
Phase by phase
  • FEED · unknown
  • EPC award · done · 7 Jan 2026 [1]
  • Engineering & procurement · in progress
  • Construction · unknown
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 hydrocarbonengineering.com · checked 26 Nov 2026

CONFIRMEDIndia · Terminal & storage

Petronet LNG Dahej: 170,000 m3 LNG/ethane tank, 140,000 m3 propane tank, handling for the PDH-PP plant

L&T Energy Hydrocarbon (LSTK EPCC)
  1. FEED: FEED: unknown
  2. Award: EPC award: done, 16 Jan 2026
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: unknown
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Engineering & procurement
Value
'large' order: Rs 2,500-5,000… [1]
Workforce
not published
Finish
'within the agreed timelines'… [1]
No open adverts linked today
Client, scope, phases, sources

Client: Petronet LNG

Value: 'large' order: Rs 2,500-5,000 crore band (L&T classification) [1]

Finish: 'within the agreed timelines' (L&T); no date published [1]

Scope
  • 170,000 m3 LNG/ethane double-wall tank [1]
  • 140,000 m3 propane double-wall tank, for the Dahej PDH-PP complex [1]
Phase by phase
  • FEED · unknown
  • EPC award · done · 16 Jan 2026 [1]
  • Engineering & procurement · in progress
  • Construction · unknown
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 larsentoubro.com · checked 26 Nov 2026

CONFIRMEDMEDIUMOFFSHOREIndia · Offshore platform

ONGC west coast: Pipeline Replacement Project PRP-X and four wellhead platforms

L&T Energy Hydrocarbon Offshore (EPCIC)
  1. FEED: FEED: unknown
  2. Award: EPC award: done, 10 Aug 2026
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: unknown
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Engineering & procurement
Value
between Rs 50bn (US$525.2m) and… [1]
Workforce
not published
Finish
not published
No open adverts linked today
Client, scope, phases, sources

Client: ONGC

Value: between Rs 50bn (US$525.2m) and Rs 100bn (US$1.05bn), L&T band [1]

Scope
  • Pipeline Replacement Project PRP-X: several subsea pipeline segments [1]
  • four wellhead platforms, EPCIC [1]
Phase by phase
  • FEED · unknown
  • EPC award · done · 10 Aug 2026 [1]
  • Engineering & procurement · in progress
  • Construction · unknown
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 offshore-technology.com · checked 26 Nov 2026

CONFIRMEDOFFSHOREIndia · Offshore platform

ONGC Additional Development of Ratna-I (ADR-I) and NLM-14: 3 wellhead + 1 riser platform, subsea pipelines

L&T Energy Hydrocarbon Offshore (EPCIC)
  1. FEED: FEED: unknown
  2. Award: EPC award: done, 9 Sep 2026
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: unknown
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Engineering & procurement
Value
'large' order: Rs 2,500-5,000… [1]
Workforce
not published
Finish
not published
No open adverts linked today
Client, scope, phases, sources

Client: ONGC

Value: 'large' order: Rs 2,500-5,000 crore band (L&T classification) [1]

Scope
  • 3 wellhead platforms + 1 riser platform, subsea pipelines (Ratna-I and NLM-14) [1]
Phase by phase
  • FEED · unknown
  • EPC award · done · 9 Sep 2026 [1]
  • Engineering & procurement · in progress
  • Construction · unknown
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 nsearchives.nseindia.com · checked 26 Nov 2026

CONFIRMEDLARGEIndia · Refinery

IOCL Panipat refinery expansion, 15 to 25 Mtpa (+ polybutadiene rubber plant)

L&T Energy Hydrocarbon (EPCC residue hydrocracker (2.5 Mtpa, Axens) and diesel hydrotreater (5 Mtpa) packages) · Toyo Engineering India (vacuum gas oil hydrotreater unit (EPCC)) · not named in the sources we read
  1. FEED: FEED: done
  2. Award: EPC award: done
  3. E&P: Engineering & procurement: unknown
  4. Build: Construction: in progress, 30 Jun 2026
  5. Comm.: Pre-commissioning & commissioning: not started, Dec 2026
  6. Start: Start-up: not started
Now: Construction · 94% complete (30 Jun 2026) [1]
94%
Value
INR 382.3bn [1]
Workforce
not published
Finish
Dec 2026 [1]
No open adverts linked today
Client, scope, phases, sources

Client: Indian Oil Corp. (IOCL)

Value: Rs 382.31 billion invested at 30 Jun 2026 (initially budgeted Rs 329.46 bn) [1]

Finish: commissioning scheduled for December 2026 (IOC filing, 31 Jul 2026) [1]

Scope
  • 15 to 25 Mtpa crude capacity (+ polybutadiene rubber plant) [1]
Phase by phase

Progress: 94% physical completion at 30 Jun 2026 (IOC) [1]

  • FEED · done
  • EPC award · done
  • Engineering & procurement · unknown
  • Construction · in progress · 30 Jun 2026 [1]
  • Pre-commissioning & commissioning · not started · Dec 2026 · planned date [1]
  • Start-up · not started

Sources: 1 ogj.com 2 larsentoubro.com 3 toyo-eng.com · checked 26 Nov 2026

CONFIRMEDMEDIUMIndia · Refinery

IOCL Koyali (Gujarat) refinery expansion, 13.7 to 18 Mtpa (+ PP and lube base stock)

Toyo Engineering India (EPCC 2.5 Mtpa vacuum distillation unit, turnkey (Aug 2022)) · Nuberg Engineering (sulphur recovery unit, Rs 650 crore (2022)) · not named in the sources we read
  1. FEED: FEED: done
  2. Award: EPC award: done
  3. E&P: Engineering & procurement: unknown
  4. Build: Construction: in progress, 30 Jun 2026
  5. Comm.: Pre-commissioning & commissioning: not started, Nov 2026
  6. Start: Start-up: not started
Now: Construction · 89.2% complete (30 Jun 2026) [1]
89.2%
Value
INR 189.4bn [1]
Workforce
not published
Finish
Nov 2026 [1]
No open adverts linked today
Client, scope, phases, sources

Client: Indian Oil Corp. (IOCL)

Value: about Rs 189.36 billion overall cost (originally Rs 178.25 bn) [1]

Finish: commissioning planned for November 2026 (IOC filing, 31 Jul 2026) [1]

Scope
  • 13.7 to 18 Mtpa crude capacity (+ polypropylene and lube base stock) [1]
Phase by phase

Progress: 89.2% physical completion at 30 Jun 2026 (IOC) [1]

  • FEED · done
  • EPC award · done
  • Engineering & procurement · unknown
  • Construction · in progress · 30 Jun 2026 [1]
  • Pre-commissioning & commissioning · not started · Nov 2026 · planned date [1]
  • Start-up · not started

Sources: 1 ogj.com 2 toyo-eng.com 3 bsppd.business-standard.com · checked 26 Nov 2026

CONFIRMEDMEDIUMIndia · Refinery

IOCL Barauni refinery expansion, 6 to 9 Mtpa

L&T Energy Hydrocarbon (EPCC-1: new 9 Mtpa atmospheric-vacuum unit, LSTK (Apr 2020)) · Technip Energies (EPCC once-through hydrocracker 1 Mtpa and fuel gas treatment (Apr 2021)) · Tecnimont (MAIRE) (EPCC 200,000 t/y polypropylene unit (with Tecnimont Private)) · McDermott (EPCC diesel hydrotreating unit and additional units (2021)) · Toyo Engineering India (PMC phase II (consultant, not EPC)) · not named in the sources we read
  1. FEED: FEED: done
  2. Award: EPC award: done
  3. E&P: Engineering & procurement: unknown
  4. Build: Construction: in progress, 30 Jun 2026
  5. Comm.: Pre-commissioning & commissioning: not started, Dec 2026
  6. Start: Start-up: not started
Now: Construction · 91.6% complete (30 Jun 2026) [1]
91.6%
Value
INR 181.1bn [1]
Workforce
not published
Finish
Dec 2026 [1]
No open adverts linked today
Client, scope, phases, sources

Client: Indian Oil Corp. (IOCL)

Value: Rs 181.13 billion invested (previously budgeted Rs 148 bn) [1]

Finish: commissioning targeted for December 2026 (IOC filing, 31 Jul 2026) [1]

Scope
  • 6 to 9 Mtpa crude capacity [1]
Phase by phase

Progress: 91.6% physical completion at 30 Jun 2026 (IOC) [1]

  • FEED · done
  • EPC award · done
  • Engineering & procurement · unknown
  • Construction · in progress · 30 Jun 2026 [1]
  • Pre-commissioning & commissioning · not started · Dec 2026 · planned date [1]
  • Start-up · not started

Sources: 1 ogj.com 2 ogj.com 3 hydrocarbonprocessing.com 4 ogj.com · checked 26 Nov 2026

REPORTEDLARGEOFFSHOREIndia · Subsea

ONGC KG-DWN-98/2 deepwater block (Cluster 2), Krishna-Godavari basin

Afcons Infrastructure (current offshore piping work, named in its advert)
  1. FEED: FEED: done
  2. Award: EPC award: done
  3. E&P: Engineering & procurement: done
  4. Build: Construction: done
  5. Comm.: Pre-commissioning & commissioning: done
  6. Start: Start-up: done, Jan 2024
Last step done: Start-up
Value
USD 5bn [1]
Workforce
not published
Finish
producing since January 2024;… [1]
Open jobs today · 1 open advert
All open jobs on this project ›
Client, scope, phases, sources

Client: ONGC

Value: USD 5 billion deep-water project (Outlook Business headline, Jan 2024) [1]

Finish: producing since January 2024; ramp-up [1]

Scope
  • Cluster 2 deep-water development, Krishna-Godavari basin [1]
Phase by phase
  • FEED · done
  • EPC award · done
  • Engineering & procurement · done
  • Construction · done
  • Pre-commissioning & commissioning · done
  • Start-up · done · Jan 2024 · first oil January 2024; ramp-up and further work ongoing [1]

Sources: 1 outlookbusiness.com · checked 26 Nov 2026

CONFIRMEDOFFSHOREUAE · Gas compression

ADNOC Offshore Umm Shaif gas cap and pressure boosting, package 1 (30,000 t gas compression)

L&T Energy Hydrocarbon Offshore (consortium leader) · Lamprell (consortium partner)
  1. FEED: FEED: done
  2. Award: EPC award: done, 4 Aug 2026
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: unknown
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Engineering & procurement
Value
'ultra-mega' order (above Rs 150… [1]
Workforce
not published
Finish
2030 [1]
No open adverts linked today
Client, scope, phases, sources

Client: ADNOC Offshore

Value: 'ultra-mega' order (above Rs 150 bn, L&T band); the three EPC packages total USD 5.1bn; FID USD 6.2bn [1]

Finish: production expected by 2030 (MEED) [1]

Scope
  • 30,000-tonne gas compression system (package 1) [1]
  • 600 MMcfd of gas [1]
Phase by phase
  • FEED · done
  • EPC award · done · 4 Aug 2026 · FID July 2026 [1]
  • Engineering & procurement · in progress
  • Construction · unknown
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 guest.meed.com · checked 26 Nov 2026

CONFIRMEDOFFSHOREUAE · Gas compression

ADNOC Umm Shaif integrated gas cap and surface pressure boosting, package 4 (jacket + topside)

McDermott (EPCI) · Qingdao McDermott Wuchuan (QMW) (consortium, fabrication yard)
  1. FEED: FEED: done
  2. Award: EPC award: done, 24 Aug 2026
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: unknown
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Engineering & procurement
Value
more than USD 1 billion ('mega'… [1]
Workforce
not published
Finish
2030 [2]
No open adverts linked today
Client, scope, phases, sources

Client: ADNOC

Value: more than USD 1 billion ('mega' award, McDermott; exact value not disclosed) [1]

Finish: production from the Umm Shaif gas cap development expected by 2030 (MEED) [2]

Scope
  • new surface pressure boosting facility: jacket, topside, brownfield modifications [1]
  • fabrication at QMW yard, Qingdao (China) [1]
Phase by phase
  • FEED · done
  • EPC award · done · 24 Aug 2026 [1]
  • Engineering & procurement · in progress
  • Construction · unknown
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 worldoil.com 2 guest.meed.com · checked 26 Nov 2026

REPORTEDMEDIUMOFFSHOREUAE · Offshore platform

ADNOC SARB deep gas development (Ghasha concession): wellhead tower, 4 wells, tie-in to Das Island

McDermott (EPC)
  1. FEED: FEED: done
  2. Award: EPC award: done, Jan 2026
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: in progress, 16 Oct 2026
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Construction
Value
USD 500m [1]
Workforce
not published
Finish
production 'later this decade'… [2]
No open adverts linked today
Client, scope, phases, sources

Client: ADNOC

Value: estimated USD 500 million (MEED) [1]

Finish: production 'later this decade' (World Oil, Jan 2026) [2]

Scope
  • 200 MMscfd from four wells, about 120 km offshore [2]
  • wellhead tower tied in to Das Island [1]
Phase by phase
  • FEED · done
  • EPC award · done · Jan 2026 · FID 7 Jan 2026 [1]
  • Engineering & procurement · in progress
  • Construction · in progress · 16 Oct 2026 · steel cut [1]
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 meed.com 2 worldoil.com · checked 26 Nov 2026

CONFIRMEDLARGEUAE · Gas processing

ADNOC Gas Rich Gas Development phase 2: new gas processing train at Habshan

Wison Engineering (EPC)
  1. FEED: FEED: done
  2. Award: EPC award: done, 10 Aug 2026
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: in progress, 11 Nov 2026
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Construction
Value
USD 3.9bn [1]
Workforce
not published
Finish
not published
No open adverts linked today
Client, scope, phases, sources

Client: ADNOC Gas

Value: USD 3.9 billion EPC contract [1]

Scope
  • new gas processing train at the Habshan complex [1]
Phase by phase
  • FEED · done
  • EPC award · done · 10 Aug 2026 [1]
  • Engineering & procurement · in progress
  • Construction · in progress · 11 Nov 2026 · groundbreaking ceremony (ADNOC Gas, via OGJ 16 Nov 2026) [2]
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 worldoil.com 2 ogj.com · checked 26 Nov 2026

CONFIRMEDLARGEUAE · Gas processing

ADNOC Gas Rich Gas Development phase 3: new NGL fractionation train at Ruwais

Tecnimont (MAIRE) (EPC)
  1. FEED: FEED: done
  2. Award: EPC award: done, 10 Aug 2026
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: in progress, 10 Nov 2026
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Construction
Value
USD 4.3bn [1]
Workforce
not published
Finish
not published
No open adverts linked today
Client, scope, phases, sources

Client: ADNOC Gas

Value: USD 4.3 billion EPC contract [1]

Scope
  • new NGL fractionation train at Ruwais [1]
Phase by phase
  • FEED · done
  • EPC award · done · 10 Aug 2026 [1]
  • Engineering & procurement · in progress
  • Construction · in progress · 10 Nov 2026 · groundbreaking ceremony (ADNOC Gas, via OGJ 16 Nov 2026) [2]
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 worldoil.com 2 ogj.com · checked 26 Nov 2026

REPORTEDMEDIUMUAE · Onshore oil field

ADNOC Onshore Bab and North East Bab one tie-in project (well tie-ins, mini-pad, well bays)

Jereh Group (EPC framework, 60 months (Jereh filing, via MEED)) · Robt Stone Middle East (portion of the work)
  1. FEED: FEED: unknown
  2. Award: EPC award: done, Nov 2026
  3. E&P: Engineering & procurement: not started
  4. Build: Construction: not started
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Last step done: EPC award
Value
USD 599m [2]
Workforce
not published
Finish
not published
No open adverts linked today
Client, scope, phases, sources

Client: ADNOC Onshore

Value: USD 599 million (Jereh filing, via MEED, 13 Nov 2026) [2]

Scope
  • well tie-ins, mini-pad and well bays, Bab and North East Bab fields [1]
Phase by phase
  • FEED · unknown
  • EPC award · done · Nov 2026 · framework model, 60 months; Robt Stone Middle East with a portion [2]
  • Engineering & procurement · not started
  • Construction · not started
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 guest.meed.com 2 guest.meed.com · checked 26 Nov 2026

ON THE RADARUAE · Onshore oil field

ADNOC Onshore Rumaitha and Shanayel field facilities (North East Bab), 45,000 b/d

Contractors: bidders not named
  1. FEED: FEED: unknown
  2. Award: EPC award: in progress, 6 Nov 2026
  3. E&P: Engineering & procurement: not started
  4. Build: Construction: not started
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: EPC award
Value
not disclosed [1]
Workforce
not published
Finish
not published
No open adverts linked today
Client, scope, phases, sources

Client: ADNOC Onshore

Value: not disclosed [1]

Scope
  • field facilities for 45,000 b/d (Rumaitha and Shanayel, North East Bab) [1]
Phase by phase
  • FEED · unknown
  • EPC award · in progress · 6 Nov 2026 · commercial bid deadline extended, no new date (Attaqa, 6 Nov 2026) [2]
  • Engineering & procurement · not started
  • Construction · not started
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 guest.meed.com 2 attaqa.net · checked 26 Nov 2026

CONFIRMEDMEDIUMOFFSHORESaudi Arabia · Offshore platform

Saudi Aramco: three offshore EPC projects (names and locations not disclosed)

NMDC Energy (EPC)
  1. FEED: FEED: unknown
  2. Award: EPC award: done, 23 Oct 2026
  3. E&P: Engineering & procurement: not started
  4. Build: Construction: not started
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Last step done: EPC award
Value
AED 2.8bn [1]
Workforce
not published
Finish
18 to 23 months from award [1]
No open adverts linked today
Client, scope, phases, sources

Client: Saudi Aramco

Value: AED 2.8 billion (about USD 763 million) [1]

Scope
  • three offshore EPC projects; names and locations not disclosed [1]
Phase by phase
  • FEED · unknown
  • EPC award · done · 23 Oct 2026 · letter of award [1]
  • Engineering & procurement · not started
  • Construction · not started
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 thenationalnews.com · checked 29 Oct 2026

CONFIRMEDMEDIUMSaudi Arabia · Gas compression

Aramco Shedgum-Uthmaniyah gas compression: Uthmaniyah compression plant package

Saipem (SNSH JV, contract share EUR 900m) · Nasser Saeed Al-Hajri & Partners Contracting (SNSH JV)
  1. FEED: FEED: done
  2. Award: EPC award: done, Jun 2026
  3. E&P: Engineering & procurement: in progress, 12 Aug 2026
  4. Build: Construction: not started
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Engineering & procurement
Value
USD 1.2bn [1]
Workforce
not published
Finish
EPC works run for 42 months (from… [1]
No open adverts linked today
Client, scope, phases, sources

Client: Saudi Aramco

Value: about USD 1.24bn (sources, MEED); Saipem share EUR 900m (USD 1.04bn) [1]

Finish: EPC works run for 42 months (from the August 2026 kick-off) [1]

Scope
  • new compression plant for the non-associated Uthmaniyah gas field (now about 1.2 bcfd of Khuff raw gas) [1]
  • one of nine EPC packages of the Shedgum-Uthmaniyah programme [1]
Phase by phase
  • FEED · done
  • EPC award · done · Jun 2026 [1]
  • Engineering & procurement · in progress · 12 Aug 2026 · EPC work kicked off [1]
  • Construction · not started
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 guest.meed.com · checked 29 Oct 2026

CONFIRMEDSaudi Arabia · Pipeline

Ghazlan 1: sales gas delivery system

GAS Arabian Services (EPC)
  1. FEED: FEED: unknown
  2. Award: EPC award: done, 9 Oct 2026
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: not started
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Engineering & procurement
Value
SAR 288m [1]
Workforce
not published
Finish
not published
No open adverts linked today
Client, scope, phases, sources

Client: Saudi Power Procurement Company

Value: above SAR 288 million (about USD 76.8m) [1]

Scope
  • sales gas delivery system to the Ghazlan 1 power plant [1]
Phase by phase
  • FEED · unknown
  • EPC award · done · 9 Oct 2026 [1]
  • Engineering & procurement · in progress
  • Construction · not started
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 tradearabia.com · checked 26 Nov 2026

CONFIRMEDLARGESaudi Arabia · Fertiliser

SABIC Agri-Nutrients SAN-7, Jubail: gas-based ammonia (3,500 t/d) and urea (7,700 t/d)

Samsung E&A (sole EPC)
  1. FEED: FEED: unknown
  2. Award: EPC award: done, 9 Sep 2026
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: not started
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Engineering & procurement
Value
KRW 4700bn [1]
Workforce
EPC Radar estimate est. 8,500-38,900 at peak how?
Finish
2030 [1]
No open adverts linked today
Client, scope, phases, sources

Client: SABIC Agri-Nutrients

Value: KRW 4.7 trillion (about USD 3.5 billion) [1]

Finish: completion scheduled for 2030 [1]

Workforce estimate (low confidence): EPC Radar estimate from 2 published refinery, petrochemical and fertiliser plants projects in this tracker, 2.4-11.1 workers per USD million of declared value (id-rdmp-balikpapan, ar-fertil-pampa), applied to contract value: about USD 3,515 m

Scope
  • 3,500 t/d ammonia [1]
  • 7,700 t/d urea [1]
Phase by phase
  • FEED · unknown
  • EPC award · done · 9 Sep 2026 [1]
  • Engineering & procurement · in progress
  • Construction · not started
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 hydrocarbonprocessing.com · checked 26 Nov 2026

ON THE RADARSaudi Arabia · Gas processing

Aramco Alhada gas processing plant expansion (3 trains, sulphur recovery, utilities)

Contractors: not yet selected (3 EPC packages)
  1. FEED: FEED: unknown
  2. Award: EPC award: not started, 30 Sep 2026
  3. E&P: Engineering & procurement: not started
  4. Build: Construction: not started
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Before the EPC award
Value
not disclosed [1]
Workforce
not published
Finish
not published
No open adverts linked today
Client, scope, phases, sources

Client: Saudi Aramco

Value: not disclosed [1]

Scope
  • 3 gas processing trains, sulphur recovery, utilities [1]
Phase by phase
  • FEED · unknown
  • EPC award · not started · 30 Sep 2026 · expressions of interest received; main tender next [1]
  • Engineering & procurement · not started
  • Construction · not started
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 guest.meed.com · checked 26 Nov 2026

CONFIRMEDLARGENigeria · LNG plant

Nigeria LNG Train 7, Bonny Island (22 to 30 Mtpa)

Saipem (SCD JV) · Chiyoda (SCD JV) · Daewoo E&C (SCD JV)
  1. FEED: FEED: done
  2. Award: EPC award: done, 2020
  3. E&P: Engineering & procurement: unknown
  4. Build: Construction: in progress, 3 Aug 2026
  5. Comm.: Pre-commissioning & commissioning: in progress, May 2026
  6. Start: Start-up: not started
Now: Pre-commissioning & commissioning · 93% complete (Aug 2026) [2]
93%
Value
USD 5bn [1]
Workforce
over 13,000 Nigerians employed on Train 7 at peak construction (NLNG project director, ThisDay, May 2026); NLNG's CEO cited 16,000 direct jobs on site [1]
Finish
2027 [3]
Open jobs today · 3 open adverts
All open jobs on this project ›
Client, scope, phases, sources

Client: Nigeria LNG (NNPC, Shell, TotalEnergies, Eni)

Value: USD 5 billion project (ThisDay, May 2026) [1]

Finish: plans to commission the new facility in 2027 (NLNG CEO) [3]

Scope
  • NLNG capacity from 22 to 30 Mtpa (+35%) [2]
  • Bonny Island, Rivers State [2]
Phase by phase

Progress: 93 per cent completion (NLNG Facts and Figures 2026, 3 Aug 2026) [2]

  • FEED · done
  • EPC award · done · 2020 [2]
  • Engineering & procurement · unknown
  • Construction · in progress · 3 Aug 2026 · 93% overall [2]
  • Pre-commissioning & commissioning · in progress · May 2026 · systems completion and pre-commissioning [1]
  • Start-up · not started

Sources: 1 thisdaylive.com 2 shippingposition.com.ng 3 leadership.ng · checked 26 Nov 2026

CONFIRMEDMEDIUMOFFSHORENigeria · Subsea

Shell Bonga North deepwater tie-back to the Bonga FPSO

Saipem (leader, share close to USD 900m) · KOA Oil & Gas · AVEON Offshore
  1. FEED: FEED: done
  2. Award: EPC award: done, 19 Dec 2024
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: in progress
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Construction
Value
USD 1bn [1]
Workforce
not published
Finish
2030 [2]
No open adverts linked today
Client, scope, phases, sources

Client: Shell Nigeria Exploration and Production Co. (SNEPCo)

Value: about USD 1 billion; Saipem share close to USD 900 million [1]

Finish: first oil 'by the end of the decade' (Shell FID, Dec 2024) [2]

Scope
  • 16 wells (8 production, 8 water injection); peak 110,000 b/d of oil; over 300 MMboe [2]
  • subsea tie-back 130 km offshore to the Bonga FPSO [1]
Phase by phase
  • FEED · done
  • EPC award · done · 19 Dec 2024 · FID 16 Dec 2024 [1]
  • Engineering & procurement · in progress
  • Construction · in progress
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 offshore-mag.com 2 ogj.com · checked 29 Oct 2026

ON THE RADARLARGENigeria · Refinery

Dangote refinery expansion, Lekki: 650,000 to 1.4 million b/d

Engineers India (EIL) (PMC and EPCM, USD 350m) · construction contractors not yet named
  1. FEED: FEED: unknown
  2. Award: EPC award: in progress, 20 Jan 2026
  3. E&P: Engineering & procurement: unknown
  4. Build: Construction: unknown
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: EPC award
Value
USD 14.3bn [1]
Workforce
about 95,000 skilled workers expected on site at the peak of construction (Aliko Dangote, 24 Apr 2026) [3]
Finish
2029 [1]
No open adverts linked today
Client, scope, phases, sources

Client: Dangote Industries

Value: USD 14.3 billion expansion plan (IPO documents, Sep 2026); EIL PMC/EPCM contract USD 350m [1]

Finish: due to be complete by 2029 (IPO prospectus, Reuters via Hydrocarbon Processing) [1]

Scope
  • refinery from 700,000 to 1.4 million b/d [1]
Phase by phase
  • FEED · unknown
  • EPC award · in progress · 20 Jan 2026 · PMC/EPCM appointed; construction contractors not named [2]
  • Engineering & procurement · unknown
  • Construction · unknown
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 hydrocarbonprocessing.com 2 industrialinfo.com 3 financialedge.com.ng · checked 26 Nov 2026

REPORTEDMEDIUMOFFSHORENigeria · Offshore platform

Ima gas project (OMLs 112/117): offshore platform + 22 km pipeline to NLNG

Aveon Offshore (EPCC, CSP package, with 2H Offshore) · 2H Offshore (Acteon) (offshore engineering and project management, CSP package)
  1. FEED: FEED: done
  2. Award: EPC award: in progress, 31 Oct 2026
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: not started
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Engineering & procurement
Value
USD 800m [1]
Workforce
not published
Finish
2028 [1]
No open adverts linked today
Client, scope, phases, sources

Client: TotalEnergies (operator, 40%) and AMNI International (60%)

Value: around USD 800 million (Nigerian government); TotalEnergies' share more than USD 600 million [1]

Finish: first gas targeted for 2028 [1]

Scope
  • about 350 MMscfd of gas at plateau [1]
  • offshore platform + 22 km pipeline to Nigeria LNG [1]
Phase by phase
  • FEED · done
  • EPC award · in progress · 31 Oct 2026 · CSP package to Aveon Offshore and 2H Offshore; other packages not published [2]
  • Engineering & procurement · in progress
  • Construction · not started
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 chemanalyst.com 2 energyfocusreport.com · checked 26 Nov 2026

CONFIRMEDOFFSHOREMozambique · Floating LNG (FLNG)

Coral Norte FLNG (3.6 Mtpa), Area 4 offshore

Technip Energies (EPCIC) · JGC (EPCIC partner) · Samsung Heavy Industries (EPCIC partner, hull)
  1. FEED: FEED: done
  2. Award: EPC award: done, 11 Jun 2026
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: in progress
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Construction
Value
not disclosed [1]
Workforce
not published
Finish
2028 [2]
No open adverts linked today
Client, scope, phases, sources

Client: Mozambique Rovuma Venture (Eni with CNPC, ENH, XRG, KOGAS)

Value: not disclosed [1]

Finish: on track to start production by 2028 (Eni, Oct 2026) [2]

Scope
  • FLNG of about 3.6 Mtpa, doubling the Coral hub to 7 Mtpa [1]
  • up to six development wells drilled from November 2026 [2]
Phase by phase
  • FEED · done
  • EPC award · done · 11 Jun 2026 [1]
  • Engineering & procurement · in progress
  • Construction · in progress · hull built in Korea [1]
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 hydrocarbonprocessing.com 2 oedigital.com · checked 26 Nov 2026

ON THE RADARMozambique · LNG plant

Rovuma LNG phase 1, onshore: 12 modular trains, 18.6 Mtpa (Afungi)

Saipem (SMDC JV) · McDermott (SMDC JV) · Daewoo E&C (SMDC JV) · CPECC (SMDC JV)
  1. FEED: FEED: unknown
  2. Award: EPC award: in progress, 10 Aug 2026
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: not started
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Engineering & procurement
Value
not disclosed [1]
Workforce
not published for the plant alone; ExxonMobil: about 7,500 Mozambicans in the Rovuma LNG construction phase (see upstream entry) [2]
Finish
2031 [1]
No open adverts linked today
Client, scope, phases, sources

Client: Area 4 partners (ExxonMobil for Mozambique Rovuma Venture)

Value: not disclosed [1]

Finish: start-up anticipated in 2031 (ExxonMobil) [1]

Scope
  • 12 modular liquefaction modules, 18.6 Mtpa [1]
Phase by phase
  • FEED · unknown
  • EPC award · in progress · 10 Aug 2026 · letter of intent for limited engineering and procurement; FID expected 2026 [1]
  • Engineering & procurement · in progress
  • Construction · not started
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 corporate.exxonmobil.com 2 corporate.exxonmobil.com · checked 26 Nov 2026

ON THE RADAROFFSHOREMozambique · Subsea

Rovuma LNG upstream: 18 wells, subsea pipelines and manifolds; Pemba shorebase

Saipem (upstream EPCI consortium, LOI) · Jan De Nul (upstream EPCI consortium, LOI) · CFML Logistic (Pemba shorebase land and infrastructure) · Alistair Group Mozambique (shorebase logistics)
  1. FEED: FEED: unknown
  2. Award: EPC award: in progress, 10 Sep 2026
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: not started
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Engineering & procurement
Value
not disclosed (ExxonMobil cites… [1]
Workforce
approximately 7,500 Mozambicans during the construction phase (ExxonMobil, 10 Sep 2026) [1]
Finish
2031 [2]
No open adverts linked today
Client, scope, phases, sources

Client: Area 4 partners (ExxonMobil for Mozambique Rovuma Venture)

Value: not disclosed (ExxonMobil cites about USD 6 billion of economic activity in Mozambique) [1]

Finish: Rovuma LNG start-up anticipated in 2031 (ExxonMobil) [2]

Scope
  • 18 wells, subsea pipelines and manifolds [1]
  • shorebase at the Pemba Bulk Terminal [1]
Phase by phase
  • FEED · unknown
  • EPC award · in progress · 10 Sep 2026 · letter of intent; final award after FID [1]
  • Engineering & procurement · in progress
  • Construction · not started
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 corporate.exxonmobil.com 2 corporate.exxonmobil.com · checked 29 Oct 2026

CONFIRMEDLARGEOFFSHOREIndonesia · FPSO

Kutei North Hub (Geng North, Gehem) FPSO, off East Kalimantan

PT Saipem Indonesia (EPCI JV) · PT Tripatra Engineers and Constructors (EPCI JV)
  1. FEED: FEED: done
  2. Award: EPC award: done, 8 Jul 2026
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: unknown
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Engineering & procurement
Value
USD 2bn [1]
Workforce
not published
Finish
EPCI duration about 48 months… [1]
Open jobs today · 1 open advert
All open jobs on this project ›
Client, scope, phases, sources

Client: Eni North Ganal (Searah: Eni + Petronas)

Value: about USD 2 billion for Saipem's share [1]

Finish: EPCI duration about 48 months from July 2026 [1]

Scope
  • FPSO for the Geng North and Gehem fields, off East Kalimantan [1]
Phase by phase
  • FEED · done
  • EPC award · done · 8 Jul 2026 [1]
  • Engineering & procurement · in progress
  • Construction · unknown
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 ogj.com · checked 29 Oct 2026

CONFIRMEDMEDIUMOFFSHOREIndonesia · Offshore platform

Tangguh Ubadari CCUS and compression (UCC), Papua Barat: 3 platforms, 90 km pipelines

Saipem (EPCI, share about USD 1bn) · PT Meindo Elang Indah (EPCI partner)
  1. FEED: FEED: done
  2. Award: EPC award: done, 27 Nov 2024
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: in progress
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Construction
Value
USD 1.2bn [1]
Workforce
not published
Finish
2028 [2]
No open adverts linked today
Client, scope, phases, sources

Client: BP Berau

Value: approximately USD 1.2bn; Saipem share around USD 1bn (project USD 7 billion) [1]

Finish: Ubadari production should start in 2028 (bp, FID Nov 2024) [2]

Scope
  • 2 wellhead production platforms + 1 CO2 reinjection platform; about 90 km of pipelines [1]
  • about 15 Mt of CO2 sequestered in the first phase; Ubadari about 3 tcf [2]
Phase by phase
  • FEED · done
  • EPC award · done · 27 Nov 2024 [1]
  • Engineering & procurement · in progress
  • Construction · in progress · platforms fabricated at Saipem Karimun yard [1]
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 offshore-technology.com 2 offshore-mag.com · checked 29 Oct 2026

ON THE RADAROFFSHOREIndonesia · LNG plant

Abadi LNG, Masela block: onshore LNG, FPSO, SURF, export pipeline

Saipem (FEED) · Tripatra (FEED) · McDermott (FEED) · Technip (FEED) · JGC (FEED) · KBR Indonesia (FEED) · Adhi Karya (FEED) · Samsung E&A (FEED) · Worley (FEED) · dual FEED: the winning group gets the EPC
  1. FEED: FEED: done, 27 Oct 2026
  2. Award: EPC award: not started
  3. E&P: Engineering & procurement: not started
  4. Build: Construction: unknown, Jul 2026
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Last step done: FEED
Value
not disclosed [1]
Workforce
estimated around 12,000 direct workers during construction (Antara, Jul 2026) [2]
Finish
first gas 2029-2030 (Dunia… [1]
No open adverts linked today
Client, scope, phases, sources

Client: INPEX Masela

Value: not disclosed [1]

Finish: first gas 2029-2030 (Dunia Energi, Oct 2026) [1]

Scope
  • onshore LNG of 9.5 Mtpa, plus FPSO, SURF and export pipeline [2]
Phase by phase
  • FEED · done · 27 Oct 2026 [1]
  • EPC award · not started · FID by end of January 2027 [1]
  • Engineering & procurement · not started
  • Construction · unknown · Jul 2026 · groundbreaking held July 2026; main EPC not awarded [2]
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 dunia-energi.com 2 en.antaranews.com · checked 26 Nov 2026

CONFIRMEDLARGEIndonesia · Refinery

Pertamina RDMP Balikpapan refinery upgrade, 260,000 to 360,000 b/d

Hyundai Engineering (EPC, 2019 contract)
  1. FEED: FEED: done
  2. Award: EPC award: done, 17 Sep 2019
  3. E&P: Engineering & procurement: done
  4. Build: Construction: done
  5. Comm.: Pre-commissioning & commissioning: done
  6. Start: Start-up: in progress, 12 Jan 2026
Now: Start-up
Value
USD 2.2bn [1]
Workforce
the number of workers involved reached 24 thousand people at peak construction (Pertamina, Nov 2025) [2]
Finish
Jan 2026 [1]
No open adverts linked today
Client, scope, phases, sources

Client: Pertamina (PT Kilang Pertamina Balikpapan)

Value: EPC USD 2.17bn (2019); project Rp 123 trillion [1]

Finish: inaugurated 12 January 2026; ramp-up under way [1]

Scope
  • refinery from 260,000 to 360,000 b/d [1]
Phase by phase
  • FEED · done
  • EPC award · done · 17 Sep 2019 [3]
  • Engineering & procurement · done
  • Construction · done
  • Pre-commissioning & commissioning · done
  • Start-up · in progress · 12 Jan 2026 · inaugurated 12 Jan 2026; ramp-up [1]

Sources: 1 hydrocarbonengineering.com 2 kpb.pertamina.com 3 ogj.com · checked 26 Nov 2026

CONFIRMEDLARGEChina · Petrochemical

Sinopec Maoming refinery transformation and ethylene upgrade (ethylene 1.0 to 1.64 Mtpa)

Sinopec Engineering (SEI) (design lead; 3 Mtpa catalytic cracker and 1 Mtpa ethylene unit) · Sinopec Nanjing Engineering · Sinopec Shanghai Engineering · Sinopec Guangzhou Engineering · Sinopec Ningbo Engineering · Maoming Ruipai Petrochemical Engineering
  1. FEED: FEED: done
  2. Award: EPC award: done
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: in progress, Jun 2026
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Construction · 63% complete (Jun 2026) [1]
63%
Value
CNY 30bn [1]
Workforce
not published
Finish
not published
No open adverts linked today
Client, scope, phases, sources

Client: Sinopec Maoming

Value: over RMB 30 billion (project) [1]

Scope
  • ethylene from 1.0 to 1.64 Mtpa [1]
  • 3 Mtpa catalytic cracker and 1 Mtpa ethylene unit [1]
Phase by phase

Progress: 63% overall; 103 of 107 main units started, 9 mechanically complete (Jun 2026) [1]

  • FEED · done
  • EPC award · done
  • Engineering & procurement · in progress
  • Construction · in progress · Jun 2026 · all heavy lifts done [1]
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 t.cj.sina.com.cn · checked 26 Nov 2026

CONFIRMEDLARGEChina · Refinery

Huajin Aramco Petrochemical (HAPCO), Panjin: 15 Mtpa refinery + 1.65 Mtpa ethylene; coal-to-hydrogen unit

China Chemical Engineering Second Construction (coal-to-hydrogen unit)
  1. FEED: FEED: done
  2. Award: EPC award: done
  3. E&P: Engineering & procurement: done
  4. Build: Construction: done, 28 Apr 2026
  5. Comm.: Pre-commissioning & commissioning: in progress, 15 Oct 2026
  6. Start: Start-up: not started
Now: Pre-commissioning & commissioning
Value
CNY 83.7bn [1]
Workforce
not published
Finish
start of operations not dated;… [2]
No open adverts linked today
Client, scope, phases, sources

Client: Huajin Aramco Petrochemical (Norinco, Aramco, Panjin Xincheng)

Value: RMB 83.7 billion (project) [1]

Finish: start of operations not dated; complex in pre-production preparation (Oct 2026) [2]

Scope
  • 300,000 b/d refinery and 1.65 Mtpa ethylene [2]
  • coal-to-hydrogen unit handed over 28 Apr 2026 [1]
Phase by phase
  • FEED · done
  • EPC award · done
  • Engineering & procurement · done
  • Construction · done · 28 Apr 2026 · coal-to-hydrogen unit handover [1]
  • Pre-commissioning & commissioning · in progress · 15 Oct 2026 · pre-production preparation; first Arabian crude arrived 9 Oct 2026 [2]
  • Start-up · not started

Sources: 1 mtz.china.com 2 hydrocarbonengineering.com · checked 26 Nov 2026

CONFIRMEDChina · Refinery

Northern Huajin Union Petrochemical: 2.6 Mtpa product refining unit (Panjin)

China Chemical Engineering No.16 Construction (4th branch) (construction)
  1. FEED: FEED: done
  2. Award: EPC award: done
  3. E&P: Engineering & procurement: done
  4. Build: Construction: done, 2 Jul 2026
  5. Comm.: Pre-commissioning & commissioning: unknown
  6. Start: Start-up: not started
Last step done: Construction
Value
not disclosed [1]
Workforce
not published
Finish
not published
No open adverts linked today
Client, scope, phases, sources

Client: Northern Huajin Union Petrochemical

Value: not disclosed [1]

Scope
  • 2.6 Mtpa product refining unit, Panjin [1]
Phase by phase
  • FEED · done
  • EPC award · done
  • Engineering & procurement · done
  • Construction · done · 2 Jul 2026 · intermediate handover [1]
  • Pre-commissioning & commissioning · unknown
  • Start-up · not started

Sources: 1 cn.chinadaily.com.cn · checked 29 Oct 2026

CONFIRMEDLARGEChina · Petrochemical

SABIC Fujian petrochemical complex, Gulei: 1.8 Mtpa ethylene, 16 derivative units

CTCI Beijing (EPC of the bimodal HDPE unit (Feb 2024)) · not named in the sources we read
  1. FEED: FEED: done
  2. Award: EPC award: done
  3. E&P: Engineering & procurement: done
  4. Build: Construction: done
  5. Comm.: Pre-commissioning & commissioning: in progress, 26 Oct 2026
  6. Start: Start-up: not started
Now: Pre-commissioning & commissioning · 87% complete (30 Sep 2025) [1]
87%
Value
USD 6.4bn [1]
Workforce
not published
Finish
2026 [2]
No open adverts linked today
Client, scope, phases, sources

Client: SABIC with Fujian Energy Petrochemical

Value: about USD 6.4 billion (project) [1]

Finish: on track for full startup during Q4 2026 (SABIC CEO, 26 Oct 2026) [2]

Scope
  • 1.8 Mtpa ethylene and 16 derivative units, Gulei [1]
Phase by phase

Progress: 87% at end of Q3 2025 (SABIC) [1]

  • FEED · done
  • EPC award · done
  • Engineering & procurement · done
  • Construction · done
  • Pre-commissioning & commissioning · in progress · 26 Oct 2026 · three PE/PP plants completed trial runs [2]
  • Start-up · not started

Sources: 1 argaam.com 2 arabnews.pk 3 nsenergybusiness.com · checked 26 Nov 2026

CONFIRMEDLARGEOFFSHOREQatar · Offshore platform

QatarEnergy Bul Hanine offshore redevelopment: 60+ facilities, 40 subsea pipelines and cables

COOEC (China Offshore Oil Engineering) (EPIC)
  1. FEED: FEED: done
  2. Award: EPC award: done, 2025
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: in progress, 15 Sep 2026
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Construction
Value
USD 4bn [1]
Workforce
not published
Finish
not published
No open adverts linked today
Client, scope, phases, sources

Client: QatarEnergy

Value: approximately USD 4 billion [1]

Scope
  • more than 60 offshore facilities and 40 subsea pipelines and cables [1]
Phase by phase
  • FEED · done
  • EPC award · done · 2025 [1]
  • Engineering & procurement · in progress
  • Construction · in progress · 15 Sep 2026 · fabrication started in Qingdao [1]
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 constructionreviewonline.com · checked 29 Oct 2026

REPORTEDLARGEOFFSHOREKuwait / Saudi Arabia · Offshore platform

Dorra offshore gas field (Al-Khafji Joint Operations)

McDermott (offshore package 2A) · L&T Energy Hydrocarbon (package 2B with Saipem; package 1) · Saipem (package 2B with L&T) · Tecnicas Reunidas (onshore package 3, lowest bidder)
  1. FEED: FEED: done
  2. Award: EPC award: in progress, 12 Aug 2026
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: unknown
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Engineering & procurement
Value
package 2A about USD 1.5bn… [1]
Workforce
not published
Finish
not published
No open adverts linked today
Client, scope, phases, sources

Client: Al-Khafji Joint Operations (Aramco Gulf Operations + Kuwait Gulf Oil Co.)

Value: package 2A about USD 1.5bn (McDermott); package 2B about USD 3.7bn (L&T + Saipem), MEED [1]

Scope
  • 1 bcfd of gas produced jointly by Saudi Arabia and Kuwait [1]
Phase by phase
  • FEED · done
  • EPC award · in progress · 12 Aug 2026 · offshore packages awarded; onshore pending [1]
  • Engineering & procurement · in progress
  • Construction · unknown
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 guest.meed.com · checked 29 Oct 2026

CONFIRMEDMEDIUMIraq · Gas processing

Ratawi gas processing complex (Gas Growth Integrated Project), 300 MMcf/d

CPECC (EPC, May 2025) · KBR (FEED)
  1. FEED: FEED: done
  2. Award: EPC award: done, May 2025
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: in progress, 21 May 2026
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Construction
Value
USD 1.6bn [1]
Workforce
not published
Finish
not published
No open adverts linked today
Client, scope, phases, sources

Client: TotalEnergies (operator) with Basra Oil Co. and QatarEnergy

Value: USD 1.61bn project [1]

Scope
  • 300 MMcfd gas processing [1]
Phase by phase
  • FEED · done
  • EPC award · done · May 2025 [1]
  • Engineering & procurement · in progress
  • Construction · in progress · 21 May 2026 · foundations under construction [1]
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 guest.meed.com · checked 29 Oct 2026

CONFIRMEDOman · Onshore oil field

PDO Block 6 EPC framework: Raba hub, Wadi Umairi, Rabab Harweel tranche 2, Bout, Dulaima, Makarem, Amal South-East, Hawqa Hasirah

L&T Energy Hydrocarbon Onshore (one of four framework contractors) · other three not named
  1. FEED: FEED: unknown
  2. Award: EPC award: done, 31 Jul 2026
  3. E&P: Engineering & procurement: unknown
  4. Build: Construction: unknown
  5. Comm.: Pre-commissioning & commissioning: unknown
  6. Start: Start-up: unknown
Last step done: EPC award
Value
USD 6bn [1]
Workforce
not published
Finish
framework runs 6 years from July… [1]
No open adverts linked today
Client, scope, phases, sources

Client: Petroleum Development Oman (PDO)

Value: up to USD 6bn for the framework [1]

Finish: framework runs 6 years from July 2026 [1]

Scope
  • 6-year EPC framework: Raba hub, Wadi Umairi, Rabab Harweel tranche 2, Bout, Dulaima, Makarem, Amal South-East, Hawqa Hasirah [1]
Phase by phase
  • FEED · unknown
  • EPC award · done · 31 Jul 2026 · framework agreed; projects tendered inside the pool [1]
  • Engineering & procurement · unknown
  • Construction · unknown
  • Pre-commissioning & commissioning · unknown
  • Start-up · unknown

Sources: 1 guest.meed.com · checked 29 Oct 2026

CONFIRMEDOFFSHOREIvory Coast · FPSO

Baleine Phase 3: new FPSO + subsea (150,000 b/d oil, 200 MMscf/d gas field total)

Saipem (SURF EPCI) · Wison New Energies (FPSO EPCIC, owner Altera)
  1. FEED: FEED: done
  2. Award: EPC award: done, 29 Jul 2026
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: unknown
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Engineering & procurement
Value
Saipem: about USD 930 million of… [1]
Workforce
not published
Finish
offshore construction expected to… [1]
No open adverts linked today
Client, scope, phases, sources

Client: Eni (with Petroci, Vitol)

Value: Saipem: about USD 930 million of new Eni contracts led by Baleine Phase 3; project value not disclosed [1]

Finish: offshore construction expected to take about three years (Jul 2026) [1]

Scope
  • new FPSO + subsea production infrastructure, flowlines, risers, umbilicals [1]
  • field total 150,000 b/d oil, 200 MMscfd gas [1]
Phase by phase
  • FEED · done
  • EPC award · done · 29 Jul 2026 · FID May 2026 [1]
  • Engineering & procurement · in progress
  • Construction · unknown
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 worldoil.com · checked 29 Oct 2026

REPORTEDLARGEOFFSHOREAngola · FPSO

TotalEnergies Kaminho (Cameia, Golfinho), Block 20/11: converted FPSO, 70,000 b/d

Saipem (FPSO, named in Saipem/GPS AG adverts)
  1. FEED: FEED: done
  2. Award: EPC award: done, 2024
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: in progress, 22 Apr 2025
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Construction
Value
USD 6bn [1]
Workforce
not published
Finish
2028 [1]
No open adverts linked today
Client, scope, phases, sources

Client: TotalEnergies (40%), Petronas (40%), Sonangol (20%)

Value: USD 6 billion (project) [1]

Finish: production planned for 2028 [1]

Scope
  • converted FPSO, 70,000 b/d (Cameia and Golfinho, Block 20/11) [1]
Phase by phase
  • FEED · done
  • EPC award · done · 2024 · FID May 2024 [2]
  • Engineering & procurement · in progress
  • Construction · in progress · 22 Apr 2025 · FPSO conversion in Nantong, China [1]
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 inspenet.com 2 offshore-technology.com · checked 29 Oct 2026

CONFIRMEDOFFSHORECyprus · Subsea

Eni Cronos gas development, Block 6 (to Zohr and Damietta LNG, Egypt), 500 MMscf/d

McDermott (subsea, USD 500-750m) · Petrojet (Egypt) (main contractor, 57 km 36-inch onshore pipeline Zohr facilities-Damietta LNG; also USD 11m subsea structures for McDermott) · other contractors at the Nicosia signing (Baker Hughes, Saipem, Technip, Oceaneering, Tenaris...) not broken down by package
  1. FEED: FEED: done
  2. Award: EPC award: done, 8 Sep 2026
  3. E&P: Engineering & procurement: in progress, 26 Oct 2026
  4. Build: Construction: not started
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Engineering & procurement
Value
not disclosed by Eni; McDermott… [1]
Workforce
not published
Finish
2028 [2]
No open adverts linked today
Client, scope, phases, sources

Client: Eni Cyprus (50%) with TotalEnergies

Value: not disclosed by Eni; McDermott subsea award USD 500-750 million [1]

Finish: first gas H1 2028 (Eni) [2]

Scope
  • 500 MMscfd, Block 6, gas processed via Zohr and Damietta LNG (Egypt) [2]
  • Egypt onshore section: 57 km, 36-inch pipeline from Zohr facilities to Damietta liquefaction plant (Petrojet, 3 Nov 2026) [3]
Phase by phase
  • FEED · done
  • EPC award · done · 8 Sep 2026 · FID 28 Jul 2026 [1]
  • Engineering & procurement · in progress · 26 Oct 2026 · execution phase launched [2]
  • Construction · not started
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 worldoil.com 2 eni.com 3 egyptoil-gas.com · checked 12 Nov 2026

CONFIRMEDOFFSHORERomania · Offshore platform

Neptun Deep, Black Sea: Neptun Alpha platform, 10 wells, 160 km pipeline

Saipem (EPCIC: jacket, topsides, installation, pipeline)
  1. FEED: FEED: done
  2. Award: EPC award: done
  3. E&P: Engineering & procurement: done
  4. Build: Construction: in progress, 10 Oct 2026
  5. Comm.: Pre-commissioning & commissioning: unknown
  6. Start: Start-up: not started
Now: Construction
Value
not stated in the source [1]
Workforce
not published
Finish
2027 [1]
Open jobs today · 1 open advert
All open jobs on this project ›
Client, scope, phases, sources

Client: OMV Petrom (50%) and Romgaz (50%)

Value: not stated in the source [1]

Finish: first gas H1 2027 [1]

Scope
  • Neptun Alpha platform, 10 wells, 160 km pipeline to shore [1]
Phase by phase
  • FEED · done
  • EPC award · done
  • Engineering & procurement · done
  • Construction · in progress · 10 Oct 2026 · platform installed Jul 2026; 7 of 10 wells done [1]
  • Pre-commissioning & commissioning · unknown
  • Start-up · not started

Sources: 1 offshore-mag.com · checked 29 Oct 2026

ON THE RADAROFFSHORENorway · FPSO

Equinor Wisting (Barents Sea): FPSO topsides

Aibel (FEED for FPSO topsides, option for engineering, procurement and project management)
  1. FEED: FEED: in progress, 22 Oct 2026
  2. Award: EPC award: not started
  3. E&P: Engineering & procurement: not started
  4. Build: Construction: not started
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: FEED
Value
not disclosed [1]
Workforce
approximately 250 people will be involved (Aibel, FEED contract) [1]
Finish
not published
No open adverts linked today
Client, scope, phases, sources

Client: Equinor (42.5%) with Aker BP, Petoro, INPEX Idemitsu

Value: not disclosed [1]

Scope
  • FEED for the topsides of the production vessel (Barents Sea) [1]
Phase by phase
  • FEED · in progress · 22 Oct 2026 [1]
  • EPC award · not started · investment decision planned for late 2027 [1]
  • Engineering & procurement · not started
  • Construction · not started
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 equinor.com · checked 29 Oct 2026

CONFIRMEDLARGEKazakhstan · Petrochemical

Silleno polyethylene plant, Atyrau: 1.25 Mtpa

Tecnimont (MAIRE) (polymerisation and offsites EPC, with Sinopec Shanghai Engineering) · Sinopec Shanghai Engineering (with Tecnimont) · pyrolysis unit contractor not named
  1. FEED: FEED: done
  2. Award: EPC award: done, 2 Sep 2025
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: in progress, 30 Sep 2026
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Construction · 39% complete (Sep 2026) [1]
39%
Value
USD 7.7bn [1]
Workforce
not published
Finish
completion 2028-2029 (Trend, Sep… [1]
No open adverts linked today
Client, scope, phases, sources

Client: Silleno LLP (KazMunayGas 40%, SIBUR 30%, Sinopec 30%)

Value: about USD 7.7bn (project) [1]

Finish: completion 2028-2029 (Trend, Sep 2026) [1]

Scope
  • 1.25 Mtpa polyethylene, Atyrau [1]
Phase by phase

Progress: construction above 39% (Sep 2026) [1]

  • FEED · done
  • EPC award · done · 2 Sep 2025 [2]
  • Engineering & procurement · in progress
  • Construction · in progress · 30 Sep 2026 [1]
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 trend.az 2 hydrocarbonprocessing.com · checked 29 Oct 2026

CONFIRMEDLARGECanada · LNG plant

LNG Canada Phase 2, Kitimat: 2 trains + 1 tank (to about 28 Mtpa)

Fluor Canada (JGC Fluor BC LNG II JV, 50%) · JGC Constructors (JGC Fluor BC LNG II JV, 50%)
  1. FEED: FEED: done
  2. Award: EPC award: done, 1 Oct 2026
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: not started
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Engineering & procurement
Value
USD 7.5bn [1]
Workforce
more than 4,000 direct jobs in the construction phase alone (Government of Canada, 29 Sep 2026) [2]
Finish
not published
No open adverts linked today
Client, scope, phases, sources

Client: LNG Canada (Shell 40%, Petronas 25%, PetroChina 15%, Mitsubishi 15%, KOGAS 5%)

Value: Fluor's share USD 7.5 billion of a multibillion-dollar contract; project USD 33 billion (Government of Canada) [1]

Scope
  • 2 liquefaction trains + 1 storage tank, terminal to about 28 Mtpa [1]
Phase by phase
  • FEED · done
  • EPC award · done · 1 Oct 2026 · FID 29 Sep 2026; notice to proceed [1]
  • Engineering & procurement · in progress
  • Construction · not started
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 energy-pedia.com 2 pm.gc.ca · checked 29 Oct 2026

ON THE RADARLARGEUnited States · Pipeline

Kinder Morgan Southeast Connector: about 470 miles, up to 2.6 bcf/d

Contractors: construction contractors not named
  1. FEED: FEED: unknown
  2. Award: EPC award: not started
  3. E&P: Engineering & procurement: not started
  4. Build: Construction: not started
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Before the EPC award
Value
USD 3.1bn [1]
Workforce
not published
Finish
2030 [1]
No open adverts linked today
Client, scope, phases, sources

Client: Southern Natural Gas (Kinder Morgan)

Value: USD 3.1 billion (project) [1]

Finish: service expected to begin in phases from Q4 2030, subject to permits [1]

Scope
  • about 470 miles of new pipeline [1]
  • up to 2.6 bcfd [1]
Phase by phase
  • FEED · unknown
  • EPC award · not started · FID 22 Oct 2026; contractors not named [1]
  • Engineering & procurement · not started
  • Construction · not started
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 ogj.com · checked 29 Oct 2026

CONFIRMEDOFFSHOREBrazil · FPSO

Petrobras Buzios FPSOs P-80 and P-82 (+450,000 b/d together)

Seatrium (turnkey FPSOs)
  1. FEED: FEED: done
  2. Award: EPC award: done
  3. E&P: Engineering & procurement: done
  4. Build: Construction: done, 27 Aug 2026
  5. Comm.: Pre-commissioning & commissioning: in progress
  6. Start: Start-up: not started
Now: Pre-commissioning & commissioning
Value
not stated in the source [1]
Workforce
not published
Finish
2027 [1]
No open adverts linked today
Client, scope, phases, sources

Client: Petrobras

Value: not stated in the source [1]

Finish: production in 2027 [1]

Scope
  • two FPSOs, +450,000 b/d together, Buzios pre-salt [1]
Phase by phase
  • FEED · done
  • EPC award · done
  • Engineering & procurement · done
  • Construction · done · 27 Aug 2026 · christened in Singapore; P-80 and P-82 sailed Sep-Oct 2026 [1]
  • Pre-commissioning & commissioning · in progress
  • Start-up · not started

Sources: 1 worldoil.com · checked 29 Oct 2026

CONFIRMEDLARGEOFFSHOREGuyana · FPSO

ExxonMobil Whiptail (Stabroek block, 6th project): 250,000 b/d, FPSO Jaguar

Saipem (subsea) · EnerMech (pre-commissioning subcontract) · FPSO builder not named in the sources we read
  1. FEED: FEED: done
  2. Award: EPC award: done
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: in progress, 13 Jan 2026
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Construction
Value
USD 12.7bn [1]
Workforce
not published
Finish
2027 [1]
No open adverts linked today
Client, scope, phases, sources

Client: ExxonMobil Guyana

Value: USD 12.7 billion (project) [1]

Finish: start-up targeted by end of 2027 [1]

Scope
  • 250,000 b/d, FPSO Jaguar, Stabroek block [1]
Phase by phase
  • FEED · done
  • EPC award · done
  • Engineering & procurement · in progress
  • Construction · in progress · 13 Jan 2026 · subsea installation [1]
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 worldoil.com · checked 29 Oct 2026

CONFIRMEDMEDIUMArgentina · Fertiliser

Fertil Pampa urea complex, Bahia Blanca: ammonia + 2 urea trains (6,000 t/d)

Tecnimont (MAIRE) (engineering, procurement, commissioning, start-up) · Nextchem (technology, EUR 140m) · SACDE (construction)
  1. FEED: FEED: done
  2. Award: EPC award: done, 20 Jul 2026
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: not started
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Engineering & procurement
Value
EUR 1.3bn [1]
Workforce
more than 3,500 direct jobs at peak construction (MAIRE) [1]
Finish
completion expected in 41 months… [1]
Open jobs today · 1 open advert
All open jobs on this project ›
Client, scope, phases, sources

Client: Fertil Pampa (Pampa Energia)

Value: approximately EUR 1.3 billion, of which EUR 140 million Nextchem technology [1]

Finish: completion expected in 41 months (from July 2026) [1]

Scope
  • ammonia plant + 2 urea trains, 6,000 t/d (2.1 Mtpa) [1]
Phase by phase
  • FEED · done
  • EPC award · done · 20 Jul 2026 [1]
  • Engineering & procurement · in progress
  • Construction · not started
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 hydrocarbonprocessing.com · checked 29 Oct 2026

CONFIRMEDMEDIUMVietnam · Refinery

Dung Quat refinery upgrade and expansion, 148,000 to 171,000 b/d

China Chengda Engineering (EPC consortium) · Beijing Petrochemical Engineering (EPC consortium) · Wood (PMC, with Petrovietnam Engineering) · Petrovietnam Engineering (PMC)
  1. FEED: FEED: done
  2. Award: EPC award: done, Aug 2026
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: unknown
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Engineering & procurement
Value
USD 1.5bn [1]
Workforce
not published
Finish
2028 [1]
No open adverts linked today
Client, scope, phases, sources

Client: Binh Son Refining and Petrochemical (BSR, Petrovietnam)

Value: USD 1.489bn [1]

Finish: commercial operation 2028 [1]

Scope
  • refinery from 148,000 to 171,000 b/d [1]
  • EPC duration 37 months [1]
Phase by phase
  • FEED · done
  • EPC award · done · Aug 2026 [1]
  • Engineering & procurement · in progress
  • Construction · unknown
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 ogj.com · checked 29 Oct 2026

CONFIRMEDOFFSHOREBrazil · FPSO

Petrobras Buzios 11: FPSO P-83 (225,000 b/d)

Seatrium (FPSO newbuild)
  1. FEED: FEED: done
  2. Award: EPC award: done
  3. E&P: Engineering & procurement: done
  4. Build: Construction: in progress
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Construction
Value
not published
Workforce
not published
Finish
2027 [1]
No open adverts linked today
Client, scope, phases, sources

Client: Petrobras (88.99%) with Buzios partners

Value: not published

Finish: start-up 2027 (Petrobras 2Q26 report) [1]

Scope
  • FPSO, 225,000 b/d oil, Buzios field, Santos Basin pre-salt; start-up 2027 [1]
  • in Seatrium's order book with P-78, P-80 and P-82 (Petrobras FPSO newbuilds) [2]
Phase by phase
  • FEED · done
  • EPC award · done
  • Engineering & procurement · done
  • Construction · in progress
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 sec.gov 2 links.sgx.com · checked 29 Oct 2026

CONFIRMEDLARGEOFFSHOREBrazil · FPSO

Petrobras Atapu 2 and Sepia 2: FPSOs P-84 and P-85 (225,000 b/d each)

Seatrium (FPSO newbuild, both units)
  1. FEED: FEED: done
  2. Award: EPC award: done, 25 May 2024
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: in progress, 2025
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Construction
Value
SGD 11bn [1]
Workforce
not published
Finish
2030 [2]
No open adverts linked today
Client, scope, phases, sources

Client: Petrobras, operator of the Atapu and Sepia consortia

Value: approximately SGD 11 billion (both FPSOs) [1]

Finish: P-84 start-up 2029, P-85 2030 (Petrobras 2Q26) [2]

Scope
  • two FPSOs, 225,000 b/d oil and 10 million m3/d gas each; all-electric, zero routine flaring [1]
  • modules (60,000 t) built in Seatrium yards in Brazil, China and Singapore; integration in Singapore [1]
  • start-up: P-84 (Atapu) 2029, P-85 (Sepia) 2030 [2]
Phase by phase
  • FEED · done
  • EPC award · done · 25 May 2024 · contracts signed [1]
  • Engineering & procurement · in progress
  • Construction · in progress · 2025 · construction to start Q1 2025 (Seatrium) [1]
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 links.sgx.com 2 sec.gov · checked 29 Oct 2026

CONFIRMEDOFFSHOREBrazil · FPSO

Petrobras SEAP I and II (Sergipe-Alagoas deepwater): FPSOs P-81 and P-87, 120,000 b/d each

SBM Offshore (design, build and operate both FPSOs (BOT))
  1. FEED: FEED: done
  2. Award: EPC award: done, 29 May 2026
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: not started
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Engineering & procurement
Value
not published
Workforce
not published
Finish
2031 [1]
No open adverts linked today
Client, scope, phases, sources

Client: Petrobras-led consortia

Value: not published

Finish: SEAP-II delivery 2030, SEAP-I 2031 [1]

Scope
  • two Fast4Ward FPSOs, 120,000 b/d oil each, about 2,500 m water depth [1]
  • SEAP-II delivery 2030, SEAP-I 2031; SBM operates for an initial 6.5 years [1]
Phase by phase
  • FEED · done
  • EPC award · done · 29 May 2026 · contracts signed [1]
  • Engineering & procurement · in progress
  • Construction · not started
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 worldoil.com 2 sec.gov · checked 29 Oct 2026

CONFIRMEDLARGEOFFSHOREBrazil · FPSO

Equinor Raia (BM-C-33), Campos Basin pre-salt: gas FPSO, 16 million m3/d

MODEC (FPSO, lump-sum turnkey EPCI) · TechnipFMC (subsea EPCI (SURF))
  1. FEED: FEED: done
  2. Award: EPC award: done, 10 May 2023
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: in progress
  5. Comm.: Pre-commissioning & commissioning: in progress, 1 Jul 2026
  6. Start: Start-up: not started
Now: Pre-commissioning & commissioning
Value
USD 9bn [1]
Workforce
not published
Finish
2028 [2]
No open adverts linked today
Client, scope, phases, sources

Client: Equinor (35%, operator), Repsol Sinopec Brasil (35%), Petrobras (30%)

Value: about USD 9 billion (project investment) [1]

Finish: operations from 2028 [2]

Scope
  • FPSO with about 126,000 b/d of oil/condensate and 16 million m3/d gas export [1]
  • FPSO accommodation commissioning completed July 2026 [2]
Phase by phase
  • FEED · done
  • EPC award · done · 10 May 2023 [1]
  • Engineering & procurement · in progress
  • Construction · in progress
  • Pre-commissioning & commissioning · in progress · 1 Jul 2026 · accommodation modules commissioned [2]
  • Start-up · not started

Sources: 1 equinor.com 2 tagdlaw.com.br · checked 29 Oct 2026

ON THE RADAROFFSHOREBrazil · FPSO

Petrobras Albacora revitalisation: FPSO P-88 (120,000 b/d), BOT tender

Yinson (lowest bidder, USD 2.29 bn; award not confirmed)
  1. FEED: FEED: done
  2. Award: EPC award: unknown
  3. E&P: Engineering & procurement: unknown
  4. Build: Construction: not started
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Last step done: FEED
Value
lowest bid USD 2.29 billion… [1]
Workforce
not published
Finish
first oil after 2031 [1]
No open adverts linked today
Client, scope, phases, sources

Client: Petrobras

Value: lowest bid USD 2.29 billion (Yinson); contract not signed [1]

Scope
  • FPSO, 120,000 b/d oil and up to 4.3 million m3/d gas, build-operate-transfer [1]
  • bids: Yinson 2.29, COOEC 2.84, Shapoorji 2.9, MISC 3.05, BW 3.19 (USD bn) [1]
Phase by phase
  • FEED · done
  • EPC award · unknown
  • Engineering & procurement · unknown
  • Construction · not started
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 agenciainfra.com · checked 29 Oct 2026

CONFIRMEDLARGEOFFSHOREGuyana · FPSO

ExxonMobil Uaru (Stabroek, 5th project): FPSO Errea Wittu, 250,000 b/d

MODEC (FPSO Errea Wittu)
  1. FEED: FEED: done
  2. Award: EPC award: done
  3. E&P: Engineering & procurement: done
  4. Build: Construction: done, 21 Aug 2026
  5. Comm.: Pre-commissioning & commissioning: in progress
  6. Start: Start-up: not started
Now: Pre-commissioning & commissioning
Value
USD 12.7bn [1]
Workforce
not published
Finish
first oil expected in Q4 2026 [2]
No open adverts linked today
Client, scope, phases, sources

Client: ExxonMobil Guyana (45%, operator), Chevron (30%), CNOOC (25%)

Value: USD 12.7 billion (project) [1]

Scope
  • FPSO Errea Wittu, up to 250,000 b/d, about 2 million bbl storage [1]
  • FPSO arrived in Guyana in August 2026; final preparations for start-up [2]
Phase by phase
  • FEED · done
  • EPC award · done
  • Engineering & procurement · done
  • Construction · done · 21 Aug 2026 · FPSO arrived in Guyanese waters [1]
  • Pre-commissioning & commissioning · in progress
  • Start-up · not started

Sources: 1 energynow.tt 2 industrialinfo.com · checked 29 Oct 2026

CONFIRMEDLARGEOFFSHOREGuyana · FPSO

ExxonMobil Hammerhead (Stabroek, 7th project): FPSO 150,000 b/d

MODEC (FPSO) · Seatrium (FPSO topsides integration, flare tower and crane pedestal, commissioning support (for MODEC, Nov 2026))
  1. FEED: FEED: done
  2. Award: EPC award: done, 24 Sep 2025
  3. E&P: Engineering & procurement: done
  4. Build: Construction: in progress
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Construction
Value
USD 6.8bn [1]
Workforce
not published
Finish
2029 [1]
No open adverts linked today
Client, scope, phases, sources

Client: ExxonMobil Guyana (45%, operator), Hess (30%), CNOOC (25%)

Value: USD 6.8 billion (field development) [1]

Finish: first oil 2029 [1]

Scope
  • FPSO 150,000 b/d, 1.6 million bbl storage, 18 production and injection wells [1]
  • construction under way (Oct 2026) [2]
Phase by phase
  • FEED · done
  • EPC award · done · 24 Sep 2025 · FID [1]
  • Engineering & procurement · done
  • Construction · in progress
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 jpt.spe.org 2 industrialinfo.com 3 euro-petrole.com · checked 17 Nov 2026

CONFIRMEDLARGEOFFSHOREGuyana · FPSO

ExxonMobil Longtail (Stabroek, 8th project): gas-condensate FPSO, FID 12 Nov 2026

SBM Offshore (FPSO (construct and install after FID)) · Saipem (subsea EPCI (SURF: structures, umbilicals, risers, flowlines); full authorization to proceed 17 Nov 2026, about 4 years) · TechnipFMC (supplier: subsea production systems and flexible production risers)
  1. FEED: FEED: done
  2. Award: EPC award: done, 12 Nov 2026
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: not started
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Engineering & procurement
Value
USD 12.5bn [1]
Workforce
not published
Finish
start-up expected in 2030… [1]
No open adverts linked today
Client, scope, phases, sources

Client: ExxonMobil Guyana (45%, operator), Hess Guyana Exploration (30%), CNOOC Petroleum Guyana (25%)

Value: USD 12.5 billion (planned additional investment) [1]

Finish: start-up expected in 2030 (ExxonMobil) [1]

Scope
  • 1.2 bcf/d gas, up to 250,000 b/d condensate, about 45 subsea production and injection wells [1]
  • SBM Fast4Ward hull, spread moored in about 1,750 m of water, about 2 million bbl condensate storage [2]
  • development of the Longtail, Tripletail and Turbot discoveries; gas and condensate with reinjection [3]
Phase by phase
  • FEED · done · SBM Offshore FEED awarded 24 Mar 2026 [2]
  • EPC award · done · 12 Nov 2026 · FID; SBM to construct and install the FPSO after FID (SBM, 24 Mar 2026) [1]
  • Engineering & procurement · in progress
  • Construction · not started
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 corporate.exxonmobil.com 2 ml-eu.globenewswire.com 3 industrialinfo.com 4 ocean-energyresources.com 5 finviz.com · checked 24 Nov 2026

REPORTEDOFFSHORESaudi Arabia · Offshore platform

Aramco Marjan offshore development: CRPO 166 structures (EPCI)

McDermott (EPCI, single-sourced change order)
  1. FEED: FEED: done
  2. Award: EPC award: done
  3. E&P: Engineering & procurement: done
  4. Build: Construction: done
  5. Comm.: Pre-commissioning & commissioning: in progress
  6. Start: Start-up: unknown
Now: Pre-commissioning & commissioning
Value
not published
Workforce
not published
Finish
not published
No open adverts linked today
Client, scope, phases, sources

Client: Saudi Aramco

Value: not published

Scope
  • EPCI of structures carved out of the USD 15 bn Marjan offshore development [1]
  • McDermott nearing completion of the EPCI works (Jan 2026) [1]
Phase by phase
  • FEED · done
  • EPC award · done
  • Engineering & procurement · done
  • Construction · done
  • Pre-commissioning & commissioning · in progress
  • Start-up · unknown

Sources: 1 guest.meed.com · checked 29 Oct 2026

CONFIRMEDMEDIUMOFFSHORESaudi Arabia · Pipeline

Aramco Safaniya: 48-inch trunkline, 65 km offshore + 12 km onshore (CRPO 156)

Saipem (EPCI under the long-term agreement)
  1. FEED: FEED: done
  2. Award: EPC award: done, 25 Feb 2026
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: unknown
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Engineering & procurement
Value
USD 500m [1]
Workforce
not published
Finish
not published
No open adverts linked today
Client, scope, phases, sources

Client: Saudi Aramco

Value: approximately USD 500 million [1]

Scope
  • 48-inch trunkline (about 65 km offshore, 12 km onshore) and subsea facilities, Safaniya field [1]
  • fabrication at Saipem's Dammam yard; offshore work by Saipem vessels in the region [1]
Phase by phase
  • FEED · done
  • EPC award · done · 25 Feb 2026 [1]
  • Engineering & procurement · in progress
  • Construction · unknown
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 pgjonline.com · checked 29 Oct 2026

REPORTEDLARGEOFFSHORESaudi Arabia · Offshore platform

Aramco Zuluf offshore expansion: CRPOs 145-148 (jackets, decks, pipelines)

Larsen & Toubro Energy Hydrocarbon (CRPO 145 (likely award)) · Subsea7 (CRPOs 146 and 148 (frontrunner)) · Lamprell (CRPO 147 (frontrunner))
  1. FEED: FEED: done
  2. Award: EPC award: in progress
  3. E&P: Engineering & procurement: unknown
  4. Build: Construction: unknown
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: EPC award
Value
about USD 5.8 billion for the… [1]
Workforce
not published
Finish
not published
No open adverts linked today
Client, scope, phases, sources

Client: Saudi Aramco

Value: about USD 5.8 billion for the four packages (MEED estimate) [1]

Scope
  • 29 slipover jackets and decks, tie-in platforms, subsea cables and about 110 km of pipelines incl. a 48-inch trunkline [1]
  • L&T announced an 'ultra-mega' offshore order (above INR 150 bn) in July 2025, likely CRPO 145 [2]
Phase by phase
  • FEED · done
  • EPC award · in progress
  • Engineering & procurement · unknown
  • Construction · unknown
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 guest.meed.com 2 guest.meed.com · checked 26 Nov 2026

REPORTEDOFFSHORESaudi Arabia · Offshore platform

Aramco Arabiyah, Hasbah and Karan: four offshore gas jackets (CRPO 161)

COOEC (China Offshore Oil Engineering) (selected; formal award pending)
  1. FEED: FEED: done
  2. Award: EPC award: in progress
  3. E&P: Engineering & procurement: not started
  4. Build: Construction: not started
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: EPC award
Value
not published
Workforce
not published
Finish
not published
No open adverts linked today
Client, scope, phases, sources

Client: Saudi Aramco

Value: not published

Scope
  • EPCI of four gas jackets at the Arabiyah, Hasbah and Karan fields [1]
Phase by phase
  • FEED · done
  • EPC award · in progress
  • Engineering & procurement · not started
  • Construction · not started
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 guest.meed.com · checked 26 Nov 2026

CONFIRMEDLARGEOFFSHOREQatar · Gas compression

QatarEnergy LNG North Field Production Sustainability COMP5: two offshore compression complexes

Saipem (EPCI, share about USD 3.1 bn) · COOEC (China Offshore Oil Engineering) (partner)
  1. FEED: FEED: done
  2. Award: EPC award: done, 22 Dec 2025
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: not started
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Engineering & procurement
Value
USD 4bn [1]
Workforce
not published
Finish
contract duration about five… [1]
No open adverts linked today
Client, scope, phases, sources

Client: QatarEnergy LNG

Value: about USD 4 billion (Saipem share about USD 3.1 billion) [1]

Finish: contract duration about five years; installation 2029 and 2030 [1]

Scope
  • two complexes: compression platform, living quarters, flare platform and bridges, about 68,000 t each [1]
  • offshore installation 2029-2030 by Saipem's De He; COMP2 and COMP3 already in execution, COMP4 to Technip Energies [1]
Phase by phase
  • FEED · done
  • EPC award · done · 22 Dec 2025 [1]
  • Engineering & procurement · in progress
  • Construction · not started
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 offshore-technology.com · checked 29 Oct 2026

CONFIRMEDOFFSHOREAustralia · Offshore platform

Woodside Scarborough: floating production unit + Pluto LNG Train 2 (5 Mtpa)

McDermott (FPU design, fabrication, integration, installation) · Bechtel (Pluto Train 2 EPC)
  1. FEED: FEED: done
  2. Award: EPC award: done
  3. E&P: Engineering & procurement: done
  4. Build: Construction: done, 13 Jan 2026
  5. Comm.: Pre-commissioning & commissioning: in progress
  6. Start: Start-up: not started
Now: Pre-commissioning & commissioning · 91% complete (Jan 2026) [1]
91%
Value
not published
Workforce
not published
Finish
2026 [1]
No open adverts linked today
Client, scope, phases, sources

Client: Woodside (operator)

Value: not published

Finish: first LNG targeted for the second half of 2026 [1]

Scope
  • semi-submersible FPU, about 30,000 t topsides (QMW yard, Qingdao) + 37,000 t hull, up to 1.8 Bcf/d [1]
  • about 433 km pipeline to Pluto LNG Train 2 (about 5 Mtpa) [1]
Phase by phase

Progress: 91% complete (Woodside, January 2026) [1]

  • FEED · done
  • EPC award · done
  • Engineering & procurement · done
  • Construction · done · 13 Jan 2026 · FPU on location [1]
  • Pre-commissioning & commissioning · in progress
  • Start-up · not started

Sources: 1 jpt.spe.org · checked 29 Oct 2026

CONFIRMEDLARGEOFFSHOREMexico · Offshore platform

Woodside-Pemex Trion (Mexican Gulf deepwater): FPU 100,000 b/d + FSO

HD Hyundai Heavy Industries (FPU EPC, Ulsan) · SBM Offshore (FPU and FSO installation)
  1. FEED: FEED: done
  2. Award: EPC award: done
  3. E&P: Engineering & procurement: done
  4. Build: Construction: in progress, 13 Nov 2024
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Construction
Value
USD 7.2bn [1]
Workforce
not published
Finish
2028 [2]
No open adverts linked today
Client, scope, phases, sources

Client: Woodside (60%, operator), Pemex (40%)

Value: estimated USD 7.2 billion (investment) [1]

Finish: first oil targeted for 2028 [2]

Scope
  • semi-submersible FPU 100,000 b/d linked to a 950,000 bbl FSO [1]
  • FPU steel cut in Ulsan in November 2024 [2]
Phase by phase
  • FEED · done
  • EPC award · done
  • Engineering & procurement · done
  • Construction · in progress · 13 Nov 2024 · FPU steel cutting [2]
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 jpt.spe.org 2 energy-pedia.com · checked 29 Oct 2026

CONFIRMEDOFFSHOREUnited States · Offshore platform

bp Kaskida (US Gulf, Paleogene): FPU 80,000 b/d

Seatrium (FPU EPC and onshore commissioning)
  1. FEED: FEED: done
  2. Award: EPC award: done, 24 Dec 2024
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: unknown
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Engineering & procurement
Value
not published
Workforce
not published
Finish
not published
No open adverts linked today
Client, scope, phases, sources

Client: bp

Value: not published

Scope
  • semi-submersible FPU, 80,000 b/d from six wells in phase 1 [1]
Phase by phase
  • FEED · done
  • EPC award · done · 24 Dec 2024 [1]
  • Engineering & procurement · in progress
  • Construction · unknown
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 bairdmaritime.com · checked 29 Oct 2026

CONFIRMEDOFFSHOREUnited Kingdom · FPSO

Rosebank (West of Shetland, UK): FPSO Rosebank (ex-Knarr), hook-up and commissioning

TechnipFMC (iEPCI: subsea production systems, umbilicals, risers and flowlines) · Altera Infrastructure (FPSO Petrojarl Knarr owner: bareboat charter and operations & maintenance) · Aker Solutions (FPSO upgrade, in JV with Drydocks World (Dubai), completed) · contractors not named in the source read today
  1. FEED: FEED: done
  2. Award: EPC award: done
  3. E&P: Engineering & procurement: done
  4. Build: Construction: done, Jun 2026
  5. Comm.: Pre-commissioning & commissioning: in progress
  6. Start: Start-up: not started
Now: Pre-commissioning & commissioning
Value
not published
Workforce
not published
Finish
start-up targeted for the first… [1]
No open adverts linked today
Client, scope, phases, sources

Client: Adura (Equinor-Shell JV, operator) and Ithaca Energy

Value: not published

Finish: start-up targeted for the first half of 2027 [1]

Scope
  • FPSO Rosebank (formerly on Knarr, Norway) moored on location June 2026; hook-up and commissioning under way [1]
  • start-up subject to final UK government approval, expected by end-2026 [1]
Phase by phase
  • FEED · done
  • EPC award · done
  • Engineering & procurement · done
  • Construction · done · Jun 2026 · FPSO moored on location [1]
  • Pre-commissioning & commissioning · in progress
  • Start-up · not started

Sources: 1 offshore-mag.com 2 pressandjournal.co.uk 3 ogj.com · checked 29 Oct 2026

ON THE RADAROFFSHORENamibia · FPSO

TotalEnergies Venus (Block 2913B, Orange Basin): FPSO 150,000-200,000 b/d, pre-FID

Hanwha Ocean (FPSO bidder) · SBM Offshore (FPSO bidder)
  1. FEED: FEED: done
  2. Award: EPC award: unknown
  3. E&P: Engineering & procurement: unknown
  4. Build: Construction: not started
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Last step done: FEED
Value
initial phase up to USD 10… [1]
Workforce
not published
Finish
2030 [1]
No open adverts linked today
Client, scope, phases, sources

Client: TotalEnergies (operator)

Value: initial phase up to USD 10 billion (industry estimate) [1]

Finish: first oil targeted for 2030 [1]

Scope
  • FPSO for 150,000-200,000 b/d; subsea package at least USD 2.5 bn [1]
Phase by phase
  • FEED · done
  • EPC award · unknown
  • Engineering & procurement · unknown
  • Construction · not started
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 republikein.com.na · checked 29 Oct 2026

CONFIRMEDLARGEOFFSHOREAngola · FPSO

Azule Energy Greater PAJ (Blocks 31 and 31/21): new FPSO 95,000 b/d

CIMC Raffles (FPSO, Haiyang yard) · Saipem (transport and installation) · TechnipFMC (risers and flowlines) · Baker Hughes (subsea production systems) · OneSubsea (umbilicals) · Vallourec (rigid pipes)
  1. FEED: FEED: done
  2. Award: EPC award: done, 23 Jun 2026
  3. E&P: Engineering & procurement: done
  4. Build: Construction: in progress
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Construction
Value
USD 5.1bn [1]
Workforce
not published
Finish
2029 [1]
No open adverts linked today
Client, scope, phases, sources

Client: Azule Energy (bp-Eni JV)

Value: USD 5.1 billion (FID investment) [1]

Finish: first oil expected in the first half of 2029 [1]

Scope
  • new FPSO 95,000 b/d linking Block 31 production with Block 31/21 discoveries [1]
  • FPSO topsides steel cut at CIMC Raffles Haiyang, July 2026 [1]
Phase by phase
  • FEED · done
  • EPC award · done · 23 Jun 2026 · FID and six main contracts [1]
  • Engineering & procurement · done
  • Construction · in progress
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 oedigital.com · checked 29 Oct 2026

CONFIRMEDOFFSHOREChina · Fabrication yard

Fabrication yard: Qingdao McDermott Wuchuan (QMW), Qingdao

McDermott (JV yard)
  1. FEED: FEED: unknown
  2. Award: EPC award: unknown
  3. E&P: Engineering & procurement: unknown
  4. Build: Construction: in progress
  5. Comm.: Pre-commissioning & commissioning: in progress
  6. Start: Start-up: unknown
Now: Pre-commissioning & commissioning
Value
not published
Workforce
not published
Finish
not published
Open jobs today · 2 open adverts
All open jobs on this project ›
Client, scope, phases, sources

Client: McDermott-Wuchuan joint venture (yard owner)

Value: not published

Scope
  • 60 ha yard, 300 m skidway (50,000 t load-out), up to 90,000 t a year [1]
  • now fabricating: jacket and topside for ADNOC Umm Shaif package 4 (awarded Aug 2026) [2]
  • built the Scarborough FPU topsides (about 30,000 t) [3]
Phase by phase
  • FEED · unknown
  • EPC award · unknown
  • Engineering & procurement · unknown
  • Construction · in progress
  • Pre-commissioning & commissioning · in progress
  • Start-up · unknown

Sources: 1 mcdermott.com 2 worldoil.com 3 jpt.spe.org · checked 29 Oct 2026

CONFIRMEDOFFSHOREIndonesia · Fabrication yard

Fabrication yard: McDermott Batam (Indonesia)

McDermott (yard)
  1. FEED: FEED: unknown
  2. Award: EPC award: unknown
  3. E&P: Engineering & procurement: unknown
  4. Build: Construction: unknown
  5. Comm.: Pre-commissioning & commissioning: unknown
  6. Start: Start-up: unknown
Phases not published
Value
not published
Workforce
not published
Finish
not published
Open jobs today · 5 open adverts

+2 more on the jobs page.

All open jobs on this project ›
Client, scope, phases, sources

Client: McDermott (yard owner)

Value: not published

Scope
  • 120 ha yard, 817 m quay, up to 60,000 t a year: fixed and floating offshore structures, LNG modules, subsea structures [1]
Phase by phase
  • FEED · unknown
  • EPC award · unknown
  • Engineering & procurement · unknown
  • Construction · unknown
  • Pre-commissioning & commissioning · unknown
  • Start-up · unknown

Sources: 1 mcdermott.com · checked 29 Oct 2026

CONFIRMEDOFFSHOREUAE · Fabrication yard

Fabrication yard: McDermott Jebel Ali (Dubai)

McDermott (yard)
  1. FEED: FEED: unknown
  2. Award: EPC award: unknown
  3. E&P: Engineering & procurement: unknown
  4. Build: Construction: unknown
  5. Comm.: Pre-commissioning & commissioning: unknown
  6. Start: Start-up: unknown
Phases not published
Value
not published
Workforce
not published
Finish
not published
Open jobs today · 1 open advert
All open jobs on this project ›
Client, scope, phases, sources

Client: McDermott (yard owner)

Value: not published

Scope
  • 53 ha yard, up to 50,000 t a year: pipe fabrication, cladding, girders for the Middle East and India [1]
Phase by phase
  • FEED · unknown
  • EPC award · unknown
  • Engineering & procurement · unknown
  • Construction · unknown
  • Pre-commissioning & commissioning · unknown
  • Start-up · unknown

Sources: 1 mcdermott.com · checked 29 Oct 2026

REPORTEDOFFSHOREUAE · Fabrication yard

Fabrication yard: NMDC Energy Mussafah (Abu Dhabi)

NMDC Energy (yard)
  1. FEED: FEED: unknown
  2. Award: EPC award: unknown
  3. E&P: Engineering & procurement: unknown
  4. Build: Construction: unknown
  5. Comm.: Pre-commissioning & commissioning: unknown
  6. Start: Start-up: unknown
Phases not published
Value
not published
Workforce
not published
Finish
not published
No open adverts linked today
Client, scope, phases, sources

Client: NMDC Energy (yard owner)

Value: not published

Scope
  • fabricated the first jackets of ADNOC's Hail and Ghasha offshore gas project (load-out July 2025) [1]
Phase by phase
  • FEED · unknown
  • EPC award · unknown
  • Engineering & procurement · unknown
  • Construction · unknown
  • Pre-commissioning & commissioning · unknown
  • Start-up · unknown

Sources: 1 meed.com · checked 29 Oct 2026

CONFIRMEDOFFSHORESaudi Arabia · Fabrication yard

Fabrication yard: NMDC Energy Ras Al Khair (Saudi Arabia)

NMDC Energy (yard)
  1. FEED: FEED: unknown
  2. Award: EPC award: unknown
  3. E&P: Engineering & procurement: unknown
  4. Build: Construction: unknown
  5. Comm.: Pre-commissioning & commissioning: unknown
  6. Start: Start-up: unknown
Phases not published
Value
AED 200m [1]
Workforce
more than 1,800 experienced employees moved from Abu Dhabi to the yard [1]
Finish
not published
No open adverts linked today
Client, scope, phases, sources

Client: NMDC Energy (yard owner)

Value: AED 200 million (yard investment) [1]

Scope
  • 400,000 m2 yard; nine offshore jackets for Aramco in production at opening [1]
Phase by phase
  • FEED · unknown
  • EPC award · unknown
  • Engineering & procurement · unknown
  • Construction · unknown
  • Pre-commissioning & commissioning · unknown
  • Start-up · unknown

Sources: 1 nmdc-group.com · checked 29 Oct 2026

CONFIRMEDOFFSHOREIndia · Fabrication yard

Fabrication yard: L&T Kattupalli modular yard (near Chennai)

Larsen & Toubro (yard)
  1. FEED: FEED: unknown
  2. Award: EPC award: unknown
  3. E&P: Engineering & procurement: unknown
  4. Build: Construction: unknown
  5. Comm.: Pre-commissioning & commissioning: unknown
  6. Start: Start-up: unknown
Phases not published
Value
not published
Workforce
not published
Finish
not published
Open jobs today · 1 open advert
All open jobs on this project ›
Client, scope, phases, sources

Client: Larsen & Toubro (yard owner)

Value: not published

Scope
  • delivered 110 modules (about 64,000 t) for Project CERES, Western Australia (Sep 2026) [1]
  • L&T modular capacity about 200,000 t a year across Kattupalli, Hazira and Oman [1]
Phase by phase
  • FEED · unknown
  • EPC award · unknown
  • Engineering & procurement · unknown
  • Construction · unknown
  • Pre-commissioning & commissioning · unknown
  • Start-up · unknown

Sources: 1 kotakneo.com · checked 29 Oct 2026

CONFIRMEDOFFSHORESingapore · Fabrication yard

Fabrication yard: Seatrium Tuas Boulevard (Singapore) and Brazil yards

Seatrium (yard)
  1. FEED: FEED: unknown
  2. Award: EPC award: unknown
  3. E&P: Engineering & procurement: unknown
  4. Build: Construction: unknown
  5. Comm.: Pre-commissioning & commissioning: unknown
  6. Start: Start-up: unknown
Phases not published
Value
not published
Workforce
not published
Finish
not published
No open adverts linked today
Client, scope, phases, sources

Client: Seatrium (yard owner)

Value: not published

Scope
  • P-80 and P-82 FPSOs completed at Tuas Boulevard (2026); modules from BrasFELS and Aracruz (Brazil) [1]
  • P-84 and P-85 integration in Singapore, modules from Brazil, China and Singapore [2]
  • bp Kaskida FPU (EPC) [3]
Phase by phase
  • FEED · unknown
  • EPC award · unknown
  • Engineering & procurement · unknown
  • Construction · unknown
  • Pre-commissioning & commissioning · unknown
  • Start-up · unknown

Sources: 1 ogj.com 2 links.sgx.com 3 bairdmaritime.com · checked 29 Oct 2026

CONFIRMEDOFFSHOREChina · Fabrication yard

Fabrication yard: COOEC Qingdao base

COOEC (China Offshore Oil Engineering) (yard)
  1. FEED: FEED: unknown
  2. Award: EPC award: unknown
  3. E&P: Engineering & procurement: unknown
  4. Build: Construction: unknown
  5. Comm.: Pre-commissioning & commissioning: unknown
  6. Start: Start-up: unknown
Phases not published
Value
not published
Workforce
not published
Finish
not published
No open adverts linked today
Client, scope, phases, sources

Client: COOEC (yard owner)

Value: not published

Scope
  • fabrication for QatarEnergy Bul Hanine (BH-EPIC1 and 2, more than 130,000 t of steel) started 15 Sep 2026 [1]
Phase by phase
  • FEED · unknown
  • EPC award · unknown
  • Engineering & procurement · unknown
  • Construction · unknown
  • Pre-commissioning & commissioning · unknown
  • Start-up · unknown

Sources: 1 equalocean.com · checked 29 Oct 2026

CONFIRMEDOFFSHORESaudi Arabia · Fabrication yard

Fabrication yard: Saipem Taqa Al-Rushaid Fabricators (Dammam)

Saipem (yard)
  1. FEED: FEED: unknown
  2. Award: EPC award: unknown
  3. E&P: Engineering & procurement: unknown
  4. Build: Construction: unknown
  5. Comm.: Pre-commissioning & commissioning: unknown
  6. Start: Start-up: unknown
Phases not published
Value
not published
Workforce
not published
Finish
not published
No open adverts linked today
Client, scope, phases, sources

Client: Saipem Taqa Al-Rushaid Fabricators (yard owner)

Value: not published

Scope
  • fabrication for the Aramco Safaniya 48-inch trunkline contract (Feb 2026) [1]
Phase by phase
  • FEED · unknown
  • EPC award · unknown
  • Engineering & procurement · unknown
  • Construction · unknown
  • Pre-commissioning & commissioning · unknown
  • Start-up · unknown

Sources: 1 pgjonline.com · checked 29 Oct 2026

CONFIRMEDOFFSHORENigeria · Fabrication yard

Fabrication yard: Dorman Long Engineering, Naval Dockyard (Lagos)

Dorman Long Engineering (yard)
  1. FEED: FEED: unknown
  2. Award: EPC award: unknown
  3. E&P: Engineering & procurement: unknown
  4. Build: Construction: unknown
  5. Comm.: Pre-commissioning & commissioning: unknown
  6. Start: Start-up: unknown
Phases not published
Value
not published
Workforce
not published
Finish
not published
No open adverts linked today
Client, scope, phases, sources

Client: Dorman Long Engineering (yard owner)

Value: not published

Scope
  • built the 1,300 t Madu conductor support platform at the Nigerian Naval Dockyard; modular separators for NAOC Irri [1]
Phase by phase
  • FEED · unknown
  • EPC award · unknown
  • Engineering & procurement · unknown
  • Construction · unknown
  • Pre-commissioning & commissioning · unknown
  • Start-up · unknown

Sources: 1 techeconomy.ng · checked 29 Oct 2026

CONFIRMEDAlgeria · Onshore oil field

Sonatrach-PTTEP Hassi Bir Rekaiz phase 2: crude processing unit 31,500 b/d

Petrojet (EPC consortium) · Arkad (EPC consortium)
  1. FEED: FEED: done
  2. Award: EPC award: done, 5 May 2026
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: unknown
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Engineering & procurement
Value
more than USD 1 billion (EPC… [1]
Workforce
not published
Finish
commissioning within 39 months [1]
No open adverts linked today
Client, scope, phases, sources

Client: Sonatrach and PTTEP (field partners)

Value: more than USD 1 billion (EPC contract) [1]

Scope
  • new crude processing unit 31,500 b/d with associated gas and produced-water treatment [1]
Phase by phase
  • FEED · done
  • EPC award · done · 5 May 2026 · EPC contract signed [1]
  • Engineering & procurement · in progress
  • Construction · unknown
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 financialafrik.com · checked 29 Oct 2026

CONFIRMEDLARGEAlgeria · Refinery

Sonatrach Hassi Messaoud (Haoud El-Hamra) grassroots refinery, 5 Mtpa

Tecnicas Reunidas (EPC, 51%) · Sinopec (EPC, 49%) · Shaanxi Huajian Engineering (erection subcontract, package PK4 (CCR))
  1. FEED: FEED: done
  2. Award: EPC award: done
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: in progress, 24 Feb 2025
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Construction
Value
USD 4bn [1]
Workforce
EPC Radar estimate est. 9,600-44,300 at peak how?
Finish
first refining units from… [1]
No open adverts linked today
Client, scope, phases, sources

Client: Sonatrach

Value: about USD 4 billion (EPC contract) [1]

Finish: first refining units from end-2027; 65-month construction [1]

Workforce estimate (low confidence): EPC Radar estimate from 2 published refinery, petrochemical and fertiliser plants projects in this tracker, 2.4-11.1 workers per USD million of declared value (id-rdmp-balikpapan, ar-fertil-pampa), applied to contract value: about USD 4,000 m

Scope
  • refinery of about 5 million t/yr of crude; CCR unit 1.35 Mt/yr in package PK4 [1]
  • first stone laid 24 Feb 2025; construction period 65 months [1]
Phase by phase
  • FEED · done
  • EPC award · done
  • Engineering & procurement · in progress
  • Construction · in progress · 24 Feb 2025 · first stone [1]
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 algerie-eco.com · checked 29 Oct 2026

CONFIRMEDLARGEAlgeria · Gas compression

Sonatrach Hassi R'Mel boosting phase III: three compression stations

Baker Hughes - Nuovo Pignone International (EPC consortium) · Tecnimont (EPC consortium)
  1. FEED: FEED: done
  2. Award: EPC award: done, 23 May 2024
  3. E&P: Engineering & procurement: done
  4. Build: Construction: in progress
  5. Comm.: Pre-commissioning & commissioning: in progress
  6. Start: Start-up: not started
Now: Pre-commissioning & commissioning · 51% complete (Jul 2025) [2]
51%
Value
USD 2.3bn [1]
Workforce
not published
Finish
Apr 2027 [2]
No open adverts linked today
Client, scope, phases, sources

Client: Sonatrach

Value: USD 2.3 billion (EPC contract) [1]

Finish: compression units commissioning Oct 2026, Jan 2027 and Apr 2027 [2]

Scope
  • three gas-boosting stations, 20 compression trains, upgrade of 300+ km of gathering lines; about 188 million m3/d [1]
Phase by phase

Progress: 51% complete (Sonatrach, July 2025) [2]

  • FEED · done
  • EPC award · done · 23 May 2024 [2]
  • Engineering & procurement · done
  • Construction · in progress
  • Pre-commissioning & commissioning · in progress
  • Start-up · not started

Sources: 1 offshore-technology.com 2 sonatrach.com · checked 29 Oct 2026

CONFIRMEDAlgeria · Fertiliser

Sonatrach Projet Phosphates Integre, phase 1: Bled El Hadba mine + Oued El-Kebrit fertiliser units

Saipem (EPC phase 1 (limited notice to proceed))
  1. FEED: FEED: done
  2. Award: EPC award: done, 12 Aug 2026
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: not started
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Engineering & procurement
Value
EUR 500m [1]
Workforce
not published
Finish
not published
No open adverts linked today
Client, scope, phases, sources

Client: Sonatrach

Value: about EUR 500 million (limited notice to proceed) [1]

Scope
  • phosphate mining infrastructure at Bled El Hadba; fertiliser process units, utilities and logistics at Oued El-Kebrit [1]
Phase by phase
  • FEED · done
  • EPC award · done · 12 Aug 2026 · limited notice to proceed [1]
  • Engineering & procurement · in progress
  • Construction · not started
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 chemxplore.com · checked 29 Oct 2026

CONFIRMEDEgypt · Gas processing

Eni/Agiba Meleiha Phase 2 (Western Desert): gas plant 100 MMscfd + 200 km pipelines

Petrojet (main EPC contract)
  1. FEED: FEED: done
  2. Award: EPC award: done
  3. E&P: Engineering & procurement: done
  4. Build: Construction: done
  5. Comm.: Pre-commissioning & commissioning: in progress
  6. Start: Start-up: in progress, 21 Oct 2026
Now: Start-up
Value
not published
Workforce
not published
Finish
not published
No open adverts linked today
Client, scope, phases, sources

Client: Agiba Petroleum (Eni-EGPC JV)

Value: not published

Scope
  • gas processing up to 100 MMscfd, sweetening and recovery units, 200 km of pipeline, 28 wells [1]
  • Eni started bringing the plant online (Oct 2026) [1]
Phase by phase
  • FEED · done
  • EPC award · done
  • Engineering & procurement · done
  • Construction · done
  • Pre-commissioning & commissioning · in progress
  • Start-up · in progress · 21 Oct 2026 · start-up under way [1]

Sources: 1 guest.meed.com · checked 29 Oct 2026

CONFIRMEDOFFSHOREEgypt · Subsea

Burullus West Delta Deep Marine: subsea umbilical and 2 km TCP flowline replacement

Oceaneering (integrated transport, installation and commissioning)
  1. FEED: FEED: done
  2. Award: EPC award: done, 21 May 2026
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: in progress
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Construction
Value
not published
Workforce
not published
Finish
not published
No open adverts linked today
Client, scope, phases, sources

Client: Burullus Gas Company

Value: not published

Scope
  • refurbished subsea umbilical + 2,000 m thermoplastic composite flowline, ROV and survey support [1]
Phase by phase
  • FEED · done
  • EPC award · done · 21 May 2026 [1]
  • Engineering & procurement · in progress
  • Construction · in progress
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 worldoil.com · checked 29 Oct 2026

CONFIRMEDLARGEOFFSHORELibya · Offshore platform

Mellitah Complex Expansion & CO2 Management (Structures A & E, NC 41 offshore)

Rosetti Marino (offshore EPC consortium, 33%) · Kerry Project Logistics (offshore EPC consortium) · Gruppo Antonini (offshore EPC consortium)
  1. FEED: FEED: done
  2. Award: EPC award: done
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: in progress
  5. Comm.: Pre-commissioning & commissioning: unknown
  6. Start: Start-up: unknown
Now: Construction
Value
USD 8bn [1]
Workforce
not published
Finish
not published
No open adverts linked today
Client, scope, phases, sources

Client: Mellitah Oil & Gas (NOC-Eni JV)

Value: about USD 8 billion (project); offshore EPC EUR 1.2 billion (June 2024) [1]

Scope
  • wellhead platform A (96 m water) and production platform E (220 m), Sabratha modifications, onshore Mellitah upgrades [1]
  • EPIC tender for subsea pipelines (about USD 3 bn): prequalification due 5 Nov 2026 [1]
Phase by phase
  • FEED · done
  • EPC award · done
  • Engineering & procurement · in progress
  • Construction · in progress
  • Pre-commissioning & commissioning · unknown
  • Start-up · unknown

Sources: 1 guest.meed.com · checked 12 Nov 2026

ON THE RADARMEDIUMOFFSHOREMorocco · Terminal & storage

Morocco Nador West Med: FSRU LNG terminal + national gas pipeline corridor (tenders)

Contractors: tenders open; no award published
  1. FEED: FEED: unknown
  2. Award: EPC award: not started
  3. E&P: Engineering & procurement: not started
  4. Build: Construction: not started
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Before the EPC award
Value
about USD 954 million first phase… [1]
Workforce
not published
Finish
2027 [1]
No open adverts linked today
Client, scope, phases, sources

Client: Ministry of Energy Transition (Morocco)

Value: about USD 954 million first phase (FSRU about USD 273 m + pipelines about USD 681 m, estimates) [1]

Finish: terminal service target 2027 [1]

Scope
  • FSRU lease at Nador West Med connected to the GME pipeline; PPP pipeline to Kenitra and Mohammedia [1]
Phase by phase
  • FEED · unknown
  • EPC award · not started
  • Engineering & procurement · not started
  • Construction · not started
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 italpress.com · checked 29 Oct 2026

CONFIRMEDSweden · CCS / BECCS

Stockholm Exergi BECCS, Vartan: 800,000 t/yr CO2 capture

Saipem (design, procurement and construction) · Skanska (ground, foundations and quay, phase 2)
  1. FEED: FEED: done
  2. Award: EPC award: done
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: in progress, Apr 2025
  5. Comm.: Pre-commissioning & commissioning: in progress
  6. Start: Start-up: not started
Now: Pre-commissioning & commissioning
Value
SEK 990m [1]
Workforce
not published
Finish
2028 [2]
No open adverts linked today
Client, scope, phases, sources

Client: Stockholm Exergi

Value: about SEK 990 million (Skanska phase 2 groundworks) [1]

Finish: operations planned for 2028 [2]

Scope
  • capture up to 800,000 t/yr of biogenic CO2 at the Vartan CHP plant [2]
  • Skanska groundworks started April 2025, completion during 2028 [1]
Phase by phase
  • FEED · done
  • EPC award · done
  • Engineering & procurement · in progress
  • Construction · in progress · Apr 2025 · groundworks start [1]
  • Pre-commissioning & commissioning · in progress
  • Start-up · not started

Sources: 1 skanska.com 2 stockholmexergi.se · checked 29 Oct 2026

CONFIRMEDDenmark · CCS / BECCS

Orsted Kalundborg CO2 Hub BECCS (Asnaes + Avedore): 430,000 t/yr

Aker Carbon Capture (five Just Catch capture units (2023 plan))
  1. FEED: FEED: done
  2. Award: EPC award: done
  3. E&P: Engineering & procurement: done
  4. Build: Construction: in progress, 25 Feb 2025
  5. Comm.: Pre-commissioning & commissioning: unknown
  6. Start: Start-up: unknown
Now: Construction
Value
not published
Workforce
not published
Finish
2026 [2]
No open adverts linked today
Client, scope, phases, sources

Client: Orsted

Value: not published

Finish: expected operational in early 2026 (Orsted, Feb 2025) [2]

Scope
  • 430,000 t/yr of biogenic CO2 from Asnaes (wood chips) and Avedore (straw), shipped to Northern Lights [1]
  • absorbers, desorbers and coolers lifted in place at both plants, Feb 2025 [2]
Phase by phase
  • FEED · done
  • EPC award · done
  • Engineering & procurement · done
  • Construction · in progress · 25 Feb 2025 · key components installed [2]
  • Pre-commissioning & commissioning · unknown
  • Start-up · unknown

Sources: 1 power-technology.com 2 energy-pedia.com · checked 29 Oct 2026

CONFIRMEDUnited Kingdom · CCS / BECCS

Net Zero Teesside Power: 742 MW gas power plant with carbon capture (2 Mt/yr)

Technip Energies (lead EPC) · GE Vernova (power island) · Balfour Beatty (construction, GBP 833 m)
  1. FEED: FEED: done
  2. Award: EPC award: done, Dec 2024
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: in progress
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Construction
Value
GBP 833m [1]
Workforce
not published
Finish
not published
No open adverts linked today
Client, scope, phases, sources

Client: Net Zero Teesside Power (bp-Equinor JV)

Value: GBP 833 million (Balfour Beatty construction contract) [1]

Scope
  • 742 MW combined-cycle plant with post-combustion capture of up to 2 Mt CO2 a year, stored by the Northern Endurance Partnership [1]
Phase by phase
  • FEED · done
  • EPC award · done · Dec 2024 · FID [1]
  • Engineering & procurement · in progress
  • Construction · in progress
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 theconstructionindex.co.uk · checked 29 Oct 2026

CONFIRMEDMEDIUMOFFSHORENorway · CCS / BECCS

Northern Lights phase 2 (Oygarden): CO2 storage expansion to 5 Mt/yr

Aker Solutions (EPC onshore facilities) · Subsea7 (EPC 5 km CO2 pipeline and subsea)
  1. FEED: FEED: done
  2. Award: EPC award: done, 31 Mar 2025
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: in progress
  5. Comm.: Pre-commissioning & commissioning: in progress
  6. Start: Start-up: not started
Now: Pre-commissioning & commissioning
Value
NOK 7.5bn [1]
Workforce
not published
Finish
2028 [1]
No open adverts linked today
Client, scope, phases, sources

Client: Northern Lights JV (Equinor, Shell, TotalEnergies)

Value: NOK 7.5 billion (phase 2 investment) [1]

Finish: commissioning scheduled for 2028 [1]

Scope
  • capacity from 1.5 to 5 Mt CO2 a year; new onshore tanks, jetty and a 5 km pipeline [1]
  • Aker Solutions works at Stord, Fornebu and Mumbai 2025-2028; Subsea7 offshore work 2026-2027 [1]
Phase by phase
  • FEED · done
  • EPC award · done · 31 Mar 2025 [1]
  • Engineering & procurement · in progress
  • Construction · in progress
  • Pre-commissioning & commissioning · in progress
  • Start-up · not started

Sources: 1 constructionreviewonline.com · checked 29 Oct 2026

CONFIRMEDOFFSHORENetherlands · CCS / BECCS

Porthos CCS, Port of Rotterdam: CO2 compressor station, 30 km pipeline, P18 storage (2.5 Mt/yr)

Bonatti (EPC compressor station)
  1. FEED: FEED: done
  2. Award: EPC award: done
  3. E&P: Engineering & procurement: done
  4. Build: Construction: in progress, 2024
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Construction
Value
not published
Workforce
not published
Finish
completion planned for 2026 (May… [2]
No open adverts linked today
Client, scope, phases, sources

Client: Porthos (Gasunie, EBN, Port of Rotterdam)

Value: not published

Finish: completion planned for 2026 (May 2024 plan; not reconfirmed in a source read today) [2]

Scope
  • 2.5 Mt CO2 a year for 15 years; three compressors up to 130 bar; onshore pipeline sized for 10 Mt [1]
  • Bonatti: design, procurement, construction and pre-commissioning of the compressor station [2]
Phase by phase
  • FEED · done
  • EPC award · done
  • Engineering & procurement · done
  • Construction · in progress · 2024 · construction start [2]
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 hellenicshippingnews.com 2 iploca.com · checked 29 Oct 2026

CONFIRMEDLARGEOFFSHORESuriname · FPSO

TotalEnergies GranMorgu (Block 58, Suriname): FPSO 220,000 b/d

SBM Offshore (Fast4Ward FPSO hull reserved, with Technip Energies) · Saipem (SURF EPCI, USD 1.9 bn (Nov 2024), in cooperation with TechnipFMC) · TechnipFMC (subsea production system, flexible risers and umbilical equipment)
  1. FEED: FEED: done
  2. Award: EPC award: done, 1 Oct 2024
  3. E&P: Engineering & procurement: done
  4. Build: Construction: in progress
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Construction
Value
USD 10.5bn [1]
Workforce
not published
Finish
2028 [2]
No open adverts linked today
Client, scope, phases, sources

Client: TotalEnergies (50%, operator), APA (50%); Staatsolie option up to 20%

Value: USD 10.5 billion (project, at FID) [1]

Finish: first oil 2028 [2]

Scope
  • FPSO 220,000 b/d on the Sapakara and Krabdagu fields, subsea wells [1]
  • construction advancing; first oil 2028 (Aug 2026) [2]
Phase by phase
  • FEED · done
  • EPC award · done · 1 Oct 2024 · FID [1]
  • Engineering & procurement · done
  • Construction · in progress
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 jpt.spe.org 2 worldoil.com 3 worldpipelines.com 4 jpt.spe.org · checked 29 Oct 2026

CONFIRMEDOFFSHOREEquatorial Guinea · Subsea

Chevron Aseng gas monetisation (Equatorial Guinea): subsea tieback to Alen platform

Subsea7 (subsea installation (EPCI))
  1. FEED: FEED: done
  2. Award: EPC award: done, 1 Apr 2026
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: unknown
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Engineering & procurement
Value
USD 150-300 million… [1]
Workforce
not published
Finish
offshore operations expected to… [1]
No open adverts linked today
Client, scope, phases, sources

Client: Noble Energy EG (Chevron)

Value: USD 150-300 million ('substantial', Subsea7 band) [1]

Finish: offshore operations expected to start in 2026 [1]

Scope
  • single-well tieback: about 19 km rigid flowline and 20 km umbilicals in about 800 m of water [1]
Phase by phase
  • FEED · done
  • EPC award · done · 1 Apr 2026 [1]
  • Engineering & procurement · in progress
  • Construction · unknown
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 worldoil.com · checked 29 Oct 2026

CONFIRMEDUganda / Tanzania · Pipeline

East African Crude Oil Pipeline (EACOP), Uganda-Tanzania, + Tilenga/Kingfisher feed station

China Petroleum Pipeline Engineering (CPP) (pipeline, feeder line and above-ground installations contractor (EACOP tender notices)) · Worley (engineering, procurement and construction management (ENR: EPC JV with CPP, 2022)) · contractors not named in the source read today
  1. FEED: FEED: done
  2. Award: EPC award: done
  3. E&P: Engineering & procurement: done
  4. Build: Construction: in progress
  5. Comm.: Pre-commissioning & commissioning: in progress
  6. Start: Start-up: not started
Now: Pre-commissioning & commissioning · 91% complete (Aug 2026) [1]
91%
Value
not published
Workforce
not published
Finish
2026 [1]
No open adverts linked today
Client, scope, phases, sources

Client: EACOP Ltd (TotalEnergies, UNOC, TPDC, CNOOC)

Value: not published

Finish: first oil expected before the end of 2026 [1]

Scope
  • pipeline 91% complete; Pump Station One (fed by Tilenga and Kingfisher) 83% complete (Aug 2026) [1]
Phase by phase

Progress: 91% complete (EACOP deputy MD, 5 Aug 2026) [1]

  • FEED · done
  • EPC award · done
  • Engineering & procurement · done
  • Construction · in progress
  • Pre-commissioning & commissioning · in progress
  • Start-up · not started

Sources: 1 monitor.co.ug 2 enr.com 3 eacop.com · checked 29 Oct 2026

CONFIRMEDKenya · Refinery

Dangote Lamu refinery and petrochemical complex (Kenya), 700,000 b/d

Engineers India (EIL) (PMC and EPCM consultant)
  1. FEED: FEED: unknown
  2. Award: EPC award: done, 22 Sep 2026
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: not started
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Engineering & procurement
Value
USD 450m [1]
Workforce
not published
Finish
construction to begin… [1]
No open adverts linked today
Client, scope, phases, sources

Client: Dangote Group

Value: more than USD 450 million (EIL PMC/EPCM contract) [1]

Finish: construction to begin end-September 2026; completion in about three years (Dangote) [1]

Scope
  • greenfield 700,000 b/d refinery and petrochemical plant at Lamu [1]
Phase by phase
  • FEED · unknown
  • EPC award · done · 22 Sep 2026 · EIL PMC/EPCM contract [1]
  • Engineering & procurement · in progress
  • Construction · not started
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 nairametrics.com · checked 29 Oct 2026

ON THE RADARLARGEPapua New Guinea · LNG plant

Papua LNG (Elk-Antelope, Gulf Province): 5.6 Mtpa, pre-FID

JGC (selected as EPC contractor with Hyundai E&C (JGC, Apr 2026); final award after FID) · Hyundai Engineering & Construction (selected as EPC contractor with JGC; final award after FID) · EPC tender complete; award recommendations await partner approval
  1. FEED: FEED: done
  2. Award: EPC award: unknown
  3. E&P: Engineering & procurement: unknown
  4. Build: Construction: not started
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Last step done: FEED
Value
USD 14bn [1]
Workforce
EPC Radar estimate est. 9,800-36,400 at peak how?
Finish
not published
No open adverts linked today
Client, scope, phases, sources

Client: ExxonMobil (operator, 34.1%), Santos, Kumul/MRDC, TotalEnergies, ENEOS Xplora

Value: about USD 14 billion (capex) [1]

Workforce estimate (low confidence): EPC Radar estimate from 2 published onshore LNG projects in this tracker, 0.7-2.6 workers per USD million of declared value (ng-nlng-train7, Golden Pass LNG), applied to project value: about USD 14,000 m

Scope
  • 5.6 Mtpa of LNG from the Elk and Antelope fields [1]
Phase by phase
  • FEED · done
  • EPC award · unknown
  • Engineering & procurement · unknown
  • Construction · not started
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 worldoil.com 2 lngprime.com · checked 19 Nov 2026

CONFIRMEDTurkmenistan · Gas processing

Turkmengaz Galkynysh gas field development, phase IV (turnkey)

CNPC Amudarya Petroleum Company (turnkey construction)
  1. FEED: FEED: unknown
  2. Award: EPC award: done, 17 Apr 2026
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: unknown
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Engineering & procurement
Value
not published
Workforce
not published
Finish
not published
No open adverts linked today
Client, scope, phases, sources

Client: Turkmengaz

Value: not published

Scope
  • turnkey construction contract for phase IV of Galkynysh development, signed 17 Apr 2026 [1]
Phase by phase
  • FEED · unknown
  • EPC award · done · 17 Apr 2026 [1]
  • Engineering & procurement · in progress
  • Construction · unknown
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 interfax.kz · checked 29 Oct 2026

CONFIRMEDOFFSHOREBrunei · Subsea

PETRONAS Carigali Brunei: six-well subsea development to a floating production unit + gas export pipeline

McDermott (EPCIC subsea system and export pipeline)
  1. FEED: FEED: done
  2. Award: EPC award: done, 9 Dec 2025
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: unknown
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Engineering & procurement
Value
not published
Workforce
not published
Finish
not published
No open adverts linked today
Client, scope, phases, sources

Client: PETRONAS Carigali Brunei

Value: not published

Scope
  • umbilicals, risers and flowlines for six wells to a floating production unit; export pipeline to Brunei LNG [1]
Phase by phase
  • FEED · done
  • EPC award · done · 9 Dec 2025 [1]
  • Engineering & procurement · in progress
  • Construction · unknown
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 pgjonline.com · checked 29 Oct 2026

CONFIRMEDOFFSHOREIsrael · Offshore platform

Chevron Leviathan expansion (Eastern Mediterranean): new modules on the Leviathan platform

Hanwha Ocean (module fabrication)
  1. FEED: FEED: done
  2. Award: EPC award: done, 5 Mar 2026
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: unknown
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Engineering & procurement
Value
not published
Workforce
not published
Finish
not published
No open adverts linked today
Client, scope, phases, sources

Client: Chevron Mediterranean (operator)

Value: not published

Scope
  • module fabrication for integration on the existing Leviathan offshore platform [1]
Phase by phase
  • FEED · done
  • EPC award · done · 5 Mar 2026 · module fabrication contract [1]
  • Engineering & procurement · in progress
  • Construction · unknown
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 worldoil.com · checked 29 Oct 2026

REPORTEDMEDIUMUAE · Onshore oil field

ADNOC Onshore South East off-plot facilities (AIP5): 150+ well tie-ins, 270+ km flowlines, degassing station upgrades

CPECC (China Petroleum Engineering & Construction Corporation) (main EPC contractor)
  1. FEED: FEED: unknown
  2. Award: EPC award: in progress, Mar 2026
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: unknown
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Engineering & procurement
Value
USD 1bn [1]
Workforce
not published
Finish
not published
No open adverts linked today
Client, scope, phases, sources

Client: ADNOC Onshore

Value: more than USD 1bn (MEED, from sources) [1]

Scope
  • tie-in of more than 150 wells, upgrade of remote and central degassing stations, over 270 km of flowlines, well digitalisation; part of the USD 2-3bn South East AIP5 development [1]
Phase by phase
  • FEED · unknown
  • EPC award · in progress · Mar 2026 · EPC works began in March 2026 (MEED, from sources); earlier EPCm (Dec 2024) cancelled in 2025 and moved to full EPC [1]
  • Engineering & procurement · in progress
  • Construction · unknown
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 guest.meed.com · checked 5 Nov 2026

REPORTEDUAE · Pipeline

ADNOC Gas Habshan-Al Nouf sales gas pipeline: 127 km, 56 inch, for EWEC

Kalpataru Projects International (India) (EPC contractor, per sources)
  1. FEED: FEED: unknown
  2. Award: EPC award: done, Oct 2026
  3. E&P: Engineering & procurement: not started
  4. Build: Construction: unknown
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Last step done: EPC award
Value
not published (Kalpataru calls a… [1]
Workforce
not published
Finish
31 months from award of contract [1]
No open adverts linked today
Client, scope, phases, sources

Client: ADNOC Gas (gas for Emirates Water & Electricity Company, EWEC)

Value: not published (Kalpataru calls a "major" order one above INR 40bn, about USD 415m: MEED) [1]

Scope
  • 127 km of 56-inch sales gas pipeline from Habshan to Al Nouf with launcher/receiver stations, four block valve stations and a customer receiving station; 600-660 MMscfd for AI data centre phase 2 and 650-715 MMscfd for the Mirfa relocation [1]
Phase by phase
  • FEED · unknown
  • EPC award · done · Oct 2026 · Kalpataru filed a "major" order on BSE without naming the project; the link to this pipeline is from MEED sources [1]
  • Engineering & procurement · not started
  • Construction · unknown
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 guest.meed.com · checked 5 Nov 2026

CONFIRMEDMEDIUMKuwait · Terminal & storage

Kuwait Oil Company Jurassic Light Oil export: 6 crude storage tanks of 618,000 barrels, new pipelines, export network upgrade

Larsen & Toubro (L&T Energy Hydrocarbon Onshore) (EPC contractor, full turnkey)
  1. FEED: FEED: unknown
  2. Award: EPC award: done, 15 Jul 2026
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: unknown
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Engineering & procurement
Value
USD 979.2m [1]
Workforce
not published
Finish
not published
No open adverts linked today
Client, scope, phases, sources

Client: Kuwait Oil Company (KOC)

Value: KD 303.5m, about USD 979.2m (MEED) [1]

Scope
  • EPC on a fixed-price full turnkey basis of six new crude oil storage tanks of 618,000 barrels each, new pipelines and upgrades to the crude loading and export network [1]
Phase by phase
  • FEED · unknown
  • EPC award · done · 15 Jul 2026 · Awarded 15 Jul 2026; only two bids in Oct 2025: L&T KD 303.5m, Petrofac KD 310.6m (MEED) [1]
  • Engineering & procurement · in progress
  • Construction · unknown
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 guest.meed.com · checked 5 Nov 2026

CONFIRMEDMEDIUMOman · Gas processing

PDO Budour-Northeast Birba integrated gas project (Dhofar)

Enppi (Egypt) (main EPC contractor)
  1. FEED: FEED: unknown
  2. Award: EPC award: done, May 2026
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: unknown
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Engineering & procurement
Value
USD 355m [1]
Workforce
not published
Finish
not published
No open adverts linked today
Client, scope, phases, sources

Client: Petroleum Development Oman (PDO)

Value: USD 355m (MEED headline) [1]

Scope
  • main EPC contract for the Budour-Northeast Birba integrated gas project, Dhofar governorate [1]
Phase by phase
  • FEED · unknown
  • EPC award · done · May 2026 · MEED reported the award in Apr 2026; Enppi confirmed on 22 May 2026 [1]
  • Engineering & procurement · in progress
  • Construction · unknown
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 meed.com · checked 5 Nov 2026

REPORTEDSMALLChina · Pipeline

Heihe-Daqing and Daqing-Changling natural gas pipeline, Section I: 279 km

Sinopec Oil Engineering and Construction Corporation (Sinopec Oilfield Service unit) (EPC contractor)
  1. FEED: FEED: unknown
  2. Award: EPC award: in progress, Jul 2026
  3. E&P: Engineering & procurement: not started
  4. Build: Construction: unknown
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: EPC award
Value
CNY 1.8bn [1]
Workforce
not published
Finish
construction expected to take 710… [1]
No open adverts linked today
Client, scope, phases, sources

Client: not stated in the source

Value: RMB 1.772bn, about USD 246m (company disclosure via PGJ) [1]

Finish: construction expected to take 710 days [1]

Scope
  • 279 km natural gas pipeline section in north-east China; Sinopec says the contract is not yet formally executed [1]
Phase by phase
  • FEED · unknown
  • EPC award · in progress · Jul 2026 · Winning bid disclosed Jul 2026; contract not yet formally executed [1]
  • Engineering & procurement · not started
  • Construction · unknown
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 pgjonline.com · checked 5 Nov 2026

REPORTEDIraq · Onshore oil field

Nahr Bin Umar and Sindbad fields (Basra): integrated field management and EPCM

Halliburton (IFMS and EPCM)
  1. FEED: FEED: unknown
  2. Award: EPC award: done, Jul 2026
  3. E&P: Engineering & procurement: not started
  4. Build: Construction: unknown
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Last step done: EPC award
Value
not published
Workforce
not published
Finish
not published
No open adverts linked today
Client, scope, phases, sources

Client: Basra Oil Company (BOC)

Value: not published

Scope
  • integrated field management services and engineering, procurement and construction management for the two fields in southern Iraq [1]
Phase by phase
  • FEED · unknown
  • EPC award · done · Jul 2026 · Reported by Iraq Business News, 21 Jul 2026 [1]
  • Engineering & procurement · not started
  • Construction · unknown
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 iraq-businessnews.com · checked 5 Nov 2026

REPORTEDOFFSHOREChina · Offshore platform

Sinopec Weizhou oilfield expansion (Beibu Gulf): new WZ-CEP central processing platform, 26 km subsea pipeline

Sinopec Petroleum Engineering Design (EPC consortium) · Sinopec Shengli Oil Construction (EPC consortium)
  1. FEED: FEED: done
  2. Award: EPC award: done, Nov 2026
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: not started
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Engineering & procurement
Value
final value not disclosed; tender… [1]
Workforce
not published
Finish
615-day execution period (World… [1]
No open adverts linked today
Client, scope, phases, sources

Client: Sinopec

Value: final value not disclosed; tender estimate RMB 1.04bn (about USD 146m) [1]

Finish: 615-day execution period (World Pipelines) [1]

Scope
  • new processing platform with 8-legged jacket, accommodation and workover module; about 26 km subsea pipeline and fibre-optic cable; 28 well slots; WZ11-4 platform modifications [1]
  • planned execution period 615 days, completion tied to first oil [1]
Phase by phase
  • FEED · done
  • EPC award · done · Nov 2026 · World Pipelines, 9 Nov 2026 [1]
  • Engineering & procurement · in progress
  • Construction · not started
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 worldpipelines.com · checked 12 Nov 2026

REPORTEDKazakhstan · Gas processing

QazaqGaz second Kashagan gas processing plant (2.5 bcm/y), Atyrau region

China National Chemical Engineering Sixth Construction Company - Kazakhstan Branch (EPCC consortium) · China Wuhuan Engineering Corporation (EPCC consortium) · AVC Production LLP (EPCC consortium) · C-NRG (Synergy) LLP (EPCC consortium)
  1. FEED: FEED: done
  2. Award: EPC award: done, Nov 2026
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: not started
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Engineering & procurement
Value
not published
Workforce
not published
Finish
not published in the source
No open adverts linked today
Client, scope, phases, sources

Client: QazaqGaz Processing LLP (QazaqGaz)

Value: not published

Scope
  • EPCC contract for a gas processing plant with 2.5 billion m3/year capacity at the Kashagan field [1]
Phase by phase
  • FEED · done
  • EPC award · done · Nov 2026 · EPCC signed (Trend, 6 Nov 2026) [1]
  • Engineering & procurement · in progress
  • Construction · not started
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 trend.az · checked 12 Nov 2026

REPORTEDSMALLAlgeria · Gas compression

Zarzaitine field (Illizi): gas lift compression unit upgrade

Tianchen Engineering Corporation (EPCC consortium) · Shaanxi Yanchang Petroleum (EPCC consortium)
  1. FEED: FEED: done
  2. Award: EPC award: done, May 2026
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: unknown
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Engineering & procurement
Value
USD 238.8m [1]
Workforce
not published
Finish
45-month term (MEED) [1]
No open adverts linked today
Client, scope, phases, sources

Client: Groupement Sonatrach-Sinopec (GSS)

Value: USD 238.8m (MEED) [1]

Scope
  • EPCC upgrade of the gas lift compression unit at Zarzaitine, 45-month term [1]
Phase by phase
  • FEED · done
  • EPC award · done · May 2026 · MEED, 14 May 2026 [1]
  • Engineering & procurement · in progress
  • Construction · unknown
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 guest.meed.com · checked 12 Nov 2026

REPORTEDMEDIUMAlgeria · Gas compression

Sonatrach Rourd Ennous gas field (Illizi): new gas compression station and pipeline network upgrade

Jereh Oil & Gas Engineering Group (EPC contractor)
  1. FEED: FEED: done
  2. Award: EPC award: done, Jul 2025
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: in progress
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Construction
Value
USD 855m [1]
Workforce
not published
Finish
2028 [1]
No open adverts linked today
Client, scope, phases, sources

Client: Sonatrach

Value: USD 855m (Algerian press) [1]

Finish: phased development through 2028 (Algerian press) [1]

Scope
  • new gas compression station and upgraded field pipeline network; phased works to 2028 [1]
Phase by phase
  • FEED · done
  • EPC award · done · Jul 2025 · signed July 2025 [1]
  • Engineering & procurement · in progress
  • Construction · in progress
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 dzair-tube.dz · checked 12 Nov 2026

REPORTEDMEDIUMOFFSHORELibya · Offshore platform

Bouri gas utilisation project (NC-41 offshore)

Saipem (main contractor (awarded Aug 2023))
  1. FEED: FEED: done
  2. Award: EPC award: done, Aug 2023
  3. E&P: Engineering & procurement: done
  4. Build: Construction: done
  5. Comm.: Pre-commissioning & commissioning: in progress, Oct 2026
  6. Start: Start-up: in progress
Now: Start-up
Value
USD 1bn [1]
Workforce
not published
Finish
start-up under way (MEED, 20 Oct… [1]
No open adverts linked today
Client, scope, phases, sources

Client: Mellitah Oil & Gas (NOC-Eni JV)

Value: USD 1bn main contract (MEED) [1]

Finish: start-up under way (MEED, 20 Oct 2026) [1]

Scope
  • gas utilisation project on the Bouri offshore field; mechanical completion reported, start-up procedures under way [1]
Phase by phase
  • FEED · done
  • EPC award · done · Aug 2023 · Saipem [1]
  • Engineering & procurement · done
  • Construction · done
  • Pre-commissioning & commissioning · in progress · Oct 2026 · mechanical completion reported by MEED, 20 Oct 2026 [1]
  • Start-up · in progress

Sources: 1 guest.meed.com · checked 12 Nov 2026

REPORTEDUganda · Onshore oil field

CNOOC Kingfisher oilfield (Lake Albert): central processing facility, 40,000 b/d

CNOOC group (built the surface facilities (CGTN); EPC package holders not re-verified on an open source)
  1. FEED: FEED: done
  2. Award: EPC award: done
  3. E&P: Engineering & procurement: done
  4. Build: Construction: done
  5. Comm.: Pre-commissioning & commissioning: in progress, Sep 2026
  6. Start: Start-up: not started
Now: Pre-commissioning & commissioning
Value
not published
Workforce
not published
Finish
first oil date not published
No open adverts linked today
Client, scope, phases, sources

Client: CNOOC Uganda (operator; TotalEnergies, UNOC partners)

Value: not published

Scope
  • central processing facility, 2 million t/y; peak 40,000 b/d; mechanical completion accepted Sep 2026 [1]
Phase by phase
  • FEED · done
  • EPC award · done [1]
  • Engineering & procurement · done
  • Construction · done
  • Pre-commissioning & commissioning · in progress · Sep 2026 · mechanical completion acceptance (CGTN, 10 Sep 2026); commissioning prep 74% in Jun 2026 [1]
  • Start-up · not started

Sources: 1 news.cgtn.com 2 kampalapost.com · checked 12 Nov 2026

ON THE RADARGabon · Refinery

SOGARA Port-Gentil refinery: debottlenecking and new modular hydrocracker complex with marine jetty

Technip Energies (two FEED contracts)
  1. FEED: FEED: in progress, Apr 2026
  2. Award: EPC award: not started
  3. E&P: Engineering & procurement: not started
  4. Build: Construction: not started
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: FEED
Value
not published
Workforce
not published
Finish
not published
No open adverts linked today
Client, scope, phases, sources

Client: Société Gabonaise de Raffinage (SOGARA)

Value: not published

Scope
  • FEED 1: debottlenecking, kerosene sweetening unit, four storage facilities; FEED 2: modular hydrocracker complex, SMR hydrogen, marine jetty [1]
Phase by phase
  • FEED · in progress · Apr 2026 · two FEED contracts to Technip Energies [1]
  • EPC award · not started
  • Engineering & procurement · not started
  • Construction · not started
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 hydrocarbonprocessing.com · checked 12 Nov 2026

REPORTEDNigeria · Pipeline

Ajaokuta-Kaduna-Kano (AKK) gas pipeline: Ajaokuta-Kaduna section (303 km) and gas treatment facilities

Oilserv (contractor for the 303 km Ajaokuta-Kaduna stretch (other lots not re-verified))
  1. FEED: FEED: done
  2. Award: EPC award: done
  3. E&P: Engineering & procurement: done
  4. Build: Construction: in progress
  5. Comm.: Pre-commissioning & commissioning: in progress, Jul 2026
  6. Start: Start-up: not started
Now: Pre-commissioning & commissioning
Value
not published
Workforce
not published
Finish
remaining works end-2026 to Q1… [1]
No open adverts linked today
Client, scope, phases, sources

Client: NNPC Ltd

Value: not published

Finish: remaining works end-2026 to Q1 2027 (Oilserv chairman) [1]

Scope
  • 303 km pipeline mechanically complete per Oilserv; gas treatment facilities at Ajaokuta and Abuja and some block valve stations still under construction [1]
Phase by phase
  • FEED · done
  • EPC award · done
  • Engineering & procurement · done
  • Construction · in progress
  • Pre-commissioning & commissioning · in progress · Jul 2026 · mechanical completion of the line stated by Oilserv chairman [1]
  • Start-up · not started

Sources: 1 billionaires.africa · checked 12 Nov 2026

REPORTEDOFFSHORENigeria · Pipeline

NLNG gas transmission system GTS-1 expansion: shallow-water pipeline to Bonny Island (about 6 km)

Oilserv (pipeline installation contractor)
  1. FEED: FEED: unknown
  2. Award: EPC award: done
  3. E&P: Engineering & procurement: done
  4. Build: Construction: in progress
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Construction
Value
not published
Workforce
not published
Finish
not published
No open adverts linked today
Client, scope, phases, sources

Client: Nigeria LNG (NLNG) gas supply network

Value: not published

Scope
  • about 6 km of shallow-water pipeline to the Bonny Island LNG plant; barge installation, welding, testing and tie-ins [1]
Phase by phase
  • FEED · unknown
  • EPC award · done
  • Engineering & procurement · done
  • Construction · in progress
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 gazettengr.com · checked 12 Nov 2026

REPORTEDTanzania · Pipeline

Ntorya-Madimba gas pipeline (Mtwara), feeding the Madimba gas processing plant

China Petroleum Pipeline (EPC contractor) · China Petroleum Technology & Development Corporation (EPC contractor)
  1. FEED: FEED: done
  2. Award: EPC award: done, Jul 2025
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: unknown
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Engineering & procurement
Value
not published
Workforce
not published
Finish
not published
No open adverts linked today
Client, scope, phases, sources

Client: Tanzania Petroleum Development Corporation (TPDC)

Value: not published

Scope
  • EPC contract for the gas pipeline from the Ntorya field to the Madimba gas processing plant [1]
Phase by phase
  • FEED · done
  • EPC award · done · Jul 2025 · TPDC award, Jul 2025 [1]
  • Engineering & procurement · in progress
  • Construction · unknown
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 tanzaniainvest.com · checked 12 Nov 2026

CONFIRMEDOFFSHOREUnited States · Subsea

Kosmos Tiberius (Keathley Canyon 964, US Gulf): 14 km steel catenary riser and flowline to the Lucius spar

Subsea7 (SURF EPCI (fabrication, transport and installation))
  1. FEED: FEED: unknown
  2. Award: EPC award: done
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: not started
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Engineering & procurement
Value
'sizeable' contract, USD 50-150 m… [1]
Workforce
not published
Finish
first oil expected by end of Q3… [2]
No open adverts linked today
Client, scope, phases, sources

Client: Kosmos Energy (operator, 33.34%), Occidental 33.33%, Navitas Petroleum 33.33%

Value: 'sizeable' contract, USD 50-150 m by Subsea7's own definition [1]

Finish: first oil expected by end of Q3 2028 (OGJ) [2]

Scope
  • 14 km steel catenary riser and wet-insulated flowline to the Lucius spar [1]
  • about 2,200 m water depth [1]
Phase by phase
  • FEED · unknown
  • EPC award · done · Subsea7 awarded 13 Nov 2026 [1]
  • Engineering & procurement · in progress · project management and engineering starting in Houston [1]
  • Construction · not started · offshore activities from 2028 [1]
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 investegate.co.uk 2 ogj.com · checked 14 Nov 2026

CONFIRMEDLARGEUnited States · LNG plant

Port Arthur LNG Phase 1 and Phase 2 (Jefferson County, Texas)

Bechtel (EPC, Phase 1 and Phase 2 (full notice to proceed on both))
  1. FEED: FEED: done
  2. Award: EPC award: done, Mar 2023
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: in progress
  5. Comm.: Pre-commissioning & commissioning: unknown
  6. Start: Start-up: not started
Now: Construction
Value
USD 13bn [1]
Workforce
an estimated 5,000 construction jobs (Sempra and Bechtel at Phase 1 FID) [1]
Finish
2027 [2]
No open adverts linked today
Client, scope, phases, sources

Client: Sempra Infrastructure (Port Arthur LNG); Phase 2 anchor buyer ConocoPhillips

Value: about USD 13 billion estimated capex for Phase 1 (Sempra at FID, March 2023); Phase 2 about USD 12 billion plus about USD 2 billion for shared facilities [1]

Finish: Train 1 commercial operation expected 2027, Train 2 2028 (Phase 1); Trains 3 and 4 in 2030-2031 (Phase 2) [2]

Scope
  • Phase 1: 2 liquefaction trains, 2 storage tanks, about 13 Mtpa [1]
  • Phase 2: 2 more trains (Trains 3 and 4) and 1 tank, about 13 Mtpa; FID September 2025 [2]
Phase by phase
  • FEED · done
  • EPC award · done · Mar 2023 · Phase 1 FID and notice to proceed to Bechtel; Phase 2 in September 2025 [1]
  • Engineering & procurement · in progress
  • Construction · in progress · Phase 1 under construction; Phase 2 awarded with full notice to proceed [2]
  • Pre-commissioning & commissioning · unknown
  • Start-up · not started · Train 1 commercial operation expected 2027, Train 2 2028 [1]

Sources: 1 bechtel.com 2 lngindustry.com · checked 19 Nov 2026

CONFIRMEDUnited States · LNG plant

CP2 LNG Phase 1, Phase 2 and CP2 Expansion (Cameron Parish, Louisiana)

Worley (EPC (reimbursable) on Phase 1, Phase 2 and the CP2 Expansion)
  1. FEED: FEED: done
  2. Award: EPC award: done, Nov 2026
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: in progress, Mar 2026
  5. Comm.: Pre-commissioning & commissioning: unknown
  6. Start: Start-up: not started
Now: Construction
Value
EPC value not disclosed; total… [3]
Workforce
not published
Finish
Expansion FID targeted for early… [1]
No open adverts linked today
Client, scope, phases, sources

Client: Venture Global (CP2 LNG)

Value: EPC value not disclosed; total CP2 project financing USD 20.7 billion after the Phase 2 FID (Venture Global) [3]

Finish: Expansion FID targeted for early 2027 [1]

Scope
  • more than 29 Mtpa nameplate once complete (Venture Global) [2]
  • Expansion: 6 more liquefaction blocks, a gas-fired power plant and a third berth, about +11.7 Mtpa peak (FERC filing) [2]
Phase by phase
  • FEED · done
  • EPC award · done · Nov 2026 · Worley EPC on Phase 1 and 2; EPC for the Expansion signed Nov 2026 [1]
  • Engineering & procurement · in progress
  • Construction · in progress · Mar 2026 · Phase 2 FID 13 Mar 2026 [3]
  • Pre-commissioning & commissioning · unknown
  • Start-up · not started

Sources: 1 lngindustry.com 2 hydrocarbonprocessing.com 3 worldoil.com · checked 19 Nov 2026

CONFIRMEDUnited States · LNG plant

Corpus Christi LNG Midscale Trains 8 & 9 and debottlenecking (Texas)

Bechtel (EPC, full notice to proceed June 2025)
  1. FEED: FEED: done
  2. Award: EPC award: done, Jun 2025
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: in progress
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Construction
Value
not published by Cheniere
Workforce
not published
Finish
later this decade (Cheniere) [1]
No open adverts linked today
Client, scope, phases, sources

Client: Cheniere (Corpus Christi Liquefaction)

Value: not published by Cheniere

Scope
  • 2 midscale trains, over 3 Mtpa; with debottlenecking about 5 Mtpa; Corpus Christi over 30 Mtpa later this decade [1]
Phase by phase
  • FEED · done
  • EPC award · done · Jun 2025 · FID and full notice to proceed to Bechtel [1]
  • Engineering & procurement · in progress
  • Construction · in progress · built next to the Stage 3 project [1]
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 cheniere.com · checked 19 Nov 2026

CONFIRMEDLARGEUnited States · LNG plant

Golden Pass LNG (Sabine Pass, Texas): Trains 1-3

McDermott (EPC JV partner (revised EPC contract Nov 2025)) · Chiyoda (EPC JV partner (Chiyoda International Corp.)) · Zachry Group, partner of the original 2019 EPC JV, is not a party to the revised EPC contract of November 2025
  1. FEED: FEED: done
  2. Award: EPC award: done
  3. E&P: Engineering & procurement: done
  4. Build: Construction: in progress
  5. Comm.: Pre-commissioning & commissioning: in progress
  6. Start: Start-up: in progress, Mar 2026
Now: Start-up
Value
USD 10bn [3]
Workforce
more than 7,000 at peak construction (Golden Pass, via Port Arthur News, 2022) [3]
Finish
2027 [2]
No open adverts linked today
Client, scope, phases, sources

Client: Golden Pass LNG (QatarEnergy 70%, ExxonMobil 30%)

Value: the USD 10 billion project (Port Arthur News, 2022) [3]

Finish: Train 3 targeted for H1 2027 [2]

Scope
  • 3 trains, 18 Mtpa; Train 1 first LNG 30 March 2026, first cargo 22 April 2026 [2]
  • revised EPC contract for Trains 2 and 3 signed by McDermott and Chiyoda in November 2025 [1]
Phase by phase
  • FEED · done
  • EPC award · done
  • Engineering & procurement · done
  • Construction · in progress · Trains 2 and 3 [2]
  • Pre-commissioning & commissioning · in progress · Train 2 start-up targeted H2 2026 [2]
  • Start-up · in progress · Mar 2026 · Train 1 first LNG [2]

Sources: 1 lngindustry.com 2 gasprocessingnews.com 3 panews.com 4 hydrocarbonengineering.com · checked 19 Nov 2026

CONFIRMEDLARGEUnited States · LNG plant

Louisiana LNG (Woodside, Calcasieu Parish): 3-train foundation development

Bechtel (EPC contractor)
  1. FEED: FEED: done
  2. Award: EPC award: done, Apr 2025
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: in progress, Jun 2026
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Construction · 28% complete (Jun 2026) [1]
28%
Value
USD 17.5bn [1]
Workforce
almost 900 construction personnel in September 2025 (Woodside); peak not published [2]
Finish
2029 [1]
No open adverts linked today
Client, scope, phases, sources

Client: Woodside Energy (Louisiana LNG)

Value: USD 17.5 billion project (OffshoreSource, Aug 2026) [1]

Finish: first cargo targeted for 2029 [1]

Scope
  • 3 trains, 16.5 Mtpa; permitted for 27.6 Mtpa with 2 expansion trains [2]
  • 2 storage tanks of 235,000 m3 each [1]
Phase by phase

Progress: 28% overall at end of Q2 2026 (Train 1 35%, Train 2 25%, Train 3 18%) [1]

  • FEED · done
  • EPC award · done · Apr 2025 · FID 29 April 2025 [2]
  • Engineering & procurement · in progress
  • Construction · in progress · Jun 2026 · 28% overall; Train 1 35%, Train 2 25%, Train 3 18% [1]
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 offshoresource.com 2 hydrocarbonengineering.com · checked 19 Nov 2026

CONFIRMEDUnited States · LNG plant

Commonwealth LNG (Cameron Parish, Louisiana): 6 SnapLNG trains

Technip Energies (EPC, full notice to proceed after FID (May 2026))
  1. FEED: FEED: done
  2. Award: EPC award: done, May 2026
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: in progress
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Construction
Value
USD 1.2bn [1]
Workforce
not published
Finish
not published in the source read…
No open adverts linked today
Client, scope, phases, sources

Client: Commonwealth LNG (Caturus)

Value: over USD 1.17 billion in revenue for Technip Energies [1]

Finish: not published in the source read today

Scope
  • 6 identical modular liquefaction trains (SnapLNG by T.EN), 9.5 Mtpa [1]
Phase by phase
  • FEED · done
  • EPC award · done · May 2026 · FID and full notice to proceed [1]
  • Engineering & procurement · in progress
  • Construction · in progress
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 oedigital.com · checked 19 Nov 2026

ON THE RADARUnited States · LNG plant

Texas LNG (Port of Brownsville, Texas)

Kiewit (lump-sum turnkey EPC, signed March 2026; limited notice to proceed July 2026; modules at Kiewit Offshore Services, Ingleside)
  1. FEED: FEED: done
  2. Award: EPC award: done, Mar 2026
  3. E&P: Engineering & procurement: in progress, Jul 2026
  4. Build: Construction: not started
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Engineering & procurement
Value
not disclosed
Workforce
not published
Finish
FID not yet announced (checked…
No open adverts linked today
Client, scope, phases, sources

Client: Glenfarne (Texas LNG)

Value: not disclosed

Finish: FID not yet announced (checked today)

Scope
  • about 4 Mtpa export project; EPC executed after 14 months of pre-FID engineering [2]
  • limited notice to proceed: long-lead orders, EPC engineering and geotechnical work before FID [1]
Phase by phase
  • FEED · done
  • EPC award · done · Mar 2026 · EPC contract executed [2]
  • Engineering & procurement · in progress · Jul 2026 · limited notice to proceed [1]
  • Construction · not started
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 lngindustry.com 2 offshore-technology.com · checked 19 Nov 2026

REPORTEDKazakhstan · Gas processing

QazaqGaz new Karachaganak gas processing plant (5 bcm/y), West Kazakhstan Region

Hyundai Engineering Co., Ltd. (EPC consortium (shares not published)) · SICIM Kazakhstan LLP (EPC consortium (shares not published))
  1. FEED: FEED: done
  2. Award: EPC award: done, 12 Nov 2026
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: not started
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Engineering & procurement
Value
not published
Workforce
not published
Finish
not published in the source
No open adverts linked today
Client, scope, phases, sources

Client: QazaqGaz Processing LLP (QazaqGaz National Company)

Value: not published

Scope
  • 5 bcm/y gas processing plant for raw gas from Karachaganak; products: commercial gas, LPG, sulphur [1]
Phase by phase
  • FEED · done
  • EPC award · done · 12 Nov 2026 · EPC contract signed with Hyundai Engineering and SICIM Kazakhstan [1]
  • Engineering & procurement · in progress
  • Construction · not started
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 trend.az · checked 19 Nov 2026

REPORTEDUAE · Onshore oil field

ADNOC Onshore North East Bab (NEB) cluster: facilities upgrade phase 2 (Al Nouf, Rumaitha, Shanayel CPP)

Mannesmann Energy (Abu Dhabi) (EPC, phase 2 facilities upgrade (picked by ADNOC Onshore, MEED))
  1. FEED: FEED: unknown
  2. Award: EPC award: done, Nov 2026
  3. E&P: Engineering & procurement: unknown
  4. Build: Construction: not started
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Last step done: EPC award
Value
not published
Workforce
not published
Finish
not published in the source
No open adverts linked today
Client, scope, phases, sources

Client: ADNOC Onshore

Value: not published

Scope
  • upgrade of existing facilities and production capacity at NEB CPP assets in Al Nouf, Rumaitha and Shanayel [2]
Phase by phase
  • FEED · unknown
  • EPC award · done · Nov 2026 · ADNOC Onshore picked Mannesmann Energy for phase 2 (MEED) [1]
  • Engineering & procurement · unknown
  • Construction · not started
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 meed.com 2 wam.ae · checked 19 Nov 2026

CONFIRMEDOFFSHOREMalaysia · Subsea

PETRONAS Limbayong deepwater development, offshore Sabah: full subsea scope

TechnipFMC (FMC Wellhead Equipment Sdn. Bhd.) (iEPCI, entire subsea scope)
  1. FEED: FEED: done
  2. Award: EPC award: done, Sep 2026
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: not started
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Engineering & procurement
Value
USD 75-250 million (TechnipFMC… [1]
Workforce
not published
Finish
not published in the source
No open adverts linked today
Client, scope, phases, sources

Client: PETRONAS Carigali Sdn. Bhd.

Value: USD 75-250 million (TechnipFMC 'significant' contract band) [1]

Scope
  • greenfield deepwater development; iEPCI with Subsea 2.0 configure-to-order equipment [1]
Phase by phase
  • FEED · done
  • EPC award · done · Sep 2026 · iEPCI to TechnipFMC [1]
  • Engineering & procurement · in progress
  • Construction · not started
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 energy-pedia.com · checked 19 Nov 2026

CONFIRMEDJapan · Terminal & storage

Shikoku Electric Sakaide LNG terminal upgrade

JFE Engineering (JV (roles not published)) · Kawasaki Heavy Industries (JV (roles not published))
  1. FEED: FEED: done
  2. Award: EPC award: done, Mar 2026
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: not started
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Engineering & procurement
Value
not disclosed
Workforce
not published
Finish
not published in the source
No open adverts linked today
Client, scope, phases, sources

Client: Shikoku Electric Power

Value: not disclosed

Scope
  • upgrade of the Sakaide LNG terminal [1]
Phase by phase
  • FEED · done
  • EPC award · done · Mar 2026 · JFE Engineering and Kawasaki Heavy Industries JV [1]
  • Engineering & procurement · in progress
  • Construction · not started
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 lngprime.com · checked 19 Nov 2026

CONFIRMEDTaiwan · Terminal & storage

CPC Kaohsiung Intercontinental LNG receiving terminal: regasification facility (1,600 t/h)

CTCI (EPC, regasification facility)
  1. FEED: FEED: done
  2. Award: EPC award: done, Aug 2025
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: not started
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Engineering & procurement
Value
TWD 29.6bn [1]
Workforce
not published
Finish
2030 [1]
No open adverts linked today
Client, scope, phases, sources

Client: CPC Corporation

Value: NT$29.6bn (about USD 968m), EPC contract [1]

Finish: expected to be operational by 2030 (Offshore Technology) [1]

Scope
  • regasification facility, output 1,600 t/h; expected operational by 2030 [1]
Phase by phase
  • FEED · done
  • EPC award · done · Aug 2025 · EPC to CTCI, NT$29.6bn [1]
  • Engineering & procurement · in progress
  • Construction · not started
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 offshore-technology.com · checked 19 Nov 2026

REPORTEDOFFSHOREAustralia · Offshore platform

Ichthys LNG Phase 2c Part 1: five subsea production wells (Brewster reservoir)

McDermott (subsea EPCI, in consortium with Baker Hughes) · Baker Hughes (subsea EPCI, in consortium with McDermott)
  1. FEED: FEED: unknown
  2. Award: EPC award: done, 19 Nov 2026
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: not started
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Engineering & procurement
Value
not published
Workforce
not published
Finish
not published
No open adverts linked today
Client, scope, phases, sources

Client: Ichthys Joint Venture (INPEX, operator)

Value: not published

Scope
  • five production wells targeting the Brewster reservoir, using existing drill centres; new subsea infrastructure tied back to the existing offshore system; Browse Basin, about 220 km off Western Australia [1]
Phase by phase
  • FEED · unknown
  • EPC award · done · 19 Nov 2026 · McDermott and Baker Hughes consortium, EPCI [1]
  • Engineering & procurement · in progress
  • Construction · not started
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 ogj.com · checked 20 Nov 2026

REPORTEDMEDIUMUAE · Gas processing

ADNOC Onshore Ruwais Diyab unconventional gas development: surface facilities and pipeline network (design-build-operate)

Jereh Group (design, build and operate: 29 months construction, 60 months operations (Jereh filing on the Shenzhen Stock Exchange, via MEED))
  1. FEED: FEED: done
  2. Award: EPC award: done, Nov 2026
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: not started
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Engineering & procurement
Value
USD 1.7bn [1]
Workforce
not published
Finish
2029 [1]
No open adverts linked today
Client, scope, phases, sources

Client: ADNOC Onshore

Value: USD 1.7 billion (Jereh filing, via MEED) [1]

Finish: first gas from 2029 [1]

Scope
  • 345 million scf/d of raw gas from 2029 over 25 years, potentially up to 1 billion scf/d; ADNOC FID on 2 Nov 2026 [1]
  • ADNOC final investment decision announced at ADIPEC, 2 Nov 2026 [2]
Phase by phase
  • FEED · done
  • EPC award · done · Nov 2026 · Jereh, design-build-operate (company filing reported by MEED, 13 Nov 2026) [1]
  • Engineering & procurement · in progress
  • Construction · not started
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 guest.meed.com 2 worldoil.com · checked 26 Nov 2026

REPORTEDMEDIUMUAE · Onshore oil field

ADNOC Onshore Bu Hasa cluster (Bu Hasa, Bida Al-Qemzan, Huwaila): wellhead surface facilities and gathering flowlines

Jereh Group (EPC, framework agreement on call-off basis) · Galfar Emirates (portion of the scope (MEED))
  1. FEED: FEED: unknown
  2. Award: EPC award: done, Nov 2026
  3. E&P: Engineering & procurement: unknown
  4. Build: Construction: unknown
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Last step done: EPC award
Value
USD 392.1m [1]
Workforce
not published
Finish
36-month framework with 24-month… [1]
No open adverts linked today
Client, scope, phases, sources

Client: ADNOC Onshore

Value: AED 1.44 billion (USD 392.1 million), Jereh filing via MEED [1]

Finish: 36-month framework with 24-month extension option [1]

Scope
  • production well module skids, gas lift skids, wellhead control panels and solar power units; 36 months plus 24-month option [1]
Phase by phase
  • FEED · unknown
  • EPC award · done · Nov 2026 · framework agreement, 36 months + 24-month option [1]
  • Engineering & procurement · unknown
  • Construction · unknown
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 guest.meed.com · checked 26 Nov 2026

REPORTEDArgentina · Pipeline

Argentina LNG: twin export pipelines, about 527 km (48-inch gas, 24-inch liquids), Neuquén to Río Negro coast

Pumpco (pipeline construction consortium, best offer (EconoJournal; shares not defined yet)) · Bonatti (pipeline construction consortium, best offer) · Contreras Hermanos (local partner in the construction consortium) · Tenaris (supply: 24-inch liquids pipe (YPF tender, Nov 2026)) · Grupo Cuñado and CPW (supply: 48-inch gas pipe (YPF tender, Nov 2026))
  1. FEED: FEED: unknown
  2. Award: EPC award: in progress, 9 Jul 2026
  3. E&P: Engineering & procurement: not started
  4. Build: Construction: not started
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: EPC award
Value
construction not published; pipe… [2]
Workforce
not published
Finish
not published
No open adverts linked today
Client, scope, phases, sources

Client: Argentina LNG (YPF with ENI and XRG)

Value: construction not published; pipe tenders about USD 2 billion (Perfil) [2]

Scope
  • two parallel pipelines of about 527 km: 48-inch gas and 24-inch liquids [1]
  • route from Meseta Buena Esperanza (Neuquén) to Sierra Grande (Río Negro); pipe supply awarded by reverse auction [2]
Phase by phase
  • FEED · unknown
  • EPC award · in progress · 9 Jul 2026 · Pumpco-Bonatti-Contreras best offer, award not confirmed by an official source; construction subject to FID [1]
  • Engineering & procurement · not started
  • Construction · not started
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 econojournal.com.ar 2 perfil.com · checked 26 Nov 2026

CONFIRMEDOFFSHORECanada · Pipeline

Prince Rupert Gas Transmission (PRGT): subsea section, about 50 km to Ksi Lisims LNG (Pearse Island)

Allseas (pipelay of the subsea section (Solitaire and Sandpiper))
  1. FEED: FEED: unknown
  2. Award: EPC award: done, 28 Jul 2026
  3. E&P: Engineering & procurement: unknown
  4. Build: Construction: not started
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Last step done: EPC award
Value
not published
Workforce
not published
Finish
2029 [1]
No open adverts linked today
Client, scope, phases, sources

Client: Western LNG

Value: not published

Finish: offshore installation planned for 2029 [1]

Scope
  • about 50 km of 36 and 48-inch concrete-weight coated pipeline, shoreline to about 450 m water depth; shore crossings, tie-ins, trenching [1]
Phase by phase
  • FEED · unknown
  • EPC award · done · 28 Jul 2026 · installation contract; Ksi Lisims LNG FID not stated in the source [1]
  • Engineering & procurement · unknown
  • Construction · not started
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 allseas.com · checked 26 Nov 2026

REPORTEDGermany · Terminal & storage

German LNG Terminal, Brunsbüttel: onshore LNG import terminal (about 10 bcm/year)

Cobra IS (terminal consortium with Sener (client of MT Group)) · Sener (terminal consortium with Cobra IS) · MT Group (balance-of-plant infrastructure)
  1. FEED: FEED: done
  2. Award: EPC award: done, 28 Jul 2026
  3. E&P: Engineering & procurement: in progress
  4. Build: Construction: in progress
  5. Comm.: Pre-commissioning & commissioning: not started
  6. Start: Start-up: not started
Now: Construction
Value
not published
Workforce
not published
Finish
2027 [1]
No open adverts linked today
Client, scope, phases, sources

Client: German LNG Terminal (Gasunie 40%, RWE 10%, KfW 50%)

Value: not published

Finish: completion scheduled for 2027 (MT Group) [1]

Scope
  • onshore LNG import terminal, about 10 bcm/year into the German grid [1]
Phase by phase
  • FEED · done
  • EPC award · done · 28 Jul 2026 · MT Group balance-of-plant award from the Cobra IS / Sener consortium [1]
  • Engineering & procurement · in progress
  • Construction · in progress
  • Pre-commissioning & commissioning · not started
  • Start-up · not started

Sources: 1 lngprime.com · checked 26 Nov 2026

Looking for work on these projects?

You apply to the contractor, not to the client. The Top 10 projects page lists the open jobs we checked today on each contractor's own portal; the jobs page has every opening we link, smaller projects included, by trade and country.

How we estimate workforce: only where no headcount is published. Declared value in USD × the lowest and highest workers per USD million of at least two projects of the same plant family with a published peak headcount and a declared value on the same basis (contract or project). Always a range, never a single number; no estimate for offshore work, fabrication yards or projects without a single declared value. Size uses the declared contract value (the project value when it is the only one); a published band counts only if it falls entirely in one class; other currencies at the ECB reference rates of 29 Oct 2026, AED at its 3.6725 peg. Benchmarks and confidence are in each card.