CONFIRMEDMEDIUMOFFSHORESaudi Arabia · Subsea
Aramco offshore: CRPO 168 and 170, seven production deck manifolds (Abu Safah, Safaniyah, Manifa, Berri, Marjan)
Saipem (EPCI under the long-term agreement (two CRPOs))
- FEED: FEED: unknown
- Award: EPC award: done, 25 Nov 2026
- E&P: Engineering & procurement: in progress
- Build: Construction: not started
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Engineering & procurement
- Value
- USD 650m [1]
- Workforce
- not published
- Finish
- not published
No open adverts linked today
Client, scope, phases, sources
Client: Saudi Aramco
Value: about USD 650 million (both contracts) [1]
Scope
- CRPO 168: EPCI of 4 production deck manifolds, about 14 km of 12-16 inch pipeline and about 24 km of 15 kV cables, subsea facilities for Abu Safah, Safaniyah, Manifa and Berri; onshore tie-in at the Manifa drill site [1]
- CRPO 170: EPCI of 3 production deck manifolds, about 25 km of 12-16 inch pipeline and about 17 km of 15 kV cables, subsea facilities at Marjan [1]
- fabrication at Saipem's Saudi yard (Saipem Taqa Al-Rushaid Fabricators); offshore work by Saipem construction vessels already in the region [1]
Phase by phase
- FEED · unknown
- EPC award · done · 25 Nov 2026 [1]
- Engineering & procurement · in progress
- Construction · not started
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 saipem.com · checked 26 Nov 2026
REPORTEDOFFSHOREQatar · Offshore platform
Maydan Mahzam redevelopment, MM-EPIC2: subsea pipelines, power cables and umbilicals
COOEC (Offshore Oil Engineering Co.) (EPIC contractor for package 2 (MM-EPIC2))
- FEED: FEED: done
- Award: EPC award: done, 20 Nov 2026
- E&P: Engineering & procurement: in progress
- Build: Construction: not started
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Engineering & procurement
- Value
- USD million 0.0008m [1]
- Workforce
- not published
- Finish
- 66-month contract [1]
No open adverts linked today
Client, scope, phases, sources
Client: QatarEnergy
Value: about $800 million (QR2.9 billion), as reported [1]
Scope
- over 100 km of subsea pipelines, power cables and umbilicals offshore Qatar; scope from project management and detailed engineering to procurement, construction, transport, offshore installation and pre-commissioning; 66-month contract [1]
Phase by phase
- FEED · done
- EPC award · done · 20 Nov 2026 · COOEC, MM-EPIC2 contract signed (award first announced in October 2026) [1]
- Engineering & procurement · in progress
- Construction · not started
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 shippingherald.com 2 oilandgasmiddleeast.com 3 saudigulfprojects.com · checked 23 Nov 2026
CONFIRMEDTOP 10LARGEMozambique · LNG plant
Mozambique LNG
Saipem (CCS JV leader) · McDermott (CCS JV partner) · Chiyoda (CCS JV partner)
- FEED: FEED: done
- Award: EPC award: done, Jun 2019
- E&P: Engineering & procurement: in progress
- Build: Construction: in progress
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now:
Construction ·
45% complete (Jul 2026)
[2]45%
- Value
- USD 6bn [1]
- Workforce
- between 7,000 and 8,000 workers (TotalEnergies CEO, Q2 2026 results call) [2]
- Finish
- 2029 [2]
Client, scope, phases, sources
Client: TotalEnergies (operator) for the Mozambique LNG Area 1 partners
Value: approximately USD 6 billion (Saipem's share of the CCS JV EPC contract, 2019) [1]
Finish: first LNG from the first train targeted for 2029 [2]
Scope
- 2 liquefaction trains, 12.88 Mtpa nameplate, storage tanks and export jetty [1]
- up to 13 Mtpa of LNG from 2029; project value USD 20 billion [2]
Phase by phase
Progress: almost 45% complete (TotalEnergies CEO, July 2026) [2]
- FEED · done
- EPC award · done · Jun 2019 [1]
- Engineering & procurement · in progress
- Construction · in progress
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 lngindustry.com 2 clubofmozambique.com · checked 29 Oct 2026
CONFIRMEDTOP 10Qatar · LNG plant
North Field East & South
Chiyoda (CTJV, North Field East) · Technip Energies (CTJV on NFE; T.EN CCC JV leader on NFS) · Consolidated Contractors Company (T.EN CCC JV, North Field South)
- FEED: FEED: done
- Award: EPC award: done, 9 Feb 2021
- E&P: Engineering & procurement: in progress
- Build: Construction: in progress
- Comm.: Pre-commissioning & commissioning: in progress, 7 Oct 2026
- Start: Start-up: not started
Now: Pre-commissioning & commissioning
- Value
- not disclosed by the contractors;… [1]
- Workforce
- not published
- Finish
- 2027 [3]
No open adverts linked today
Client, scope, phases, sources
Client: QatarEnergy
Value: not disclosed by the contractors; each award is 'major' for Technip Energies (NFE: over USD 1.0 bn; NFS: above EUR 1 bn of revenue) [1]
Finish: NFE: production expected to begin in H1 2027 (QatarEnergy CEO, per Reuters); first-train LNG in Q1 2027 per sources [3]
Scope
- NFE: 4 mega trains x 8 Mtpa plus a large CO2 capture and sequestration facility; Qatar from 77 to 110 Mtpa [2]
- NFS: 2 mega trains x 8 Mtpa plus 1.5 Mtpa CO2 capture [1]
Phase by phase
- FEED · done
- EPC award · done · 9 Feb 2021 · NFE 9 Feb 2021; NFS 16 May 2023 [2]
- Engineering & procurement · in progress
- Construction · in progress
- Pre-commissioning & commissioning · in progress · 7 Oct 2026 · first NFE train reported ready to start operation in November 2026 (Reuters, sources) [3]
- Start-up · not started
Sources: 1 ten.com 2 ten.com 3 boereport.com · checked 29 Oct 2026
REPORTEDTOP 10LARGESaudi Arabia · Gas processing
Jafurah
Larsen & Toubro (gas processing facilities, phase 2) · Samsung E&A (gas treatment) · Hyundai E&C (sulphur recovery, with Hyundai Engineering) · Hyundai Engineering (sulphur recovery, with Hyundai E&C)
- FEED: FEED: done
- Award: EPC award: done, 30 Jun 2024
- E&P: Engineering & procurement: in progress
- Build: Construction: in progress
- Comm.: Pre-commissioning & commissioning: unknown
- Start: Start-up: in progress, Dec 2025
Now: Start-up
- Value
- USD 12.4bn [1]
- Workforce
- not published
- Finish
- 2030 [2]
Client, scope, phases, sources
Client: Saudi Aramco
Value: 16 contracts totalling around USD 12.4bn (SR46.5bn) for the second phase (June 2024) [1]
Finish: 2 bscfd of sales gas targeted by 2030 (Aramco) [2]
Scope
- phase 2: gas compression, pipelines, new gas processing trains, utilities, sulphur and export facilities, NGL fractionation at Jubail [1]
- 17,000 km2, 229 tcf of raw gas; 2 bscfd of sales gas, 420 MMscfd ethane and about 630,000 b/d liquids targeted by 2030 [2]
Phase by phase
- FEED · done
- EPC award · done · 30 Jun 2024 · phase 2 contracts [1]
- Engineering & procurement · in progress
- Construction · in progress
- Pre-commissioning & commissioning · unknown
- Start-up · in progress · Dec 2025 · phase 1: first shale gas produced December 2025; phase 2 under construction [2]
Sources: 1 offshore-technology.com 2 aramco.com · checked 26 Nov 2026
CONFIRMEDTOP 10LARGEOFFSHOREUAE · Gas processing
Hail & Ghasha
Saipem (offshore EPC, with NMDC Energy, formerly NPCC) · NMDC Energy (offshore EPC) · Tecnimont (MAIRE) (onshore EPC)
- FEED: FEED: done
- Award: EPC award: done, 5 Oct 2023
- E&P: Engineering & procurement: in progress
- Build: Construction: in progress
- Comm.: Pre-commissioning & commissioning: unknown
- Start: Start-up: not started
Now: Construction
- Value
- USD 16.9bn [1]
- Workforce
- not published
- Finish
- 2028 [2]
Client, scope, phases, sources
Client: ADNOC
Value: USD 16.9bn (SR63.39bn) across two EPC contracts: offshore about USD 8.2bn (NPCC-Saipem), onshore USD 8.7bn (Tecnimont) [1]
Finish: onshore: completion expected during 2028 (MAIRE, 2023); first gas by the end of the decade (The National, Dec 2025) [2]
Scope
- 4 drilling centres and a processing plant on artificial islands; over 300 km of subsea pipelines [1]
- onshore: 2 gas processing units, 3 sulphur recovery sections, export pipelines [2]
- up to 1.8 bscfd of gas; 1.5 Mtpa CO2 capture [3]
Phase by phase
- FEED · done
- EPC award · done · 5 Oct 2023 [2]
- Engineering & procurement · in progress
- Construction · in progress
- Pre-commissioning & commissioning · unknown
- Start-up · not started
Sources: 1 offshore-technology.com 2 tecnimont.com 3 thenationalnews.com · checked 29 Oct 2026
CONFIRMEDTOP 10LARGEUAE · LNG plant
Ruwais LNG
Technip Energies (TJN Ruwais JV leader) · JGC (TJN Ruwais JV partner) · NMDC Energy (TJN Ruwais JV partner)
- FEED: FEED: done
- Award: EPC award: done, 13 Jun 2024
- E&P: Engineering & procurement: in progress
- Build: Construction: in progress
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Construction
- Value
- USD 5.5bn [1]
- Workforce
- not published
- Finish
- 2028 [1]
Client, scope, phases, sources
Client: ADNOC (ADNOC Gas to hold 60%)
Value: EPC contract valued at over USD 5.5 billion (World Oil); 'major' for Technip Energies (above EUR 1 bn of revenue) [1]
Finish: train 1 on stream in H2 2028, train 2 in early 2029 (ADNOC Gas, Nov 2024) [1]
Scope
- 2 trains x 4.8 Mtpa = 9.6 Mtpa [1]
- electric-driven motors instead of gas turbines [2]
Phase by phase
- FEED · done
- EPC award · done · 13 Jun 2024 [2]
- Engineering & procurement · in progress
- Construction · in progress
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 worldoil.com 2 ten.com · checked 29 Oct 2026
CONFIRMEDTOP 10Qatar · LNG plant
North Field West
Technip Energies (T.EN CCC GAC JV leader) · Consolidated Contractors Company (JV partner) · Gulf Asia Contracting (JV partner)
- FEED: FEED: done
- Award: EPC award: done, 25 Feb 2026
- E&P: Engineering & procurement: in progress
- Build: Construction: unknown
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Engineering & procurement
- Value
- not disclosed; 'major' award for… [1]
- Workforce
- not published
- Finish
- not published
No open adverts linked today
Client, scope, phases, sources
Client: QatarEnergy
Value: not disclosed; 'major' award for Technip Energies: above EUR 1 billion of revenue [1]
Scope
- 2 mega trains x 8 Mtpa (about 16 Mtpa) [1]
- 1.1 Mtpa CO2 capture (2.2 Mtpa with NFS) [1]
Phase by phase
- FEED · done
- EPC award · done · 25 Feb 2026 [1]
- Engineering & procurement · in progress
- Construction · unknown
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 ten.com · checked 29 Oct 2026
CONFIRMEDTOP 10LARGESaudi Arabia · Gas processing
Fadhili Gas Plant Expansion
Samsung E&A (gas treatment unit, utilities and offsites) · GS Engineering & Construction (EPC package) · Nesma & Partners (EPC package)
- FEED: FEED: done
- Award: EPC award: done, 2 Apr 2024
- E&P: Engineering & procurement: in progress
- Build: Construction: in progress
- Comm.: Pre-commissioning & commissioning: unknown
- Start: Start-up: not started
Now: Construction
- Value
- USD 7.7bn [1]
- Workforce
- not published
- Finish
- Nov 2027 [1]
No open adverts linked today
Client, scope, phases, sources
Client: Saudi Aramco
Value: USD 7.7 billion of contracts (Aramco) [1]
Finish: expected to be completed by November 2027 (Aramco, April 2024) [1]
Scope
- adds up to 1.5 bscfd of raw gas processing capacity [1]
- adds 2,300 t/d of sulphur production [1]
Phase by phase
- FEED · done
- EPC award · done · 2 Apr 2024 [1]
- Engineering & procurement · in progress
- Construction · in progress
- Pre-commissioning & commissioning · unknown
- Start-up · not started
Sources: 1 aramco.com · checked 26 Nov 2026
CONFIRMEDTOP 10LARGESaudi Arabia · Petrochemical
Amiral
Hyundai E&C (mixed-feed cracker and utilities) · Tecnimont (MAIRE) (two polyethylene units) · Sinopec Engineering Group Saudi (tank farm and SATORP integration)
- FEED: FEED: done
- Award: EPC award: done, 24 Jun 2023
- E&P: Engineering & procurement: in progress
- Build: Construction: in progress
- Comm.: Pre-commissioning & commissioning: unknown
- Start: Start-up: not started
Now: Construction
- Value
- USD 11bn [1]
- Workforce
- no construction figure published; TotalEnergies: 7,000 local direct and indirect jobs (whole project, including the chemicals park) [1]
- Finish
- 2027 [1]
Client, scope, phases, sources
Client: SATORP (Aramco 62.5%, TotalEnergies 37.5%)
Value: an investment of USD 11 billion (TotalEnergies) [1]
Finish: operational start-up planned for 2027 (TotalEnergies) [1]
Scope
- mixed-feed cracker, 1.65 Mtpa of ethylene [1]
- two polyethylene lines of 500,000 t/y each [1]
Phase by phase
- FEED · done
- EPC award · done · 24 Jun 2023 · FID December 2022 [2]
- Engineering & procurement · in progress
- Construction · in progress
- Pre-commissioning & commissioning · unknown
- Start-up · not started
Sources: 1 totalenergies.com 2 totalenergies.com · checked 26 Nov 2026
CONFIRMEDTOP 10MEDIUMOman · LNG plant
Marsa LNG
Technip Energies (EPC, LNG plant) · McDermott (CB&I) (EPC, LNG storage tank)
- FEED: FEED: done
- Award: EPC award: done, 22 Apr 2024
- E&P: Engineering & procurement: in progress
- Build: Construction: in progress
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now:
Construction ·
55% complete (Jun 2026)
[2]55%
- Value
- not disclosed; 'substantial'… [1]
- Workforce
- not published
- Finish
- 2028 [2]
No open adverts linked today
Client, scope, phases, sources
Client: TotalEnergies (80%) and OQ (20%)
Value: not disclosed; 'substantial' award for Technip Energies (EUR 500 million to 1 billion of revenue) [1]
Finish: start-up targeted in the first quarter of 2028 [2]
Scope
- 1 Mtpa liquefaction complex for ship fuelling [2]
- 165,000 m3 LNG storage tank [2]
Phase by phase
Progress: more than 55 per cent complete at the end of June 2026 [2]
- FEED · done
- EPC award · done · 22 Apr 2024 [1]
- Engineering & procurement · in progress
- Construction · in progress
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 ten.com 2 omanobserver.om · checked 29 Oct 2026
CONFIRMEDTOP 10United States · LNG plant
Rio Grande LNG
Bechtel (EPC, all five trains)
- FEED: FEED: done
- Award: EPC award: done
- E&P: Engineering & procurement: in progress, Jun 2026
- Build: Construction: in progress, Jun 2026
- Comm.: Pre-commissioning & commissioning: in progress, Jun 2026
- Start: Start-up: not started
Now:
Pre-commissioning & commissioning ·
74% complete (Jun 2026)
[1]74%
- Value
- not stated in the sources read today
- Workforce
- ~7,500 construction and trade workers during peak construction (NextDecade); FERC approved the raise from 5,225 in April 2026 [2]
- Finish
- 2027 [1]
Client, scope, phases, sources
Client: NextDecade (Rio Grande LNG)
Value: not stated in the sources read today
Finish: first LNG from Train 1 expected in H1 2027; Phase 1 ahead of the guaranteed schedule (NextDecade, Q2 2026) [1]
Scope
- Trains 1-5: about 30 Mtpa expected capacity [1]
- 48 Mtpa under construction and in development; site room for up to 10 trains [2]
Phase by phase
Progress: Trains 1-2: 74.0% (engineering 99.1%, procurement 97.8%, construction 58.9%, commissioning 0.6%); Train 3 50.4%; Train 4 15.5%; Train 5 9.4% [1]
- FEED · done
- EPC award · done
- Engineering & procurement · in progress · Jun 2026 · Trains 1-2 engineering 99.1%, procurement 97.8% [1]
- Construction · in progress · Jun 2026 · Trains 1-2 construction 58.9% [1]
- Pre-commissioning & commissioning · in progress · Jun 2026 · Trains 1-2 commissioning 0.6%; first gas expected H2 2026 [1]
- Start-up · not started
Sources: 1 finviz.com 2 next-decade.com · checked 29 Oct 2026
CONFIRMEDMEDIUMIndia · Refinery
HPCL Mumbai refinery: lube modernisation and bottom upgradation (LMBU)
Technip Energies (EPC)
- FEED: FEED: unknown
- Award: EPC award: done, 12 Oct 2026
- E&P: Engineering & procurement: in progress
- Build: Construction: unknown
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now:
Engineering & procurement ·
9.9% complete (31 Mar 2026)
[1]9.9%
- Value
- INR 57.4bn [1]
- Workforce
- not published
- Finish
- Mar 2028 [1]
No open adverts linked today
Client, scope, phases, sources
Client: Hindustan Petroleum Corp. (HPCL)
Value: project cost Rs 57.40 billion (US$600.4 million) at 31 Mar 2026, up from Rs 46.79 billion; Technip Energies' order: EUR 250-500 million of revenue [1]
Finish: scheduled to be fully completed in March 2028 (HPCL, May 2026) [1]
Scope
- 550,000 t/y integrated hydrocracker and catalytic dewaxing unit [1]
- 850,000 t/y solvent deasphalting unit [1]
Phase by phase
Progress: 9.9% physical completion at 31 Mar 2026 (HPCL) [1]
- FEED · unknown
- EPC award · done · 12 Oct 2026 [2]
- Engineering & procurement · in progress
- Construction · unknown
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 ogj.com 2 hydrocarbonengineering.com · checked 26 Nov 2026
CONFIRMEDMEDIUMIndia · Petrochemical
BPCL Bina Petchem & Refinery Expansion: LLDPE/HDPE swing unit (2 x 575 ktpa)
L&T Energy Hydrocarbon (LSTK EPCC)
- FEED: FEED: unknown
- Award: EPC award: done, 23 Dec 2025
- E&P: Engineering & procurement: in progress
- Build: Construction: in progress, 29 Oct 2026
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Construction
- Value
- 'major' order: Rs 5,000-10,000… [1]
- Workforce
- not published
- Finish
- May 2028 [2]
Client, scope, phases, sources
Client: Bharat Petroleum Corp. (BPCL)
Value: 'major' order: Rs 5,000-10,000 crore band (L&T classification) [1]
Finish: BPREP scheduled for completion in May 2028 (BPCL annual report, via OGJ) [2]
Scope
- LLDPE/HDPE swing unit, 2 x 575 ktpa [1]
- part of BPREP: refinery 7.8 to 11 Mtpa and a 1.2 Mtpa ethylene dual-feed cracker (project Rs 490 bn approved 2023) [2]
Phase by phase
- FEED · unknown
- EPC award · done · 23 Dec 2025 [1]
- Engineering & procurement · in progress
- Construction · in progress · 29 Oct 2026 · L&T advertises piping fabrication and erection roles at Bina [3]
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 larsentoubro.com 2 ogj.com 3 larsentoubrocareers.peoplestrong.com · checked 26 Nov 2026
CONFIRMEDIndia · Petrochemical
BPCL Bina expansion: polypropylene (550 ktpa) and Butene-1 (50 ktpa) units
Technip Energies (EPCC)
- FEED: FEED: unknown
- Award: EPC award: done, 7 Jan 2026
- E&P: Engineering & procurement: in progress
- Build: Construction: unknown
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Engineering & procurement
- Value
- not disclosed (described as a… [1]
- Workforce
- not published
- Finish
- May 2028 [2]
No open adverts linked today
Client, scope, phases, sources
Client: Bharat Petroleum Corp. (BPCL)
Value: not disclosed (described as a 'large' contract) [1]
Finish: BPREP scheduled for completion in May 2028 (BPCL annual report, via OGJ) [2]
Scope
- 550,000 t/y polypropylene and 50,000 t/y Butene-1 [1]
- part of BPREP (Bina refinery to 11 Mtpa, 1.2 Mtpa ethylene cracker) [2]
Phase by phase
- FEED · unknown
- EPC award · done · 7 Jan 2026 [1]
- Engineering & procurement · in progress
- Construction · unknown
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 hydrocarbonengineering.com 2 ogj.com · checked 26 Nov 2026
CONFIRMEDIndia · Refinery
BPCL Mumbai refinery: 3 Mtpa petro resid FCC (PRFCC), India's first
Technip Energies (EPsCm: engineering, procurement, construction management)
- FEED: FEED: unknown
- Award: EPC award: done, 7 Jan 2026
- E&P: Engineering & procurement: in progress
- Build: Construction: unknown
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Engineering & procurement
- Value
- not disclosed (described as a… [1]
- Workforce
- not published
- Finish
- not published
No open adverts linked today
Client, scope, phases, sources
Client: Bharat Petroleum Corp. (BPCL)
Value: not disclosed (described as a 'large' contract) [1]
Scope
- 3 Mtpa petro resid fluidised catalytic cracker (PRFCC), Mumbai refinery [1]
Phase by phase
- FEED · unknown
- EPC award · done · 7 Jan 2026 [1]
- Engineering & procurement · in progress
- Construction · unknown
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 hydrocarbonengineering.com · checked 26 Nov 2026
CONFIRMEDIndia · Terminal & storage
Petronet LNG Dahej: 170,000 m3 LNG/ethane tank, 140,000 m3 propane tank, handling for the PDH-PP plant
L&T Energy Hydrocarbon (LSTK EPCC)
- FEED: FEED: unknown
- Award: EPC award: done, 16 Jan 2026
- E&P: Engineering & procurement: in progress
- Build: Construction: unknown
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Engineering & procurement
- Value
- 'large' order: Rs 2,500-5,000… [1]
- Workforce
- not published
- Finish
- 'within the agreed timelines'… [1]
No open adverts linked today
Client, scope, phases, sources
Client: Petronet LNG
Value: 'large' order: Rs 2,500-5,000 crore band (L&T classification) [1]
Finish: 'within the agreed timelines' (L&T); no date published [1]
Scope
- 170,000 m3 LNG/ethane double-wall tank [1]
- 140,000 m3 propane double-wall tank, for the Dahej PDH-PP complex [1]
Phase by phase
- FEED · unknown
- EPC award · done · 16 Jan 2026 [1]
- Engineering & procurement · in progress
- Construction · unknown
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 larsentoubro.com · checked 26 Nov 2026
CONFIRMEDMEDIUMOFFSHOREIndia · Offshore platform
ONGC west coast: Pipeline Replacement Project PRP-X and four wellhead platforms
L&T Energy Hydrocarbon Offshore (EPCIC)
- FEED: FEED: unknown
- Award: EPC award: done, 10 Aug 2026
- E&P: Engineering & procurement: in progress
- Build: Construction: unknown
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Engineering & procurement
- Value
- between Rs 50bn (US$525.2m) and… [1]
- Workforce
- not published
- Finish
- not published
No open adverts linked today
Client, scope, phases, sources
Client: ONGC
Value: between Rs 50bn (US$525.2m) and Rs 100bn (US$1.05bn), L&T band [1]
Scope
- Pipeline Replacement Project PRP-X: several subsea pipeline segments [1]
- four wellhead platforms, EPCIC [1]
Phase by phase
- FEED · unknown
- EPC award · done · 10 Aug 2026 [1]
- Engineering & procurement · in progress
- Construction · unknown
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 offshore-technology.com · checked 26 Nov 2026
CONFIRMEDOFFSHOREIndia · Offshore platform
ONGC Additional Development of Ratna-I (ADR-I) and NLM-14: 3 wellhead + 1 riser platform, subsea pipelines
L&T Energy Hydrocarbon Offshore (EPCIC)
- FEED: FEED: unknown
- Award: EPC award: done, 9 Sep 2026
- E&P: Engineering & procurement: in progress
- Build: Construction: unknown
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Engineering & procurement
- Value
- 'large' order: Rs 2,500-5,000… [1]
- Workforce
- not published
- Finish
- not published
No open adverts linked today
Client, scope, phases, sources
Client: ONGC
Value: 'large' order: Rs 2,500-5,000 crore band (L&T classification) [1]
Scope
- 3 wellhead platforms + 1 riser platform, subsea pipelines (Ratna-I and NLM-14) [1]
Phase by phase
- FEED · unknown
- EPC award · done · 9 Sep 2026 [1]
- Engineering & procurement · in progress
- Construction · unknown
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 nsearchives.nseindia.com · checked 26 Nov 2026
CONFIRMEDLARGEIndia · Refinery
IOCL Panipat refinery expansion, 15 to 25 Mtpa (+ polybutadiene rubber plant)
L&T Energy Hydrocarbon (EPCC residue hydrocracker (2.5 Mtpa, Axens) and diesel hydrotreater (5 Mtpa) packages) · Toyo Engineering India (vacuum gas oil hydrotreater unit (EPCC)) · not named in the sources we read
- FEED: FEED: done
- Award: EPC award: done
- E&P: Engineering & procurement: unknown
- Build: Construction: in progress, 30 Jun 2026
- Comm.: Pre-commissioning & commissioning: not started, Dec 2026
- Start: Start-up: not started
Now:
Construction ·
94% complete (30 Jun 2026)
[1]94%
- Value
- INR 382.3bn [1]
- Workforce
- not published
- Finish
- Dec 2026 [1]
No open adverts linked today
Client, scope, phases, sources
Client: Indian Oil Corp. (IOCL)
Value: Rs 382.31 billion invested at 30 Jun 2026 (initially budgeted Rs 329.46 bn) [1]
Finish: commissioning scheduled for December 2026 (IOC filing, 31 Jul 2026) [1]
Scope
- 15 to 25 Mtpa crude capacity (+ polybutadiene rubber plant) [1]
Phase by phase
Progress: 94% physical completion at 30 Jun 2026 (IOC) [1]
- FEED · done
- EPC award · done
- Engineering & procurement · unknown
- Construction · in progress · 30 Jun 2026 [1]
- Pre-commissioning & commissioning · not started · Dec 2026 · planned date [1]
- Start-up · not started
Sources: 1 ogj.com 2 larsentoubro.com 3 toyo-eng.com · checked 26 Nov 2026
CONFIRMEDMEDIUMIndia · Refinery
IOCL Koyali (Gujarat) refinery expansion, 13.7 to 18 Mtpa (+ PP and lube base stock)
Toyo Engineering India (EPCC 2.5 Mtpa vacuum distillation unit, turnkey (Aug 2022)) · Nuberg Engineering (sulphur recovery unit, Rs 650 crore (2022)) · not named in the sources we read
- FEED: FEED: done
- Award: EPC award: done
- E&P: Engineering & procurement: unknown
- Build: Construction: in progress, 30 Jun 2026
- Comm.: Pre-commissioning & commissioning: not started, Nov 2026
- Start: Start-up: not started
Now:
Construction ·
89.2% complete (30 Jun 2026)
[1]89.2%
- Value
- INR 189.4bn [1]
- Workforce
- not published
- Finish
- Nov 2026 [1]
No open adverts linked today
Client, scope, phases, sources
Client: Indian Oil Corp. (IOCL)
Value: about Rs 189.36 billion overall cost (originally Rs 178.25 bn) [1]
Finish: commissioning planned for November 2026 (IOC filing, 31 Jul 2026) [1]
Scope
- 13.7 to 18 Mtpa crude capacity (+ polypropylene and lube base stock) [1]
Phase by phase
Progress: 89.2% physical completion at 30 Jun 2026 (IOC) [1]
- FEED · done
- EPC award · done
- Engineering & procurement · unknown
- Construction · in progress · 30 Jun 2026 [1]
- Pre-commissioning & commissioning · not started · Nov 2026 · planned date [1]
- Start-up · not started
Sources: 1 ogj.com 2 toyo-eng.com 3 bsppd.business-standard.com · checked 26 Nov 2026
CONFIRMEDMEDIUMIndia · Refinery
IOCL Barauni refinery expansion, 6 to 9 Mtpa
L&T Energy Hydrocarbon (EPCC-1: new 9 Mtpa atmospheric-vacuum unit, LSTK (Apr 2020)) · Technip Energies (EPCC once-through hydrocracker 1 Mtpa and fuel gas treatment (Apr 2021)) · Tecnimont (MAIRE) (EPCC 200,000 t/y polypropylene unit (with Tecnimont Private)) · McDermott (EPCC diesel hydrotreating unit and additional units (2021)) · Toyo Engineering India (PMC phase II (consultant, not EPC)) · not named in the sources we read
- FEED: FEED: done
- Award: EPC award: done
- E&P: Engineering & procurement: unknown
- Build: Construction: in progress, 30 Jun 2026
- Comm.: Pre-commissioning & commissioning: not started, Dec 2026
- Start: Start-up: not started
Now:
Construction ·
91.6% complete (30 Jun 2026)
[1]91.6%
- Value
- INR 181.1bn [1]
- Workforce
- not published
- Finish
- Dec 2026 [1]
No open adverts linked today
Client, scope, phases, sources
Client: Indian Oil Corp. (IOCL)
Value: Rs 181.13 billion invested (previously budgeted Rs 148 bn) [1]
Finish: commissioning targeted for December 2026 (IOC filing, 31 Jul 2026) [1]
Scope
- 6 to 9 Mtpa crude capacity [1]
Phase by phase
Progress: 91.6% physical completion at 30 Jun 2026 (IOC) [1]
- FEED · done
- EPC award · done
- Engineering & procurement · unknown
- Construction · in progress · 30 Jun 2026 [1]
- Pre-commissioning & commissioning · not started · Dec 2026 · planned date [1]
- Start-up · not started
Sources: 1 ogj.com 2 ogj.com 3 hydrocarbonprocessing.com 4 ogj.com · checked 26 Nov 2026
REPORTEDLARGEOFFSHOREIndia · Subsea
ONGC KG-DWN-98/2 deepwater block (Cluster 2), Krishna-Godavari basin
Afcons Infrastructure (current offshore piping work, named in its advert)
- FEED: FEED: done
- Award: EPC award: done
- E&P: Engineering & procurement: done
- Build: Construction: done
- Comm.: Pre-commissioning & commissioning: done
- Start: Start-up: done, Jan 2024
Last step done: Start-up
- Value
- USD 5bn [1]
- Workforce
- not published
- Finish
- producing since January 2024;… [1]
Client, scope, phases, sources
Client: ONGC
Value: USD 5 billion deep-water project (Outlook Business headline, Jan 2024) [1]
Finish: producing since January 2024; ramp-up [1]
Scope
- Cluster 2 deep-water development, Krishna-Godavari basin [1]
Phase by phase
- FEED · done
- EPC award · done
- Engineering & procurement · done
- Construction · done
- Pre-commissioning & commissioning · done
- Start-up · done · Jan 2024 · first oil January 2024; ramp-up and further work ongoing [1]
Sources: 1 outlookbusiness.com · checked 26 Nov 2026
CONFIRMEDOFFSHOREUAE · Gas compression
ADNOC Offshore Umm Shaif gas cap and pressure boosting, package 1 (30,000 t gas compression)
L&T Energy Hydrocarbon Offshore (consortium leader) · Lamprell (consortium partner)
- FEED: FEED: done
- Award: EPC award: done, 4 Aug 2026
- E&P: Engineering & procurement: in progress
- Build: Construction: unknown
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Engineering & procurement
- Value
- 'ultra-mega' order (above Rs 150… [1]
- Workforce
- not published
- Finish
- 2030 [1]
No open adverts linked today
Client, scope, phases, sources
Client: ADNOC Offshore
Value: 'ultra-mega' order (above Rs 150 bn, L&T band); the three EPC packages total USD 5.1bn; FID USD 6.2bn [1]
Finish: production expected by 2030 (MEED) [1]
Scope
- 30,000-tonne gas compression system (package 1) [1]
- 600 MMcfd of gas [1]
Phase by phase
- FEED · done
- EPC award · done · 4 Aug 2026 · FID July 2026 [1]
- Engineering & procurement · in progress
- Construction · unknown
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 guest.meed.com · checked 26 Nov 2026
CONFIRMEDOFFSHOREUAE · Gas compression
ADNOC Umm Shaif integrated gas cap and surface pressure boosting, package 4 (jacket + topside)
McDermott (EPCI) · Qingdao McDermott Wuchuan (QMW) (consortium, fabrication yard)
- FEED: FEED: done
- Award: EPC award: done, 24 Aug 2026
- E&P: Engineering & procurement: in progress
- Build: Construction: unknown
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Engineering & procurement
- Value
- more than USD 1 billion ('mega'… [1]
- Workforce
- not published
- Finish
- 2030 [2]
No open adverts linked today
Client, scope, phases, sources
Client: ADNOC
Value: more than USD 1 billion ('mega' award, McDermott; exact value not disclosed) [1]
Finish: production from the Umm Shaif gas cap development expected by 2030 (MEED) [2]
Scope
- new surface pressure boosting facility: jacket, topside, brownfield modifications [1]
- fabrication at QMW yard, Qingdao (China) [1]
Phase by phase
- FEED · done
- EPC award · done · 24 Aug 2026 [1]
- Engineering & procurement · in progress
- Construction · unknown
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 worldoil.com 2 guest.meed.com · checked 26 Nov 2026
REPORTEDMEDIUMOFFSHOREUAE · Offshore platform
ADNOC SARB deep gas development (Ghasha concession): wellhead tower, 4 wells, tie-in to Das Island
McDermott (EPC)
- FEED: FEED: done
- Award: EPC award: done, Jan 2026
- E&P: Engineering & procurement: in progress
- Build: Construction: in progress, 16 Oct 2026
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Construction
- Value
- USD 500m [1]
- Workforce
- not published
- Finish
- production 'later this decade'… [2]
No open adverts linked today
Client, scope, phases, sources
Client: ADNOC
Value: estimated USD 500 million (MEED) [1]
Finish: production 'later this decade' (World Oil, Jan 2026) [2]
Scope
- 200 MMscfd from four wells, about 120 km offshore [2]
- wellhead tower tied in to Das Island [1]
Phase by phase
- FEED · done
- EPC award · done · Jan 2026 · FID 7 Jan 2026 [1]
- Engineering & procurement · in progress
- Construction · in progress · 16 Oct 2026 · steel cut [1]
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 meed.com 2 worldoil.com · checked 26 Nov 2026
CONFIRMEDLARGEUAE · Gas processing
ADNOC Gas Rich Gas Development phase 2: new gas processing train at Habshan
Wison Engineering (EPC)
- FEED: FEED: done
- Award: EPC award: done, 10 Aug 2026
- E&P: Engineering & procurement: in progress
- Build: Construction: in progress, 11 Nov 2026
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Construction
- Value
- USD 3.9bn [1]
- Workforce
- not published
- Finish
- not published
No open adverts linked today
Client, scope, phases, sources
Client: ADNOC Gas
Value: USD 3.9 billion EPC contract [1]
Scope
- new gas processing train at the Habshan complex [1]
Phase by phase
- FEED · done
- EPC award · done · 10 Aug 2026 [1]
- Engineering & procurement · in progress
- Construction · in progress · 11 Nov 2026 · groundbreaking ceremony (ADNOC Gas, via OGJ 16 Nov 2026) [2]
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 worldoil.com 2 ogj.com · checked 26 Nov 2026
CONFIRMEDLARGEUAE · Gas processing
ADNOC Gas Rich Gas Development phase 3: new NGL fractionation train at Ruwais
Tecnimont (MAIRE) (EPC)
- FEED: FEED: done
- Award: EPC award: done, 10 Aug 2026
- E&P: Engineering & procurement: in progress
- Build: Construction: in progress, 10 Nov 2026
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Construction
- Value
- USD 4.3bn [1]
- Workforce
- not published
- Finish
- not published
No open adverts linked today
Client, scope, phases, sources
Client: ADNOC Gas
Value: USD 4.3 billion EPC contract [1]
Scope
- new NGL fractionation train at Ruwais [1]
Phase by phase
- FEED · done
- EPC award · done · 10 Aug 2026 [1]
- Engineering & procurement · in progress
- Construction · in progress · 10 Nov 2026 · groundbreaking ceremony (ADNOC Gas, via OGJ 16 Nov 2026) [2]
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 worldoil.com 2 ogj.com · checked 26 Nov 2026
REPORTEDMEDIUMUAE · Onshore oil field
ADNOC Onshore Bab and North East Bab one tie-in project (well tie-ins, mini-pad, well bays)
Jereh Group (EPC framework, 60 months (Jereh filing, via MEED)) · Robt Stone Middle East (portion of the work)
- FEED: FEED: unknown
- Award: EPC award: done, Nov 2026
- E&P: Engineering & procurement: not started
- Build: Construction: not started
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Last step done: EPC award
- Value
- USD 599m [2]
- Workforce
- not published
- Finish
- not published
No open adverts linked today
Client, scope, phases, sources
Client: ADNOC Onshore
Value: USD 599 million (Jereh filing, via MEED, 13 Nov 2026) [2]
Scope
- well tie-ins, mini-pad and well bays, Bab and North East Bab fields [1]
Phase by phase
- FEED · unknown
- EPC award · done · Nov 2026 · framework model, 60 months; Robt Stone Middle East with a portion [2]
- Engineering & procurement · not started
- Construction · not started
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 guest.meed.com 2 guest.meed.com · checked 26 Nov 2026
ON THE RADARUAE · Onshore oil field
ADNOC Onshore Rumaitha and Shanayel field facilities (North East Bab), 45,000 b/d
Contractors: bidders not named
- FEED: FEED: unknown
- Award: EPC award: in progress, 6 Nov 2026
- E&P: Engineering & procurement: not started
- Build: Construction: not started
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: EPC award
- Value
- not disclosed [1]
- Workforce
- not published
- Finish
- not published
No open adverts linked today
Client, scope, phases, sources
Client: ADNOC Onshore
Value: not disclosed [1]
Scope
- field facilities for 45,000 b/d (Rumaitha and Shanayel, North East Bab) [1]
Phase by phase
- FEED · unknown
- EPC award · in progress · 6 Nov 2026 · commercial bid deadline extended, no new date (Attaqa, 6 Nov 2026) [2]
- Engineering & procurement · not started
- Construction · not started
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 guest.meed.com 2 attaqa.net · checked 26 Nov 2026
CONFIRMEDMEDIUMOFFSHORESaudi Arabia · Offshore platform
Saudi Aramco: three offshore EPC projects (names and locations not disclosed)
NMDC Energy (EPC)
- FEED: FEED: unknown
- Award: EPC award: done, 23 Oct 2026
- E&P: Engineering & procurement: not started
- Build: Construction: not started
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Last step done: EPC award
- Value
- AED 2.8bn [1]
- Workforce
- not published
- Finish
- 18 to 23 months from award [1]
No open adverts linked today
Client, scope, phases, sources
Client: Saudi Aramco
Value: AED 2.8 billion (about USD 763 million) [1]
Scope
- three offshore EPC projects; names and locations not disclosed [1]
Phase by phase
- FEED · unknown
- EPC award · done · 23 Oct 2026 · letter of award [1]
- Engineering & procurement · not started
- Construction · not started
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 thenationalnews.com · checked 29 Oct 2026
CONFIRMEDMEDIUMSaudi Arabia · Gas compression
Aramco Shedgum-Uthmaniyah gas compression: Uthmaniyah compression plant package
Saipem (SNSH JV, contract share EUR 900m) · Nasser Saeed Al-Hajri & Partners Contracting (SNSH JV)
- FEED: FEED: done
- Award: EPC award: done, Jun 2026
- E&P: Engineering & procurement: in progress, 12 Aug 2026
- Build: Construction: not started
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Engineering & procurement
- Value
- USD 1.2bn [1]
- Workforce
- not published
- Finish
- EPC works run for 42 months (from… [1]
No open adverts linked today
Client, scope, phases, sources
Client: Saudi Aramco
Value: about USD 1.24bn (sources, MEED); Saipem share EUR 900m (USD 1.04bn) [1]
Finish: EPC works run for 42 months (from the August 2026 kick-off) [1]
Scope
- new compression plant for the non-associated Uthmaniyah gas field (now about 1.2 bcfd of Khuff raw gas) [1]
- one of nine EPC packages of the Shedgum-Uthmaniyah programme [1]
Phase by phase
- FEED · done
- EPC award · done · Jun 2026 [1]
- Engineering & procurement · in progress · 12 Aug 2026 · EPC work kicked off [1]
- Construction · not started
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 guest.meed.com · checked 29 Oct 2026
CONFIRMEDSaudi Arabia · Pipeline
Ghazlan 1: sales gas delivery system
GAS Arabian Services (EPC)
- FEED: FEED: unknown
- Award: EPC award: done, 9 Oct 2026
- E&P: Engineering & procurement: in progress
- Build: Construction: not started
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Engineering & procurement
- Value
- SAR 288m [1]
- Workforce
- not published
- Finish
- not published
No open adverts linked today
Client, scope, phases, sources
Client: Saudi Power Procurement Company
Value: above SAR 288 million (about USD 76.8m) [1]
Scope
- sales gas delivery system to the Ghazlan 1 power plant [1]
Phase by phase
- FEED · unknown
- EPC award · done · 9 Oct 2026 [1]
- Engineering & procurement · in progress
- Construction · not started
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 tradearabia.com · checked 26 Nov 2026
CONFIRMEDLARGESaudi Arabia · Fertiliser
SABIC Agri-Nutrients SAN-7, Jubail: gas-based ammonia (3,500 t/d) and urea (7,700 t/d)
Samsung E&A (sole EPC)
- FEED: FEED: unknown
- Award: EPC award: done, 9 Sep 2026
- E&P: Engineering & procurement: in progress
- Build: Construction: not started
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Engineering & procurement
- Value
- KRW 4700bn [1]
- Workforce
- EPC Radar estimate est. 8,500-38,900 at peak how?
- Finish
- 2030 [1]
No open adverts linked today
Client, scope, phases, sources
Client: SABIC Agri-Nutrients
Value: KRW 4.7 trillion (about USD 3.5 billion) [1]
Finish: completion scheduled for 2030 [1]
Workforce estimate (low confidence): EPC Radar estimate from 2 published refinery, petrochemical and fertiliser plants projects in this tracker, 2.4-11.1 workers per USD million of declared value (id-rdmp-balikpapan, ar-fertil-pampa), applied to contract value: about USD 3,515 m
Scope
- 3,500 t/d ammonia [1]
- 7,700 t/d urea [1]
Phase by phase
- FEED · unknown
- EPC award · done · 9 Sep 2026 [1]
- Engineering & procurement · in progress
- Construction · not started
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 hydrocarbonprocessing.com · checked 26 Nov 2026
ON THE RADARSaudi Arabia · Gas processing
Aramco Alhada gas processing plant expansion (3 trains, sulphur recovery, utilities)
Contractors: not yet selected (3 EPC packages)
- FEED: FEED: unknown
- Award: EPC award: not started, 30 Sep 2026
- E&P: Engineering & procurement: not started
- Build: Construction: not started
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Before the EPC award
- Value
- not disclosed [1]
- Workforce
- not published
- Finish
- not published
No open adverts linked today
Client, scope, phases, sources
Client: Saudi Aramco
Value: not disclosed [1]
Scope
- 3 gas processing trains, sulphur recovery, utilities [1]
Phase by phase
- FEED · unknown
- EPC award · not started · 30 Sep 2026 · expressions of interest received; main tender next [1]
- Engineering & procurement · not started
- Construction · not started
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 guest.meed.com · checked 26 Nov 2026
CONFIRMEDLARGENigeria · LNG plant
Nigeria LNG Train 7, Bonny Island (22 to 30 Mtpa)
Saipem (SCD JV) · Chiyoda (SCD JV) · Daewoo E&C (SCD JV)
- FEED: FEED: done
- Award: EPC award: done, 2020
- E&P: Engineering & procurement: unknown
- Build: Construction: in progress, 3 Aug 2026
- Comm.: Pre-commissioning & commissioning: in progress, May 2026
- Start: Start-up: not started
Now:
Pre-commissioning & commissioning ·
93% complete (Aug 2026)
[2]93%
- Value
- USD 5bn [1]
- Workforce
- over 13,000 Nigerians employed on Train 7 at peak construction (NLNG project director, ThisDay, May 2026); NLNG's CEO cited 16,000 direct jobs on site [1]
- Finish
- 2027 [3]
Client, scope, phases, sources
Client: Nigeria LNG (NNPC, Shell, TotalEnergies, Eni)
Value: USD 5 billion project (ThisDay, May 2026) [1]
Finish: plans to commission the new facility in 2027 (NLNG CEO) [3]
Scope
- NLNG capacity from 22 to 30 Mtpa (+35%) [2]
- Bonny Island, Rivers State [2]
Phase by phase
Progress: 93 per cent completion (NLNG Facts and Figures 2026, 3 Aug 2026) [2]
- FEED · done
- EPC award · done · 2020 [2]
- Engineering & procurement · unknown
- Construction · in progress · 3 Aug 2026 · 93% overall [2]
- Pre-commissioning & commissioning · in progress · May 2026 · systems completion and pre-commissioning [1]
- Start-up · not started
Sources: 1 thisdaylive.com 2 shippingposition.com.ng 3 leadership.ng · checked 26 Nov 2026
CONFIRMEDMEDIUMOFFSHORENigeria · Subsea
Shell Bonga North deepwater tie-back to the Bonga FPSO
Saipem (leader, share close to USD 900m) · KOA Oil & Gas · AVEON Offshore
- FEED: FEED: done
- Award: EPC award: done, 19 Dec 2024
- E&P: Engineering & procurement: in progress
- Build: Construction: in progress
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Construction
- Value
- USD 1bn [1]
- Workforce
- not published
- Finish
- 2030 [2]
No open adverts linked today
Client, scope, phases, sources
Client: Shell Nigeria Exploration and Production Co. (SNEPCo)
Value: about USD 1 billion; Saipem share close to USD 900 million [1]
Finish: first oil 'by the end of the decade' (Shell FID, Dec 2024) [2]
Scope
- 16 wells (8 production, 8 water injection); peak 110,000 b/d of oil; over 300 MMboe [2]
- subsea tie-back 130 km offshore to the Bonga FPSO [1]
Phase by phase
- FEED · done
- EPC award · done · 19 Dec 2024 · FID 16 Dec 2024 [1]
- Engineering & procurement · in progress
- Construction · in progress
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 offshore-mag.com 2 ogj.com · checked 29 Oct 2026
ON THE RADARLARGENigeria · Refinery
Dangote refinery expansion, Lekki: 650,000 to 1.4 million b/d
Engineers India (EIL) (PMC and EPCM, USD 350m) · construction contractors not yet named
- FEED: FEED: unknown
- Award: EPC award: in progress, 20 Jan 2026
- E&P: Engineering & procurement: unknown
- Build: Construction: unknown
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: EPC award
- Value
- USD 14.3bn [1]
- Workforce
- about 95,000 skilled workers expected on site at the peak of construction (Aliko Dangote, 24 Apr 2026) [3]
- Finish
- 2029 [1]
No open adverts linked today
Client, scope, phases, sources
Client: Dangote Industries
Value: USD 14.3 billion expansion plan (IPO documents, Sep 2026); EIL PMC/EPCM contract USD 350m [1]
Finish: due to be complete by 2029 (IPO prospectus, Reuters via Hydrocarbon Processing) [1]
Scope
- refinery from 700,000 to 1.4 million b/d [1]
Phase by phase
- FEED · unknown
- EPC award · in progress · 20 Jan 2026 · PMC/EPCM appointed; construction contractors not named [2]
- Engineering & procurement · unknown
- Construction · unknown
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 hydrocarbonprocessing.com 2 industrialinfo.com 3 financialedge.com.ng · checked 26 Nov 2026
REPORTEDMEDIUMOFFSHORENigeria · Offshore platform
Ima gas project (OMLs 112/117): offshore platform + 22 km pipeline to NLNG
Aveon Offshore (EPCC, CSP package, with 2H Offshore) · 2H Offshore (Acteon) (offshore engineering and project management, CSP package)
- FEED: FEED: done
- Award: EPC award: in progress, 31 Oct 2026
- E&P: Engineering & procurement: in progress
- Build: Construction: not started
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Engineering & procurement
- Value
- USD 800m [1]
- Workforce
- not published
- Finish
- 2028 [1]
No open adverts linked today
Client, scope, phases, sources
Client: TotalEnergies (operator, 40%) and AMNI International (60%)
Value: around USD 800 million (Nigerian government); TotalEnergies' share more than USD 600 million [1]
Finish: first gas targeted for 2028 [1]
Scope
- about 350 MMscfd of gas at plateau [1]
- offshore platform + 22 km pipeline to Nigeria LNG [1]
Phase by phase
- FEED · done
- EPC award · in progress · 31 Oct 2026 · CSP package to Aveon Offshore and 2H Offshore; other packages not published [2]
- Engineering & procurement · in progress
- Construction · not started
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 chemanalyst.com 2 energyfocusreport.com · checked 26 Nov 2026
CONFIRMEDOFFSHOREMozambique · Floating LNG (FLNG)
Coral Norte FLNG (3.6 Mtpa), Area 4 offshore
Technip Energies (EPCIC) · JGC (EPCIC partner) · Samsung Heavy Industries (EPCIC partner, hull)
- FEED: FEED: done
- Award: EPC award: done, 11 Jun 2026
- E&P: Engineering & procurement: in progress
- Build: Construction: in progress
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Construction
- Value
- not disclosed [1]
- Workforce
- not published
- Finish
- 2028 [2]
No open adverts linked today
Client, scope, phases, sources
Client: Mozambique Rovuma Venture (Eni with CNPC, ENH, XRG, KOGAS)
Value: not disclosed [1]
Finish: on track to start production by 2028 (Eni, Oct 2026) [2]
Scope
- FLNG of about 3.6 Mtpa, doubling the Coral hub to 7 Mtpa [1]
- up to six development wells drilled from November 2026 [2]
Phase by phase
- FEED · done
- EPC award · done · 11 Jun 2026 [1]
- Engineering & procurement · in progress
- Construction · in progress · hull built in Korea [1]
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 hydrocarbonprocessing.com 2 oedigital.com · checked 26 Nov 2026
ON THE RADARMozambique · LNG plant
Rovuma LNG phase 1, onshore: 12 modular trains, 18.6 Mtpa (Afungi)
Saipem (SMDC JV) · McDermott (SMDC JV) · Daewoo E&C (SMDC JV) · CPECC (SMDC JV)
- FEED: FEED: unknown
- Award: EPC award: in progress, 10 Aug 2026
- E&P: Engineering & procurement: in progress
- Build: Construction: not started
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Engineering & procurement
- Value
- not disclosed [1]
- Workforce
- not published for the plant alone; ExxonMobil: about 7,500 Mozambicans in the Rovuma LNG construction phase (see upstream entry) [2]
- Finish
- 2031 [1]
No open adverts linked today
Client, scope, phases, sources
Client: Area 4 partners (ExxonMobil for Mozambique Rovuma Venture)
Value: not disclosed [1]
Finish: start-up anticipated in 2031 (ExxonMobil) [1]
Scope
- 12 modular liquefaction modules, 18.6 Mtpa [1]
Phase by phase
- FEED · unknown
- EPC award · in progress · 10 Aug 2026 · letter of intent for limited engineering and procurement; FID expected 2026 [1]
- Engineering & procurement · in progress
- Construction · not started
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 corporate.exxonmobil.com 2 corporate.exxonmobil.com · checked 26 Nov 2026
ON THE RADAROFFSHOREMozambique · Subsea
Rovuma LNG upstream: 18 wells, subsea pipelines and manifolds; Pemba shorebase
Saipem (upstream EPCI consortium, LOI) · Jan De Nul (upstream EPCI consortium, LOI) · CFML Logistic (Pemba shorebase land and infrastructure) · Alistair Group Mozambique (shorebase logistics)
- FEED: FEED: unknown
- Award: EPC award: in progress, 10 Sep 2026
- E&P: Engineering & procurement: in progress
- Build: Construction: not started
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Engineering & procurement
- Value
- not disclosed (ExxonMobil cites… [1]
- Workforce
- approximately 7,500 Mozambicans during the construction phase (ExxonMobil, 10 Sep 2026) [1]
- Finish
- 2031 [2]
No open adverts linked today
Client, scope, phases, sources
Client: Area 4 partners (ExxonMobil for Mozambique Rovuma Venture)
Value: not disclosed (ExxonMobil cites about USD 6 billion of economic activity in Mozambique) [1]
Finish: Rovuma LNG start-up anticipated in 2031 (ExxonMobil) [2]
Scope
- 18 wells, subsea pipelines and manifolds [1]
- shorebase at the Pemba Bulk Terminal [1]
Phase by phase
- FEED · unknown
- EPC award · in progress · 10 Sep 2026 · letter of intent; final award after FID [1]
- Engineering & procurement · in progress
- Construction · not started
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 corporate.exxonmobil.com 2 corporate.exxonmobil.com · checked 29 Oct 2026
CONFIRMEDLARGEOFFSHOREIndonesia · FPSO
Kutei North Hub (Geng North, Gehem) FPSO, off East Kalimantan
PT Saipem Indonesia (EPCI JV) · PT Tripatra Engineers and Constructors (EPCI JV)
- FEED: FEED: done
- Award: EPC award: done, 8 Jul 2026
- E&P: Engineering & procurement: in progress
- Build: Construction: unknown
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Engineering & procurement
- Value
- USD 2bn [1]
- Workforce
- not published
- Finish
- EPCI duration about 48 months… [1]
Client, scope, phases, sources
Client: Eni North Ganal (Searah: Eni + Petronas)
Value: about USD 2 billion for Saipem's share [1]
Finish: EPCI duration about 48 months from July 2026 [1]
Scope
- FPSO for the Geng North and Gehem fields, off East Kalimantan [1]
Phase by phase
- FEED · done
- EPC award · done · 8 Jul 2026 [1]
- Engineering & procurement · in progress
- Construction · unknown
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 ogj.com · checked 29 Oct 2026
CONFIRMEDMEDIUMOFFSHOREIndonesia · Offshore platform
Tangguh Ubadari CCUS and compression (UCC), Papua Barat: 3 platforms, 90 km pipelines
Saipem (EPCI, share about USD 1bn) · PT Meindo Elang Indah (EPCI partner)
- FEED: FEED: done
- Award: EPC award: done, 27 Nov 2024
- E&P: Engineering & procurement: in progress
- Build: Construction: in progress
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Construction
- Value
- USD 1.2bn [1]
- Workforce
- not published
- Finish
- 2028 [2]
No open adverts linked today
Client, scope, phases, sources
Client: BP Berau
Value: approximately USD 1.2bn; Saipem share around USD 1bn (project USD 7 billion) [1]
Finish: Ubadari production should start in 2028 (bp, FID Nov 2024) [2]
Scope
- 2 wellhead production platforms + 1 CO2 reinjection platform; about 90 km of pipelines [1]
- about 15 Mt of CO2 sequestered in the first phase; Ubadari about 3 tcf [2]
Phase by phase
- FEED · done
- EPC award · done · 27 Nov 2024 [1]
- Engineering & procurement · in progress
- Construction · in progress · platforms fabricated at Saipem Karimun yard [1]
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 offshore-technology.com 2 offshore-mag.com · checked 29 Oct 2026
ON THE RADAROFFSHOREIndonesia · LNG plant
Abadi LNG, Masela block: onshore LNG, FPSO, SURF, export pipeline
Saipem (FEED) · Tripatra (FEED) · McDermott (FEED) · Technip (FEED) · JGC (FEED) · KBR Indonesia (FEED) · Adhi Karya (FEED) · Samsung E&A (FEED) · Worley (FEED) · dual FEED: the winning group gets the EPC
- FEED: FEED: done, 27 Oct 2026
- Award: EPC award: not started
- E&P: Engineering & procurement: not started
- Build: Construction: unknown, Jul 2026
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Last step done: FEED
- Value
- not disclosed [1]
- Workforce
- estimated around 12,000 direct workers during construction (Antara, Jul 2026) [2]
- Finish
- first gas 2029-2030 (Dunia… [1]
No open adverts linked today
Client, scope, phases, sources
Client: INPEX Masela
Value: not disclosed [1]
Finish: first gas 2029-2030 (Dunia Energi, Oct 2026) [1]
Scope
- onshore LNG of 9.5 Mtpa, plus FPSO, SURF and export pipeline [2]
Phase by phase
- FEED · done · 27 Oct 2026 [1]
- EPC award · not started · FID by end of January 2027 [1]
- Engineering & procurement · not started
- Construction · unknown · Jul 2026 · groundbreaking held July 2026; main EPC not awarded [2]
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 dunia-energi.com 2 en.antaranews.com · checked 26 Nov 2026
CONFIRMEDLARGEIndonesia · Refinery
Pertamina RDMP Balikpapan refinery upgrade, 260,000 to 360,000 b/d
Hyundai Engineering (EPC, 2019 contract)
- FEED: FEED: done
- Award: EPC award: done, 17 Sep 2019
- E&P: Engineering & procurement: done
- Build: Construction: done
- Comm.: Pre-commissioning & commissioning: done
- Start: Start-up: in progress, 12 Jan 2026
Now: Start-up
- Value
- USD 2.2bn [1]
- Workforce
- the number of workers involved reached 24 thousand people at peak construction (Pertamina, Nov 2025) [2]
- Finish
- Jan 2026 [1]
No open adverts linked today
Client, scope, phases, sources
Client: Pertamina (PT Kilang Pertamina Balikpapan)
Value: EPC USD 2.17bn (2019); project Rp 123 trillion [1]
Finish: inaugurated 12 January 2026; ramp-up under way [1]
Scope
- refinery from 260,000 to 360,000 b/d [1]
Phase by phase
- FEED · done
- EPC award · done · 17 Sep 2019 [3]
- Engineering & procurement · done
- Construction · done
- Pre-commissioning & commissioning · done
- Start-up · in progress · 12 Jan 2026 · inaugurated 12 Jan 2026; ramp-up [1]
Sources: 1 hydrocarbonengineering.com 2 kpb.pertamina.com 3 ogj.com · checked 26 Nov 2026
CONFIRMEDLARGEChina · Petrochemical
Sinopec Maoming refinery transformation and ethylene upgrade (ethylene 1.0 to 1.64 Mtpa)
Sinopec Engineering (SEI) (design lead; 3 Mtpa catalytic cracker and 1 Mtpa ethylene unit) · Sinopec Nanjing Engineering · Sinopec Shanghai Engineering · Sinopec Guangzhou Engineering · Sinopec Ningbo Engineering · Maoming Ruipai Petrochemical Engineering
- FEED: FEED: done
- Award: EPC award: done
- E&P: Engineering & procurement: in progress
- Build: Construction: in progress, Jun 2026
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now:
Construction ·
63% complete (Jun 2026)
[1]63%
- Value
- CNY 30bn [1]
- Workforce
- not published
- Finish
- not published
No open adverts linked today
Client, scope, phases, sources
Client: Sinopec Maoming
Value: over RMB 30 billion (project) [1]
Scope
- ethylene from 1.0 to 1.64 Mtpa [1]
- 3 Mtpa catalytic cracker and 1 Mtpa ethylene unit [1]
Phase by phase
Progress: 63% overall; 103 of 107 main units started, 9 mechanically complete (Jun 2026) [1]
- FEED · done
- EPC award · done
- Engineering & procurement · in progress
- Construction · in progress · Jun 2026 · all heavy lifts done [1]
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 t.cj.sina.com.cn · checked 26 Nov 2026
CONFIRMEDLARGEChina · Refinery
Huajin Aramco Petrochemical (HAPCO), Panjin: 15 Mtpa refinery + 1.65 Mtpa ethylene; coal-to-hydrogen unit
China Chemical Engineering Second Construction (coal-to-hydrogen unit)
- FEED: FEED: done
- Award: EPC award: done
- E&P: Engineering & procurement: done
- Build: Construction: done, 28 Apr 2026
- Comm.: Pre-commissioning & commissioning: in progress, 15 Oct 2026
- Start: Start-up: not started
Now: Pre-commissioning & commissioning
- Value
- CNY 83.7bn [1]
- Workforce
- not published
- Finish
- start of operations not dated;… [2]
No open adverts linked today
Client, scope, phases, sources
Client: Huajin Aramco Petrochemical (Norinco, Aramco, Panjin Xincheng)
Value: RMB 83.7 billion (project) [1]
Finish: start of operations not dated; complex in pre-production preparation (Oct 2026) [2]
Scope
- 300,000 b/d refinery and 1.65 Mtpa ethylene [2]
- coal-to-hydrogen unit handed over 28 Apr 2026 [1]
Phase by phase
- FEED · done
- EPC award · done
- Engineering & procurement · done
- Construction · done · 28 Apr 2026 · coal-to-hydrogen unit handover [1]
- Pre-commissioning & commissioning · in progress · 15 Oct 2026 · pre-production preparation; first Arabian crude arrived 9 Oct 2026 [2]
- Start-up · not started
Sources: 1 mtz.china.com 2 hydrocarbonengineering.com · checked 26 Nov 2026
CONFIRMEDChina · Refinery
Northern Huajin Union Petrochemical: 2.6 Mtpa product refining unit (Panjin)
China Chemical Engineering No.16 Construction (4th branch) (construction)
- FEED: FEED: done
- Award: EPC award: done
- E&P: Engineering & procurement: done
- Build: Construction: done, 2 Jul 2026
- Comm.: Pre-commissioning & commissioning: unknown
- Start: Start-up: not started
Last step done: Construction
- Value
- not disclosed [1]
- Workforce
- not published
- Finish
- not published
No open adverts linked today
Client, scope, phases, sources
Client: Northern Huajin Union Petrochemical
Value: not disclosed [1]
Scope
- 2.6 Mtpa product refining unit, Panjin [1]
Phase by phase
- FEED · done
- EPC award · done
- Engineering & procurement · done
- Construction · done · 2 Jul 2026 · intermediate handover [1]
- Pre-commissioning & commissioning · unknown
- Start-up · not started
Sources: 1 cn.chinadaily.com.cn · checked 29 Oct 2026
CONFIRMEDLARGEChina · Petrochemical
SABIC Fujian petrochemical complex, Gulei: 1.8 Mtpa ethylene, 16 derivative units
CTCI Beijing (EPC of the bimodal HDPE unit (Feb 2024)) · not named in the sources we read
- FEED: FEED: done
- Award: EPC award: done
- E&P: Engineering & procurement: done
- Build: Construction: done
- Comm.: Pre-commissioning & commissioning: in progress, 26 Oct 2026
- Start: Start-up: not started
Now:
Pre-commissioning & commissioning ·
87% complete (30 Sep 2025)
[1]87%
- Value
- USD 6.4bn [1]
- Workforce
- not published
- Finish
- 2026 [2]
No open adverts linked today
Client, scope, phases, sources
Client: SABIC with Fujian Energy Petrochemical
Value: about USD 6.4 billion (project) [1]
Finish: on track for full startup during Q4 2026 (SABIC CEO, 26 Oct 2026) [2]
Scope
- 1.8 Mtpa ethylene and 16 derivative units, Gulei [1]
Phase by phase
Progress: 87% at end of Q3 2025 (SABIC) [1]
- FEED · done
- EPC award · done
- Engineering & procurement · done
- Construction · done
- Pre-commissioning & commissioning · in progress · 26 Oct 2026 · three PE/PP plants completed trial runs [2]
- Start-up · not started
Sources: 1 argaam.com 2 arabnews.pk 3 nsenergybusiness.com · checked 26 Nov 2026
CONFIRMEDLARGEOFFSHOREQatar · Offshore platform
QatarEnergy Bul Hanine offshore redevelopment: 60+ facilities, 40 subsea pipelines and cables
COOEC (China Offshore Oil Engineering) (EPIC)
- FEED: FEED: done
- Award: EPC award: done, 2025
- E&P: Engineering & procurement: in progress
- Build: Construction: in progress, 15 Sep 2026
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Construction
- Value
- USD 4bn [1]
- Workforce
- not published
- Finish
- not published
No open adverts linked today
Client, scope, phases, sources
Client: QatarEnergy
Value: approximately USD 4 billion [1]
Scope
- more than 60 offshore facilities and 40 subsea pipelines and cables [1]
Phase by phase
- FEED · done
- EPC award · done · 2025 [1]
- Engineering & procurement · in progress
- Construction · in progress · 15 Sep 2026 · fabrication started in Qingdao [1]
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 constructionreviewonline.com · checked 29 Oct 2026
REPORTEDLARGEOFFSHOREKuwait / Saudi Arabia · Offshore platform
Dorra offshore gas field (Al-Khafji Joint Operations)
McDermott (offshore package 2A) · L&T Energy Hydrocarbon (package 2B with Saipem; package 1) · Saipem (package 2B with L&T) · Tecnicas Reunidas (onshore package 3, lowest bidder)
- FEED: FEED: done
- Award: EPC award: in progress, 12 Aug 2026
- E&P: Engineering & procurement: in progress
- Build: Construction: unknown
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Engineering & procurement
- Value
- package 2A about USD 1.5bn… [1]
- Workforce
- not published
- Finish
- not published
No open adverts linked today
Client, scope, phases, sources
Client: Al-Khafji Joint Operations (Aramco Gulf Operations + Kuwait Gulf Oil Co.)
Value: package 2A about USD 1.5bn (McDermott); package 2B about USD 3.7bn (L&T + Saipem), MEED [1]
Scope
- 1 bcfd of gas produced jointly by Saudi Arabia and Kuwait [1]
Phase by phase
- FEED · done
- EPC award · in progress · 12 Aug 2026 · offshore packages awarded; onshore pending [1]
- Engineering & procurement · in progress
- Construction · unknown
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 guest.meed.com · checked 29 Oct 2026
CONFIRMEDMEDIUMIraq · Gas processing
Ratawi gas processing complex (Gas Growth Integrated Project), 300 MMcf/d
CPECC (EPC, May 2025) · KBR (FEED)
- FEED: FEED: done
- Award: EPC award: done, May 2025
- E&P: Engineering & procurement: in progress
- Build: Construction: in progress, 21 May 2026
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Construction
- Value
- USD 1.6bn [1]
- Workforce
- not published
- Finish
- not published
No open adverts linked today
Client, scope, phases, sources
Client: TotalEnergies (operator) with Basra Oil Co. and QatarEnergy
Value: USD 1.61bn project [1]
Scope
- 300 MMcfd gas processing [1]
Phase by phase
- FEED · done
- EPC award · done · May 2025 [1]
- Engineering & procurement · in progress
- Construction · in progress · 21 May 2026 · foundations under construction [1]
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 guest.meed.com · checked 29 Oct 2026
CONFIRMEDOman · Onshore oil field
PDO Block 6 EPC framework: Raba hub, Wadi Umairi, Rabab Harweel tranche 2, Bout, Dulaima, Makarem, Amal South-East, Hawqa Hasirah
L&T Energy Hydrocarbon Onshore (one of four framework contractors) · other three not named
- FEED: FEED: unknown
- Award: EPC award: done, 31 Jul 2026
- E&P: Engineering & procurement: unknown
- Build: Construction: unknown
- Comm.: Pre-commissioning & commissioning: unknown
- Start: Start-up: unknown
Last step done: EPC award
- Value
- USD 6bn [1]
- Workforce
- not published
- Finish
- framework runs 6 years from July… [1]
No open adverts linked today
Client, scope, phases, sources
Client: Petroleum Development Oman (PDO)
Value: up to USD 6bn for the framework [1]
Finish: framework runs 6 years from July 2026 [1]
Scope
- 6-year EPC framework: Raba hub, Wadi Umairi, Rabab Harweel tranche 2, Bout, Dulaima, Makarem, Amal South-East, Hawqa Hasirah [1]
Phase by phase
- FEED · unknown
- EPC award · done · 31 Jul 2026 · framework agreed; projects tendered inside the pool [1]
- Engineering & procurement · unknown
- Construction · unknown
- Pre-commissioning & commissioning · unknown
- Start-up · unknown
Sources: 1 guest.meed.com · checked 29 Oct 2026
CONFIRMEDOFFSHOREIvory Coast · FPSO
Baleine Phase 3: new FPSO + subsea (150,000 b/d oil, 200 MMscf/d gas field total)
Saipem (SURF EPCI) · Wison New Energies (FPSO EPCIC, owner Altera)
- FEED: FEED: done
- Award: EPC award: done, 29 Jul 2026
- E&P: Engineering & procurement: in progress
- Build: Construction: unknown
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Engineering & procurement
- Value
- Saipem: about USD 930 million of… [1]
- Workforce
- not published
- Finish
- offshore construction expected to… [1]
No open adverts linked today
Client, scope, phases, sources
Client: Eni (with Petroci, Vitol)
Value: Saipem: about USD 930 million of new Eni contracts led by Baleine Phase 3; project value not disclosed [1]
Finish: offshore construction expected to take about three years (Jul 2026) [1]
Scope
- new FPSO + subsea production infrastructure, flowlines, risers, umbilicals [1]
- field total 150,000 b/d oil, 200 MMscfd gas [1]
Phase by phase
- FEED · done
- EPC award · done · 29 Jul 2026 · FID May 2026 [1]
- Engineering & procurement · in progress
- Construction · unknown
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 worldoil.com · checked 29 Oct 2026
REPORTEDLARGEOFFSHOREAngola · FPSO
TotalEnergies Kaminho (Cameia, Golfinho), Block 20/11: converted FPSO, 70,000 b/d
Saipem (FPSO, named in Saipem/GPS AG adverts)
- FEED: FEED: done
- Award: EPC award: done, 2024
- E&P: Engineering & procurement: in progress
- Build: Construction: in progress, 22 Apr 2025
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Construction
- Value
- USD 6bn [1]
- Workforce
- not published
- Finish
- 2028 [1]
No open adverts linked today
Client, scope, phases, sources
Client: TotalEnergies (40%), Petronas (40%), Sonangol (20%)
Value: USD 6 billion (project) [1]
Finish: production planned for 2028 [1]
Scope
- converted FPSO, 70,000 b/d (Cameia and Golfinho, Block 20/11) [1]
Phase by phase
- FEED · done
- EPC award · done · 2024 · FID May 2024 [2]
- Engineering & procurement · in progress
- Construction · in progress · 22 Apr 2025 · FPSO conversion in Nantong, China [1]
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 inspenet.com 2 offshore-technology.com · checked 29 Oct 2026
CONFIRMEDOFFSHORECyprus · Subsea
Eni Cronos gas development, Block 6 (to Zohr and Damietta LNG, Egypt), 500 MMscf/d
McDermott (subsea, USD 500-750m) · Petrojet (Egypt) (main contractor, 57 km 36-inch onshore pipeline Zohr facilities-Damietta LNG; also USD 11m subsea structures for McDermott) · other contractors at the Nicosia signing (Baker Hughes, Saipem, Technip, Oceaneering, Tenaris...) not broken down by package
- FEED: FEED: done
- Award: EPC award: done, 8 Sep 2026
- E&P: Engineering & procurement: in progress, 26 Oct 2026
- Build: Construction: not started
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Engineering & procurement
- Value
- not disclosed by Eni; McDermott… [1]
- Workforce
- not published
- Finish
- 2028 [2]
No open adverts linked today
Client, scope, phases, sources
Client: Eni Cyprus (50%) with TotalEnergies
Value: not disclosed by Eni; McDermott subsea award USD 500-750 million [1]
Finish: first gas H1 2028 (Eni) [2]
Scope
- 500 MMscfd, Block 6, gas processed via Zohr and Damietta LNG (Egypt) [2]
- Egypt onshore section: 57 km, 36-inch pipeline from Zohr facilities to Damietta liquefaction plant (Petrojet, 3 Nov 2026) [3]
Phase by phase
- FEED · done
- EPC award · done · 8 Sep 2026 · FID 28 Jul 2026 [1]
- Engineering & procurement · in progress · 26 Oct 2026 · execution phase launched [2]
- Construction · not started
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 worldoil.com 2 eni.com 3 egyptoil-gas.com · checked 12 Nov 2026
CONFIRMEDOFFSHORERomania · Offshore platform
Neptun Deep, Black Sea: Neptun Alpha platform, 10 wells, 160 km pipeline
Saipem (EPCIC: jacket, topsides, installation, pipeline)
- FEED: FEED: done
- Award: EPC award: done
- E&P: Engineering & procurement: done
- Build: Construction: in progress, 10 Oct 2026
- Comm.: Pre-commissioning & commissioning: unknown
- Start: Start-up: not started
Now: Construction
- Value
- not stated in the source [1]
- Workforce
- not published
- Finish
- 2027 [1]
Client, scope, phases, sources
Client: OMV Petrom (50%) and Romgaz (50%)
Value: not stated in the source [1]
Finish: first gas H1 2027 [1]
Scope
- Neptun Alpha platform, 10 wells, 160 km pipeline to shore [1]
Phase by phase
- FEED · done
- EPC award · done
- Engineering & procurement · done
- Construction · in progress · 10 Oct 2026 · platform installed Jul 2026; 7 of 10 wells done [1]
- Pre-commissioning & commissioning · unknown
- Start-up · not started
Sources: 1 offshore-mag.com · checked 29 Oct 2026
ON THE RADAROFFSHORENorway · FPSO
Equinor Wisting (Barents Sea): FPSO topsides
Aibel (FEED for FPSO topsides, option for engineering, procurement and project management)
- FEED: FEED: in progress, 22 Oct 2026
- Award: EPC award: not started
- E&P: Engineering & procurement: not started
- Build: Construction: not started
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: FEED
- Value
- not disclosed [1]
- Workforce
- approximately 250 people will be involved (Aibel, FEED contract) [1]
- Finish
- not published
No open adverts linked today
Client, scope, phases, sources
Client: Equinor (42.5%) with Aker BP, Petoro, INPEX Idemitsu
Value: not disclosed [1]
Scope
- FEED for the topsides of the production vessel (Barents Sea) [1]
Phase by phase
- FEED · in progress · 22 Oct 2026 [1]
- EPC award · not started · investment decision planned for late 2027 [1]
- Engineering & procurement · not started
- Construction · not started
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 equinor.com · checked 29 Oct 2026
CONFIRMEDLARGEKazakhstan · Petrochemical
Silleno polyethylene plant, Atyrau: 1.25 Mtpa
Tecnimont (MAIRE) (polymerisation and offsites EPC, with Sinopec Shanghai Engineering) · Sinopec Shanghai Engineering (with Tecnimont) · pyrolysis unit contractor not named
- FEED: FEED: done
- Award: EPC award: done, 2 Sep 2025
- E&P: Engineering & procurement: in progress
- Build: Construction: in progress, 30 Sep 2026
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now:
Construction ·
39% complete (Sep 2026)
[1]39%
- Value
- USD 7.7bn [1]
- Workforce
- not published
- Finish
- completion 2028-2029 (Trend, Sep… [1]
No open adverts linked today
Client, scope, phases, sources
Client: Silleno LLP (KazMunayGas 40%, SIBUR 30%, Sinopec 30%)
Value: about USD 7.7bn (project) [1]
Finish: completion 2028-2029 (Trend, Sep 2026) [1]
Scope
- 1.25 Mtpa polyethylene, Atyrau [1]
Phase by phase
Progress: construction above 39% (Sep 2026) [1]
- FEED · done
- EPC award · done · 2 Sep 2025 [2]
- Engineering & procurement · in progress
- Construction · in progress · 30 Sep 2026 [1]
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 trend.az 2 hydrocarbonprocessing.com · checked 29 Oct 2026
CONFIRMEDLARGECanada · LNG plant
LNG Canada Phase 2, Kitimat: 2 trains + 1 tank (to about 28 Mtpa)
Fluor Canada (JGC Fluor BC LNG II JV, 50%) · JGC Constructors (JGC Fluor BC LNG II JV, 50%)
- FEED: FEED: done
- Award: EPC award: done, 1 Oct 2026
- E&P: Engineering & procurement: in progress
- Build: Construction: not started
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Engineering & procurement
- Value
- USD 7.5bn [1]
- Workforce
- more than 4,000 direct jobs in the construction phase alone (Government of Canada, 29 Sep 2026) [2]
- Finish
- not published
No open adverts linked today
Client, scope, phases, sources
Client: LNG Canada (Shell 40%, Petronas 25%, PetroChina 15%, Mitsubishi 15%, KOGAS 5%)
Value: Fluor's share USD 7.5 billion of a multibillion-dollar contract; project USD 33 billion (Government of Canada) [1]
Scope
- 2 liquefaction trains + 1 storage tank, terminal to about 28 Mtpa [1]
Phase by phase
- FEED · done
- EPC award · done · 1 Oct 2026 · FID 29 Sep 2026; notice to proceed [1]
- Engineering & procurement · in progress
- Construction · not started
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 energy-pedia.com 2 pm.gc.ca · checked 29 Oct 2026
CONFIRMEDCanada · Gas compression
Coastal GasLink Phase 2: 5 compressor stations (pipeline capacity doubled)
TR Canada E&C (Tecnicas Reunidas) (EPCM)
- FEED: FEED: unknown
- Award: EPC award: done, 21 Oct 2026
- E&P: Engineering & procurement: in progress
- Build: Construction: not started
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Engineering & procurement
- Value
- EUR 200m [1]
- Workforce
- CGL Phase 2 expected to create over 2,000 jobs (Government of Canada, 29 Sep 2026) [2]
- Finish
- execution from early 2027, over 4… [1]
No open adverts linked today
Client, scope, phases, sources
Client: LNG Canada (execution manager); Coastal GasLink owner
Value: above EUR 200 million (about USD 225m) [1]
Finish: execution from early 2027, over 4 years (OGJ) [1]
Scope
- 5 compressor stations, pipeline capacity doubled [1]
Phase by phase
- FEED · unknown
- EPC award · done · 21 Oct 2026 [1]
- Engineering & procurement · in progress
- Construction · not started
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 ogj.com 2 pm.gc.ca · checked 29 Oct 2026
ON THE RADARLARGEUnited States · Pipeline
Kinder Morgan Southeast Connector: about 470 miles, up to 2.6 bcf/d
Contractors: construction contractors not named
- FEED: FEED: unknown
- Award: EPC award: not started
- E&P: Engineering & procurement: not started
- Build: Construction: not started
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Before the EPC award
- Value
- USD 3.1bn [1]
- Workforce
- not published
- Finish
- 2030 [1]
No open adverts linked today
Client, scope, phases, sources
Client: Southern Natural Gas (Kinder Morgan)
Value: USD 3.1 billion (project) [1]
Finish: service expected to begin in phases from Q4 2030, subject to permits [1]
Scope
- about 470 miles of new pipeline [1]
- up to 2.6 bcfd [1]
Phase by phase
- FEED · unknown
- EPC award · not started · FID 22 Oct 2026; contractors not named [1]
- Engineering & procurement · not started
- Construction · not started
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 ogj.com · checked 29 Oct 2026
CONFIRMEDOFFSHOREBrazil · FPSO
Petrobras Buzios FPSOs P-80 and P-82 (+450,000 b/d together)
Seatrium (turnkey FPSOs)
- FEED: FEED: done
- Award: EPC award: done
- E&P: Engineering & procurement: done
- Build: Construction: done, 27 Aug 2026
- Comm.: Pre-commissioning & commissioning: in progress
- Start: Start-up: not started
Now: Pre-commissioning & commissioning
- Value
- not stated in the source [1]
- Workforce
- not published
- Finish
- 2027 [1]
No open adverts linked today
Client, scope, phases, sources
Client: Petrobras
Value: not stated in the source [1]
Finish: production in 2027 [1]
Scope
- two FPSOs, +450,000 b/d together, Buzios pre-salt [1]
Phase by phase
- FEED · done
- EPC award · done
- Engineering & procurement · done
- Construction · done · 27 Aug 2026 · christened in Singapore; P-80 and P-82 sailed Sep-Oct 2026 [1]
- Pre-commissioning & commissioning · in progress
- Start-up · not started
Sources: 1 worldoil.com · checked 29 Oct 2026
CONFIRMEDLARGEOFFSHOREGuyana · FPSO
ExxonMobil Whiptail (Stabroek block, 6th project): 250,000 b/d, FPSO Jaguar
Saipem (subsea) · EnerMech (pre-commissioning subcontract) · FPSO builder not named in the sources we read
- FEED: FEED: done
- Award: EPC award: done
- E&P: Engineering & procurement: in progress
- Build: Construction: in progress, 13 Jan 2026
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Construction
- Value
- USD 12.7bn [1]
- Workforce
- not published
- Finish
- 2027 [1]
No open adverts linked today
Client, scope, phases, sources
Client: ExxonMobil Guyana
Value: USD 12.7 billion (project) [1]
Finish: start-up targeted by end of 2027 [1]
Scope
- 250,000 b/d, FPSO Jaguar, Stabroek block [1]
Phase by phase
- FEED · done
- EPC award · done
- Engineering & procurement · in progress
- Construction · in progress · 13 Jan 2026 · subsea installation [1]
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 worldoil.com · checked 29 Oct 2026
CONFIRMEDMEDIUMArgentina · Fertiliser
Fertil Pampa urea complex, Bahia Blanca: ammonia + 2 urea trains (6,000 t/d)
Tecnimont (MAIRE) (engineering, procurement, commissioning, start-up) · Nextchem (technology, EUR 140m) · SACDE (construction)
- FEED: FEED: done
- Award: EPC award: done, 20 Jul 2026
- E&P: Engineering & procurement: in progress
- Build: Construction: not started
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Engineering & procurement
- Value
- EUR 1.3bn [1]
- Workforce
- more than 3,500 direct jobs at peak construction (MAIRE) [1]
- Finish
- completion expected in 41 months… [1]
Client, scope, phases, sources
Client: Fertil Pampa (Pampa Energia)
Value: approximately EUR 1.3 billion, of which EUR 140 million Nextchem technology [1]
Finish: completion expected in 41 months (from July 2026) [1]
Scope
- ammonia plant + 2 urea trains, 6,000 t/d (2.1 Mtpa) [1]
Phase by phase
- FEED · done
- EPC award · done · 20 Jul 2026 [1]
- Engineering & procurement · in progress
- Construction · not started
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 hydrocarbonprocessing.com · checked 29 Oct 2026
CONFIRMEDMEDIUMVietnam · Refinery
Dung Quat refinery upgrade and expansion, 148,000 to 171,000 b/d
China Chengda Engineering (EPC consortium) · Beijing Petrochemical Engineering (EPC consortium) · Wood (PMC, with Petrovietnam Engineering) · Petrovietnam Engineering (PMC)
- FEED: FEED: done
- Award: EPC award: done, Aug 2026
- E&P: Engineering & procurement: in progress
- Build: Construction: unknown
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Engineering & procurement
- Value
- USD 1.5bn [1]
- Workforce
- not published
- Finish
- 2028 [1]
No open adverts linked today
Client, scope, phases, sources
Client: Binh Son Refining and Petrochemical (BSR, Petrovietnam)
Value: USD 1.489bn [1]
Finish: commercial operation 2028 [1]
Scope
- refinery from 148,000 to 171,000 b/d [1]
- EPC duration 37 months [1]
Phase by phase
- FEED · done
- EPC award · done · Aug 2026 [1]
- Engineering & procurement · in progress
- Construction · unknown
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 ogj.com · checked 29 Oct 2026
CONFIRMEDOFFSHOREBrazil · FPSO
Petrobras Buzios 11: FPSO P-83 (225,000 b/d)
Seatrium (FPSO newbuild)
- FEED: FEED: done
- Award: EPC award: done
- E&P: Engineering & procurement: done
- Build: Construction: in progress
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Construction
- Value
- not published
- Workforce
- not published
- Finish
- 2027 [1]
No open adverts linked today
Client, scope, phases, sources
Client: Petrobras (88.99%) with Buzios partners
Value: not published
Finish: start-up 2027 (Petrobras 2Q26 report) [1]
Scope
- FPSO, 225,000 b/d oil, Buzios field, Santos Basin pre-salt; start-up 2027 [1]
- in Seatrium's order book with P-78, P-80 and P-82 (Petrobras FPSO newbuilds) [2]
Phase by phase
- FEED · done
- EPC award · done
- Engineering & procurement · done
- Construction · in progress
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 sec.gov 2 links.sgx.com · checked 29 Oct 2026
CONFIRMEDLARGEOFFSHOREBrazil · FPSO
Petrobras Atapu 2 and Sepia 2: FPSOs P-84 and P-85 (225,000 b/d each)
Seatrium (FPSO newbuild, both units)
- FEED: FEED: done
- Award: EPC award: done, 25 May 2024
- E&P: Engineering & procurement: in progress
- Build: Construction: in progress, 2025
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Construction
- Value
- SGD 11bn [1]
- Workforce
- not published
- Finish
- 2030 [2]
No open adverts linked today
Client, scope, phases, sources
Client: Petrobras, operator of the Atapu and Sepia consortia
Value: approximately SGD 11 billion (both FPSOs) [1]
Finish: P-84 start-up 2029, P-85 2030 (Petrobras 2Q26) [2]
Scope
- two FPSOs, 225,000 b/d oil and 10 million m3/d gas each; all-electric, zero routine flaring [1]
- modules (60,000 t) built in Seatrium yards in Brazil, China and Singapore; integration in Singapore [1]
- start-up: P-84 (Atapu) 2029, P-85 (Sepia) 2030 [2]
Phase by phase
- FEED · done
- EPC award · done · 25 May 2024 · contracts signed [1]
- Engineering & procurement · in progress
- Construction · in progress · 2025 · construction to start Q1 2025 (Seatrium) [1]
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 links.sgx.com 2 sec.gov · checked 29 Oct 2026
CONFIRMEDOFFSHOREBrazil · FPSO
Petrobras SEAP I and II (Sergipe-Alagoas deepwater): FPSOs P-81 and P-87, 120,000 b/d each
SBM Offshore (design, build and operate both FPSOs (BOT))
- FEED: FEED: done
- Award: EPC award: done, 29 May 2026
- E&P: Engineering & procurement: in progress
- Build: Construction: not started
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Engineering & procurement
- Value
- not published
- Workforce
- not published
- Finish
- 2031 [1]
No open adverts linked today
Client, scope, phases, sources
Client: Petrobras-led consortia
Value: not published
Finish: SEAP-II delivery 2030, SEAP-I 2031 [1]
Scope
- two Fast4Ward FPSOs, 120,000 b/d oil each, about 2,500 m water depth [1]
- SEAP-II delivery 2030, SEAP-I 2031; SBM operates for an initial 6.5 years [1]
Phase by phase
- FEED · done
- EPC award · done · 29 May 2026 · contracts signed [1]
- Engineering & procurement · in progress
- Construction · not started
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 worldoil.com 2 sec.gov · checked 29 Oct 2026
CONFIRMEDLARGEOFFSHOREBrazil · FPSO
Equinor Raia (BM-C-33), Campos Basin pre-salt: gas FPSO, 16 million m3/d
MODEC (FPSO, lump-sum turnkey EPCI) · TechnipFMC (subsea EPCI (SURF))
- FEED: FEED: done
- Award: EPC award: done, 10 May 2023
- E&P: Engineering & procurement: in progress
- Build: Construction: in progress
- Comm.: Pre-commissioning & commissioning: in progress, 1 Jul 2026
- Start: Start-up: not started
Now: Pre-commissioning & commissioning
- Value
- USD 9bn [1]
- Workforce
- not published
- Finish
- 2028 [2]
No open adverts linked today
Client, scope, phases, sources
Client: Equinor (35%, operator), Repsol Sinopec Brasil (35%), Petrobras (30%)
Value: about USD 9 billion (project investment) [1]
Finish: operations from 2028 [2]
Scope
- FPSO with about 126,000 b/d of oil/condensate and 16 million m3/d gas export [1]
- FPSO accommodation commissioning completed July 2026 [2]
Phase by phase
- FEED · done
- EPC award · done · 10 May 2023 [1]
- Engineering & procurement · in progress
- Construction · in progress
- Pre-commissioning & commissioning · in progress · 1 Jul 2026 · accommodation modules commissioned [2]
- Start-up · not started
Sources: 1 equinor.com 2 tagdlaw.com.br · checked 29 Oct 2026
ON THE RADAROFFSHOREBrazil · FPSO
Petrobras Albacora revitalisation: FPSO P-88 (120,000 b/d), BOT tender
Yinson (lowest bidder, USD 2.29 bn; award not confirmed)
- FEED: FEED: done
- Award: EPC award: unknown
- E&P: Engineering & procurement: unknown
- Build: Construction: not started
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Last step done: FEED
- Value
- lowest bid USD 2.29 billion… [1]
- Workforce
- not published
- Finish
- first oil after 2031 [1]
No open adverts linked today
Client, scope, phases, sources
Client: Petrobras
Value: lowest bid USD 2.29 billion (Yinson); contract not signed [1]
Scope
- FPSO, 120,000 b/d oil and up to 4.3 million m3/d gas, build-operate-transfer [1]
- bids: Yinson 2.29, COOEC 2.84, Shapoorji 2.9, MISC 3.05, BW 3.19 (USD bn) [1]
Phase by phase
- FEED · done
- EPC award · unknown
- Engineering & procurement · unknown
- Construction · not started
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 agenciainfra.com · checked 29 Oct 2026
CONFIRMEDLARGEOFFSHOREGuyana · FPSO
ExxonMobil Uaru (Stabroek, 5th project): FPSO Errea Wittu, 250,000 b/d
MODEC (FPSO Errea Wittu)
- FEED: FEED: done
- Award: EPC award: done
- E&P: Engineering & procurement: done
- Build: Construction: done, 21 Aug 2026
- Comm.: Pre-commissioning & commissioning: in progress
- Start: Start-up: not started
Now: Pre-commissioning & commissioning
- Value
- USD 12.7bn [1]
- Workforce
- not published
- Finish
- first oil expected in Q4 2026 [2]
No open adverts linked today
Client, scope, phases, sources
Client: ExxonMobil Guyana (45%, operator), Chevron (30%), CNOOC (25%)
Value: USD 12.7 billion (project) [1]
Scope
- FPSO Errea Wittu, up to 250,000 b/d, about 2 million bbl storage [1]
- FPSO arrived in Guyana in August 2026; final preparations for start-up [2]
Phase by phase
- FEED · done
- EPC award · done
- Engineering & procurement · done
- Construction · done · 21 Aug 2026 · FPSO arrived in Guyanese waters [1]
- Pre-commissioning & commissioning · in progress
- Start-up · not started
Sources: 1 energynow.tt 2 industrialinfo.com · checked 29 Oct 2026
CONFIRMEDLARGEOFFSHOREGuyana · FPSO
ExxonMobil Hammerhead (Stabroek, 7th project): FPSO 150,000 b/d
MODEC (FPSO) · Seatrium (FPSO topsides integration, flare tower and crane pedestal, commissioning support (for MODEC, Nov 2026))
- FEED: FEED: done
- Award: EPC award: done, 24 Sep 2025
- E&P: Engineering & procurement: done
- Build: Construction: in progress
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Construction
- Value
- USD 6.8bn [1]
- Workforce
- not published
- Finish
- 2029 [1]
No open adverts linked today
Client, scope, phases, sources
Client: ExxonMobil Guyana (45%, operator), Hess (30%), CNOOC (25%)
Value: USD 6.8 billion (field development) [1]
Finish: first oil 2029 [1]
Scope
- FPSO 150,000 b/d, 1.6 million bbl storage, 18 production and injection wells [1]
- construction under way (Oct 2026) [2]
Phase by phase
- FEED · done
- EPC award · done · 24 Sep 2025 · FID [1]
- Engineering & procurement · done
- Construction · in progress
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 jpt.spe.org 2 industrialinfo.com 3 euro-petrole.com · checked 17 Nov 2026
CONFIRMEDLARGEOFFSHOREGuyana · FPSO
ExxonMobil Longtail (Stabroek, 8th project): gas-condensate FPSO, FID 12 Nov 2026
SBM Offshore (FPSO (construct and install after FID)) · Saipem (subsea EPCI (SURF: structures, umbilicals, risers, flowlines); full authorization to proceed 17 Nov 2026, about 4 years) · TechnipFMC (supplier: subsea production systems and flexible production risers)
- FEED: FEED: done
- Award: EPC award: done, 12 Nov 2026
- E&P: Engineering & procurement: in progress
- Build: Construction: not started
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Engineering & procurement
- Value
- USD 12.5bn [1]
- Workforce
- not published
- Finish
- start-up expected in 2030… [1]
No open adverts linked today
Client, scope, phases, sources
Client: ExxonMobil Guyana (45%, operator), Hess Guyana Exploration (30%), CNOOC Petroleum Guyana (25%)
Value: USD 12.5 billion (planned additional investment) [1]
Finish: start-up expected in 2030 (ExxonMobil) [1]
Scope
- 1.2 bcf/d gas, up to 250,000 b/d condensate, about 45 subsea production and injection wells [1]
- SBM Fast4Ward hull, spread moored in about 1,750 m of water, about 2 million bbl condensate storage [2]
- development of the Longtail, Tripletail and Turbot discoveries; gas and condensate with reinjection [3]
Phase by phase
- FEED · done · SBM Offshore FEED awarded 24 Mar 2026 [2]
- EPC award · done · 12 Nov 2026 · FID; SBM to construct and install the FPSO after FID (SBM, 24 Mar 2026) [1]
- Engineering & procurement · in progress
- Construction · not started
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 corporate.exxonmobil.com 2 ml-eu.globenewswire.com 3 industrialinfo.com 4 ocean-energyresources.com 5 finviz.com · checked 24 Nov 2026
REPORTEDOFFSHORESaudi Arabia · Offshore platform
Aramco Marjan offshore development: CRPO 166 structures (EPCI)
McDermott (EPCI, single-sourced change order)
- FEED: FEED: done
- Award: EPC award: done
- E&P: Engineering & procurement: done
- Build: Construction: done
- Comm.: Pre-commissioning & commissioning: in progress
- Start: Start-up: unknown
Now: Pre-commissioning & commissioning
- Value
- not published
- Workforce
- not published
- Finish
- not published
No open adverts linked today
Client, scope, phases, sources
Client: Saudi Aramco
Value: not published
Scope
- EPCI of structures carved out of the USD 15 bn Marjan offshore development [1]
- McDermott nearing completion of the EPCI works (Jan 2026) [1]
Phase by phase
- FEED · done
- EPC award · done
- Engineering & procurement · done
- Construction · done
- Pre-commissioning & commissioning · in progress
- Start-up · unknown
Sources: 1 guest.meed.com · checked 29 Oct 2026
CONFIRMEDMEDIUMOFFSHORESaudi Arabia · Pipeline
Aramco Safaniya: 48-inch trunkline, 65 km offshore + 12 km onshore (CRPO 156)
Saipem (EPCI under the long-term agreement)
- FEED: FEED: done
- Award: EPC award: done, 25 Feb 2026
- E&P: Engineering & procurement: in progress
- Build: Construction: unknown
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Engineering & procurement
- Value
- USD 500m [1]
- Workforce
- not published
- Finish
- not published
No open adverts linked today
Client, scope, phases, sources
Client: Saudi Aramco
Value: approximately USD 500 million [1]
Scope
- 48-inch trunkline (about 65 km offshore, 12 km onshore) and subsea facilities, Safaniya field [1]
- fabrication at Saipem's Dammam yard; offshore work by Saipem vessels in the region [1]
Phase by phase
- FEED · done
- EPC award · done · 25 Feb 2026 [1]
- Engineering & procurement · in progress
- Construction · unknown
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 pgjonline.com · checked 29 Oct 2026
REPORTEDLARGEOFFSHORESaudi Arabia · Offshore platform
Aramco Zuluf offshore expansion: CRPOs 145-148 (jackets, decks, pipelines)
Larsen & Toubro Energy Hydrocarbon (CRPO 145 (likely award)) · Subsea7 (CRPOs 146 and 148 (frontrunner)) · Lamprell (CRPO 147 (frontrunner))
- FEED: FEED: done
- Award: EPC award: in progress
- E&P: Engineering & procurement: unknown
- Build: Construction: unknown
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: EPC award
- Value
- about USD 5.8 billion for the… [1]
- Workforce
- not published
- Finish
- not published
No open adverts linked today
Client, scope, phases, sources
Client: Saudi Aramco
Value: about USD 5.8 billion for the four packages (MEED estimate) [1]
Scope
- 29 slipover jackets and decks, tie-in platforms, subsea cables and about 110 km of pipelines incl. a 48-inch trunkline [1]
- L&T announced an 'ultra-mega' offshore order (above INR 150 bn) in July 2025, likely CRPO 145 [2]
Phase by phase
- FEED · done
- EPC award · in progress
- Engineering & procurement · unknown
- Construction · unknown
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 guest.meed.com 2 guest.meed.com · checked 26 Nov 2026
REPORTEDOFFSHORESaudi Arabia · Offshore platform
Aramco Arabiyah, Hasbah and Karan: four offshore gas jackets (CRPO 161)
COOEC (China Offshore Oil Engineering) (selected; formal award pending)
- FEED: FEED: done
- Award: EPC award: in progress
- E&P: Engineering & procurement: not started
- Build: Construction: not started
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: EPC award
- Value
- not published
- Workforce
- not published
- Finish
- not published
No open adverts linked today
Client, scope, phases, sources
Client: Saudi Aramco
Value: not published
Scope
- EPCI of four gas jackets at the Arabiyah, Hasbah and Karan fields [1]
Phase by phase
- FEED · done
- EPC award · in progress
- Engineering & procurement · not started
- Construction · not started
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 guest.meed.com · checked 26 Nov 2026
CONFIRMEDLARGEOFFSHOREQatar · Gas compression
QatarEnergy LNG North Field Production Sustainability COMP5: two offshore compression complexes
Saipem (EPCI, share about USD 3.1 bn) · COOEC (China Offshore Oil Engineering) (partner)
- FEED: FEED: done
- Award: EPC award: done, 22 Dec 2025
- E&P: Engineering & procurement: in progress
- Build: Construction: not started
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Engineering & procurement
- Value
- USD 4bn [1]
- Workforce
- not published
- Finish
- contract duration about five… [1]
No open adverts linked today
Client, scope, phases, sources
Client: QatarEnergy LNG
Value: about USD 4 billion (Saipem share about USD 3.1 billion) [1]
Finish: contract duration about five years; installation 2029 and 2030 [1]
Scope
- two complexes: compression platform, living quarters, flare platform and bridges, about 68,000 t each [1]
- offshore installation 2029-2030 by Saipem's De He; COMP2 and COMP3 already in execution, COMP4 to Technip Energies [1]
Phase by phase
- FEED · done
- EPC award · done · 22 Dec 2025 [1]
- Engineering & procurement · in progress
- Construction · not started
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 offshore-technology.com · checked 29 Oct 2026
CONFIRMEDOFFSHOREAustralia · Offshore platform
Woodside Scarborough: floating production unit + Pluto LNG Train 2 (5 Mtpa)
McDermott (FPU design, fabrication, integration, installation) · Bechtel (Pluto Train 2 EPC)
- FEED: FEED: done
- Award: EPC award: done
- E&P: Engineering & procurement: done
- Build: Construction: done, 13 Jan 2026
- Comm.: Pre-commissioning & commissioning: in progress
- Start: Start-up: not started
Now:
Pre-commissioning & commissioning ·
91% complete (Jan 2026)
[1]91%
- Value
- not published
- Workforce
- not published
- Finish
- 2026 [1]
No open adverts linked today
Client, scope, phases, sources
Client: Woodside (operator)
Value: not published
Finish: first LNG targeted for the second half of 2026 [1]
Scope
- semi-submersible FPU, about 30,000 t topsides (QMW yard, Qingdao) + 37,000 t hull, up to 1.8 Bcf/d [1]
- about 433 km pipeline to Pluto LNG Train 2 (about 5 Mtpa) [1]
Phase by phase
Progress: 91% complete (Woodside, January 2026) [1]
- FEED · done
- EPC award · done
- Engineering & procurement · done
- Construction · done · 13 Jan 2026 · FPU on location [1]
- Pre-commissioning & commissioning · in progress
- Start-up · not started
Sources: 1 jpt.spe.org · checked 29 Oct 2026
CONFIRMEDLARGEOFFSHOREMexico · Offshore platform
Woodside-Pemex Trion (Mexican Gulf deepwater): FPU 100,000 b/d + FSO
HD Hyundai Heavy Industries (FPU EPC, Ulsan) · SBM Offshore (FPU and FSO installation)
- FEED: FEED: done
- Award: EPC award: done
- E&P: Engineering & procurement: done
- Build: Construction: in progress, 13 Nov 2024
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Construction
- Value
- USD 7.2bn [1]
- Workforce
- not published
- Finish
- 2028 [2]
No open adverts linked today
Client, scope, phases, sources
Client: Woodside (60%, operator), Pemex (40%)
Value: estimated USD 7.2 billion (investment) [1]
Finish: first oil targeted for 2028 [2]
Scope
- semi-submersible FPU 100,000 b/d linked to a 950,000 bbl FSO [1]
- FPU steel cut in Ulsan in November 2024 [2]
Phase by phase
- FEED · done
- EPC award · done
- Engineering & procurement · done
- Construction · in progress · 13 Nov 2024 · FPU steel cutting [2]
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 jpt.spe.org 2 energy-pedia.com · checked 29 Oct 2026
CONFIRMEDOFFSHOREUnited States · Offshore platform
bp Kaskida (US Gulf, Paleogene): FPU 80,000 b/d
Seatrium (FPU EPC and onshore commissioning)
- FEED: FEED: done
- Award: EPC award: done, 24 Dec 2024
- E&P: Engineering & procurement: in progress
- Build: Construction: unknown
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Engineering & procurement
- Value
- not published
- Workforce
- not published
- Finish
- not published
No open adverts linked today
Client, scope, phases, sources
Client: bp
Value: not published
Scope
- semi-submersible FPU, 80,000 b/d from six wells in phase 1 [1]
Phase by phase
- FEED · done
- EPC award · done · 24 Dec 2024 [1]
- Engineering & procurement · in progress
- Construction · unknown
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 bairdmaritime.com · checked 29 Oct 2026
CONFIRMEDOFFSHOREUnited Kingdom · FPSO
Rosebank (West of Shetland, UK): FPSO Rosebank (ex-Knarr), hook-up and commissioning
TechnipFMC (iEPCI: subsea production systems, umbilicals, risers and flowlines) · Altera Infrastructure (FPSO Petrojarl Knarr owner: bareboat charter and operations & maintenance) · Aker Solutions (FPSO upgrade, in JV with Drydocks World (Dubai), completed) · contractors not named in the source read today
- FEED: FEED: done
- Award: EPC award: done
- E&P: Engineering & procurement: done
- Build: Construction: done, Jun 2026
- Comm.: Pre-commissioning & commissioning: in progress
- Start: Start-up: not started
Now: Pre-commissioning & commissioning
- Value
- not published
- Workforce
- not published
- Finish
- start-up targeted for the first… [1]
No open adverts linked today
Client, scope, phases, sources
Client: Adura (Equinor-Shell JV, operator) and Ithaca Energy
Value: not published
Finish: start-up targeted for the first half of 2027 [1]
Scope
- FPSO Rosebank (formerly on Knarr, Norway) moored on location June 2026; hook-up and commissioning under way [1]
- start-up subject to final UK government approval, expected by end-2026 [1]
Phase by phase
- FEED · done
- EPC award · done
- Engineering & procurement · done
- Construction · done · Jun 2026 · FPSO moored on location [1]
- Pre-commissioning & commissioning · in progress
- Start-up · not started
Sources: 1 offshore-mag.com 2 pressandjournal.co.uk 3 ogj.com · checked 29 Oct 2026
ON THE RADAROFFSHORENamibia · FPSO
TotalEnergies Venus (Block 2913B, Orange Basin): FPSO 150,000-200,000 b/d, pre-FID
Hanwha Ocean (FPSO bidder) · SBM Offshore (FPSO bidder)
- FEED: FEED: done
- Award: EPC award: unknown
- E&P: Engineering & procurement: unknown
- Build: Construction: not started
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Last step done: FEED
- Value
- initial phase up to USD 10… [1]
- Workforce
- not published
- Finish
- 2030 [1]
No open adverts linked today
Client, scope, phases, sources
Client: TotalEnergies (operator)
Value: initial phase up to USD 10 billion (industry estimate) [1]
Finish: first oil targeted for 2030 [1]
Scope
- FPSO for 150,000-200,000 b/d; subsea package at least USD 2.5 bn [1]
Phase by phase
- FEED · done
- EPC award · unknown
- Engineering & procurement · unknown
- Construction · not started
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 republikein.com.na · checked 29 Oct 2026
CONFIRMEDLARGEOFFSHOREAngola · FPSO
Azule Energy Greater PAJ (Blocks 31 and 31/21): new FPSO 95,000 b/d
CIMC Raffles (FPSO, Haiyang yard) · Saipem (transport and installation) · TechnipFMC (risers and flowlines) · Baker Hughes (subsea production systems) · OneSubsea (umbilicals) · Vallourec (rigid pipes)
- FEED: FEED: done
- Award: EPC award: done, 23 Jun 2026
- E&P: Engineering & procurement: done
- Build: Construction: in progress
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Construction
- Value
- USD 5.1bn [1]
- Workforce
- not published
- Finish
- 2029 [1]
No open adverts linked today
Client, scope, phases, sources
Client: Azule Energy (bp-Eni JV)
Value: USD 5.1 billion (FID investment) [1]
Finish: first oil expected in the first half of 2029 [1]
Scope
- new FPSO 95,000 b/d linking Block 31 production with Block 31/21 discoveries [1]
- FPSO topsides steel cut at CIMC Raffles Haiyang, July 2026 [1]
Phase by phase
- FEED · done
- EPC award · done · 23 Jun 2026 · FID and six main contracts [1]
- Engineering & procurement · done
- Construction · in progress
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 oedigital.com · checked 29 Oct 2026
CONFIRMEDOFFSHOREChina · Fabrication yard
Fabrication yard: Qingdao McDermott Wuchuan (QMW), Qingdao
McDermott (JV yard)
- FEED: FEED: unknown
- Award: EPC award: unknown
- E&P: Engineering & procurement: unknown
- Build: Construction: in progress
- Comm.: Pre-commissioning & commissioning: in progress
- Start: Start-up: unknown
Now: Pre-commissioning & commissioning
- Value
- not published
- Workforce
- not published
- Finish
- not published
Client, scope, phases, sources
Client: McDermott-Wuchuan joint venture (yard owner)
Value: not published
Scope
- 60 ha yard, 300 m skidway (50,000 t load-out), up to 90,000 t a year [1]
- now fabricating: jacket and topside for ADNOC Umm Shaif package 4 (awarded Aug 2026) [2]
- built the Scarborough FPU topsides (about 30,000 t) [3]
Phase by phase
- FEED · unknown
- EPC award · unknown
- Engineering & procurement · unknown
- Construction · in progress
- Pre-commissioning & commissioning · in progress
- Start-up · unknown
Sources: 1 mcdermott.com 2 worldoil.com 3 jpt.spe.org · checked 29 Oct 2026
CONFIRMEDOFFSHOREIndonesia · Fabrication yard
Fabrication yard: McDermott Batam (Indonesia)
McDermott (yard)
- FEED: FEED: unknown
- Award: EPC award: unknown
- E&P: Engineering & procurement: unknown
- Build: Construction: unknown
- Comm.: Pre-commissioning & commissioning: unknown
- Start: Start-up: unknown
Phases not published
- Value
- not published
- Workforce
- not published
- Finish
- not published
Client, scope, phases, sources
Client: McDermott (yard owner)
Value: not published
Scope
- 120 ha yard, 817 m quay, up to 60,000 t a year: fixed and floating offshore structures, LNG modules, subsea structures [1]
Phase by phase
- FEED · unknown
- EPC award · unknown
- Engineering & procurement · unknown
- Construction · unknown
- Pre-commissioning & commissioning · unknown
- Start-up · unknown
Sources: 1 mcdermott.com · checked 29 Oct 2026
CONFIRMEDOFFSHOREUAE · Fabrication yard
Fabrication yard: McDermott Jebel Ali (Dubai)
McDermott (yard)
- FEED: FEED: unknown
- Award: EPC award: unknown
- E&P: Engineering & procurement: unknown
- Build: Construction: unknown
- Comm.: Pre-commissioning & commissioning: unknown
- Start: Start-up: unknown
Phases not published
- Value
- not published
- Workforce
- not published
- Finish
- not published
Client, scope, phases, sources
Client: McDermott (yard owner)
Value: not published
Scope
- 53 ha yard, up to 50,000 t a year: pipe fabrication, cladding, girders for the Middle East and India [1]
Phase by phase
- FEED · unknown
- EPC award · unknown
- Engineering & procurement · unknown
- Construction · unknown
- Pre-commissioning & commissioning · unknown
- Start-up · unknown
Sources: 1 mcdermott.com · checked 29 Oct 2026
REPORTEDOFFSHOREUAE · Fabrication yard
Fabrication yard: NMDC Energy Mussafah (Abu Dhabi)
NMDC Energy (yard)
- FEED: FEED: unknown
- Award: EPC award: unknown
- E&P: Engineering & procurement: unknown
- Build: Construction: unknown
- Comm.: Pre-commissioning & commissioning: unknown
- Start: Start-up: unknown
Phases not published
- Value
- not published
- Workforce
- not published
- Finish
- not published
No open adverts linked today
Client, scope, phases, sources
Client: NMDC Energy (yard owner)
Value: not published
Scope
- fabricated the first jackets of ADNOC's Hail and Ghasha offshore gas project (load-out July 2025) [1]
Phase by phase
- FEED · unknown
- EPC award · unknown
- Engineering & procurement · unknown
- Construction · unknown
- Pre-commissioning & commissioning · unknown
- Start-up · unknown
Sources: 1 meed.com · checked 29 Oct 2026
CONFIRMEDOFFSHORESaudi Arabia · Fabrication yard
Fabrication yard: NMDC Energy Ras Al Khair (Saudi Arabia)
NMDC Energy (yard)
- FEED: FEED: unknown
- Award: EPC award: unknown
- E&P: Engineering & procurement: unknown
- Build: Construction: unknown
- Comm.: Pre-commissioning & commissioning: unknown
- Start: Start-up: unknown
Phases not published
- Value
- AED 200m [1]
- Workforce
- more than 1,800 experienced employees moved from Abu Dhabi to the yard [1]
- Finish
- not published
No open adverts linked today
Client, scope, phases, sources
Client: NMDC Energy (yard owner)
Value: AED 200 million (yard investment) [1]
Scope
- 400,000 m2 yard; nine offshore jackets for Aramco in production at opening [1]
Phase by phase
- FEED · unknown
- EPC award · unknown
- Engineering & procurement · unknown
- Construction · unknown
- Pre-commissioning & commissioning · unknown
- Start-up · unknown
Sources: 1 nmdc-group.com · checked 29 Oct 2026
CONFIRMEDOFFSHOREIndia · Fabrication yard
Fabrication yard: L&T Kattupalli modular yard (near Chennai)
Larsen & Toubro (yard)
- FEED: FEED: unknown
- Award: EPC award: unknown
- E&P: Engineering & procurement: unknown
- Build: Construction: unknown
- Comm.: Pre-commissioning & commissioning: unknown
- Start: Start-up: unknown
Phases not published
- Value
- not published
- Workforce
- not published
- Finish
- not published
Client, scope, phases, sources
Client: Larsen & Toubro (yard owner)
Value: not published
Scope
- delivered 110 modules (about 64,000 t) for Project CERES, Western Australia (Sep 2026) [1]
- L&T modular capacity about 200,000 t a year across Kattupalli, Hazira and Oman [1]
Phase by phase
- FEED · unknown
- EPC award · unknown
- Engineering & procurement · unknown
- Construction · unknown
- Pre-commissioning & commissioning · unknown
- Start-up · unknown
Sources: 1 kotakneo.com · checked 29 Oct 2026
CONFIRMEDOFFSHORESingapore · Fabrication yard
Fabrication yard: Seatrium Tuas Boulevard (Singapore) and Brazil yards
Seatrium (yard)
- FEED: FEED: unknown
- Award: EPC award: unknown
- E&P: Engineering & procurement: unknown
- Build: Construction: unknown
- Comm.: Pre-commissioning & commissioning: unknown
- Start: Start-up: unknown
Phases not published
- Value
- not published
- Workforce
- not published
- Finish
- not published
No open adverts linked today
Client, scope, phases, sources
Client: Seatrium (yard owner)
Value: not published
Scope
- P-80 and P-82 FPSOs completed at Tuas Boulevard (2026); modules from BrasFELS and Aracruz (Brazil) [1]
- P-84 and P-85 integration in Singapore, modules from Brazil, China and Singapore [2]
- bp Kaskida FPU (EPC) [3]
Phase by phase
- FEED · unknown
- EPC award · unknown
- Engineering & procurement · unknown
- Construction · unknown
- Pre-commissioning & commissioning · unknown
- Start-up · unknown
Sources: 1 ogj.com 2 links.sgx.com 3 bairdmaritime.com · checked 29 Oct 2026
CONFIRMEDOFFSHOREChina · Fabrication yard
Fabrication yard: COOEC Qingdao base
COOEC (China Offshore Oil Engineering) (yard)
- FEED: FEED: unknown
- Award: EPC award: unknown
- E&P: Engineering & procurement: unknown
- Build: Construction: unknown
- Comm.: Pre-commissioning & commissioning: unknown
- Start: Start-up: unknown
Phases not published
- Value
- not published
- Workforce
- not published
- Finish
- not published
No open adverts linked today
Client, scope, phases, sources
Client: COOEC (yard owner)
Value: not published
Scope
- fabrication for QatarEnergy Bul Hanine (BH-EPIC1 and 2, more than 130,000 t of steel) started 15 Sep 2026 [1]
Phase by phase
- FEED · unknown
- EPC award · unknown
- Engineering & procurement · unknown
- Construction · unknown
- Pre-commissioning & commissioning · unknown
- Start-up · unknown
Sources: 1 equalocean.com · checked 29 Oct 2026
CONFIRMEDOFFSHORESaudi Arabia · Fabrication yard
Fabrication yard: Saipem Taqa Al-Rushaid Fabricators (Dammam)
Saipem (yard)
- FEED: FEED: unknown
- Award: EPC award: unknown
- E&P: Engineering & procurement: unknown
- Build: Construction: unknown
- Comm.: Pre-commissioning & commissioning: unknown
- Start: Start-up: unknown
Phases not published
- Value
- not published
- Workforce
- not published
- Finish
- not published
No open adverts linked today
Client, scope, phases, sources
Client: Saipem Taqa Al-Rushaid Fabricators (yard owner)
Value: not published
Scope
- fabrication for the Aramco Safaniya 48-inch trunkline contract (Feb 2026) [1]
Phase by phase
- FEED · unknown
- EPC award · unknown
- Engineering & procurement · unknown
- Construction · unknown
- Pre-commissioning & commissioning · unknown
- Start-up · unknown
Sources: 1 pgjonline.com · checked 29 Oct 2026
CONFIRMEDOFFSHORENigeria · Fabrication yard
Fabrication yard: Dorman Long Engineering, Naval Dockyard (Lagos)
Dorman Long Engineering (yard)
- FEED: FEED: unknown
- Award: EPC award: unknown
- E&P: Engineering & procurement: unknown
- Build: Construction: unknown
- Comm.: Pre-commissioning & commissioning: unknown
- Start: Start-up: unknown
Phases not published
- Value
- not published
- Workforce
- not published
- Finish
- not published
No open adverts linked today
Client, scope, phases, sources
Client: Dorman Long Engineering (yard owner)
Value: not published
Scope
- built the 1,300 t Madu conductor support platform at the Nigerian Naval Dockyard; modular separators for NAOC Irri [1]
Phase by phase
- FEED · unknown
- EPC award · unknown
- Engineering & procurement · unknown
- Construction · unknown
- Pre-commissioning & commissioning · unknown
- Start-up · unknown
Sources: 1 techeconomy.ng · checked 29 Oct 2026
CONFIRMEDAlgeria · Onshore oil field
Sonatrach-PTTEP Hassi Bir Rekaiz phase 2: crude processing unit 31,500 b/d
Petrojet (EPC consortium) · Arkad (EPC consortium)
- FEED: FEED: done
- Award: EPC award: done, 5 May 2026
- E&P: Engineering & procurement: in progress
- Build: Construction: unknown
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Engineering & procurement
- Value
- more than USD 1 billion (EPC… [1]
- Workforce
- not published
- Finish
- commissioning within 39 months [1]
No open adverts linked today
Client, scope, phases, sources
Client: Sonatrach and PTTEP (field partners)
Value: more than USD 1 billion (EPC contract) [1]
Scope
- new crude processing unit 31,500 b/d with associated gas and produced-water treatment [1]
Phase by phase
- FEED · done
- EPC award · done · 5 May 2026 · EPC contract signed [1]
- Engineering & procurement · in progress
- Construction · unknown
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 financialafrik.com · checked 29 Oct 2026
CONFIRMEDLARGEAlgeria · Refinery
Sonatrach Hassi Messaoud (Haoud El-Hamra) grassroots refinery, 5 Mtpa
Tecnicas Reunidas (EPC, 51%) · Sinopec (EPC, 49%) · Shaanxi Huajian Engineering (erection subcontract, package PK4 (CCR))
- FEED: FEED: done
- Award: EPC award: done
- E&P: Engineering & procurement: in progress
- Build: Construction: in progress, 24 Feb 2025
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Construction
- Value
- USD 4bn [1]
- Workforce
- EPC Radar estimate est. 9,600-44,300 at peak how?
- Finish
- first refining units from… [1]
No open adverts linked today
Client, scope, phases, sources
Client: Sonatrach
Value: about USD 4 billion (EPC contract) [1]
Finish: first refining units from end-2027; 65-month construction [1]
Workforce estimate (low confidence): EPC Radar estimate from 2 published refinery, petrochemical and fertiliser plants projects in this tracker, 2.4-11.1 workers per USD million of declared value (id-rdmp-balikpapan, ar-fertil-pampa), applied to contract value: about USD 4,000 m
Scope
- refinery of about 5 million t/yr of crude; CCR unit 1.35 Mt/yr in package PK4 [1]
- first stone laid 24 Feb 2025; construction period 65 months [1]
Phase by phase
- FEED · done
- EPC award · done
- Engineering & procurement · in progress
- Construction · in progress · 24 Feb 2025 · first stone [1]
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 algerie-eco.com · checked 29 Oct 2026
CONFIRMEDLARGEAlgeria · Gas compression
Sonatrach Hassi R'Mel boosting phase III: three compression stations
Baker Hughes - Nuovo Pignone International (EPC consortium) · Tecnimont (EPC consortium)
- FEED: FEED: done
- Award: EPC award: done, 23 May 2024
- E&P: Engineering & procurement: done
- Build: Construction: in progress
- Comm.: Pre-commissioning & commissioning: in progress
- Start: Start-up: not started
Now:
Pre-commissioning & commissioning ·
51% complete (Jul 2025)
[2]51%
- Value
- USD 2.3bn [1]
- Workforce
- not published
- Finish
- Apr 2027 [2]
No open adverts linked today
Client, scope, phases, sources
Client: Sonatrach
Value: USD 2.3 billion (EPC contract) [1]
Finish: compression units commissioning Oct 2026, Jan 2027 and Apr 2027 [2]
Scope
- three gas-boosting stations, 20 compression trains, upgrade of 300+ km of gathering lines; about 188 million m3/d [1]
Phase by phase
Progress: 51% complete (Sonatrach, July 2025) [2]
- FEED · done
- EPC award · done · 23 May 2024 [2]
- Engineering & procurement · done
- Construction · in progress
- Pre-commissioning & commissioning · in progress
- Start-up · not started
Sources: 1 offshore-technology.com 2 sonatrach.com · checked 29 Oct 2026
CONFIRMEDAlgeria · Fertiliser
Sonatrach Projet Phosphates Integre, phase 1: Bled El Hadba mine + Oued El-Kebrit fertiliser units
Saipem (EPC phase 1 (limited notice to proceed))
- FEED: FEED: done
- Award: EPC award: done, 12 Aug 2026
- E&P: Engineering & procurement: in progress
- Build: Construction: not started
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Engineering & procurement
- Value
- EUR 500m [1]
- Workforce
- not published
- Finish
- not published
No open adverts linked today
Client, scope, phases, sources
Client: Sonatrach
Value: about EUR 500 million (limited notice to proceed) [1]
Scope
- phosphate mining infrastructure at Bled El Hadba; fertiliser process units, utilities and logistics at Oued El-Kebrit [1]
Phase by phase
- FEED · done
- EPC award · done · 12 Aug 2026 · limited notice to proceed [1]
- Engineering & procurement · in progress
- Construction · not started
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 chemxplore.com · checked 29 Oct 2026
CONFIRMEDEgypt · Gas processing
Eni/Agiba Meleiha Phase 2 (Western Desert): gas plant 100 MMscfd + 200 km pipelines
Petrojet (main EPC contract)
- FEED: FEED: done
- Award: EPC award: done
- E&P: Engineering & procurement: done
- Build: Construction: done
- Comm.: Pre-commissioning & commissioning: in progress
- Start: Start-up: in progress, 21 Oct 2026
Now: Start-up
- Value
- not published
- Workforce
- not published
- Finish
- not published
No open adverts linked today
Client, scope, phases, sources
Client: Agiba Petroleum (Eni-EGPC JV)
Value: not published
Scope
- gas processing up to 100 MMscfd, sweetening and recovery units, 200 km of pipeline, 28 wells [1]
- Eni started bringing the plant online (Oct 2026) [1]
Phase by phase
- FEED · done
- EPC award · done
- Engineering & procurement · done
- Construction · done
- Pre-commissioning & commissioning · in progress
- Start-up · in progress · 21 Oct 2026 · start-up under way [1]
Sources: 1 guest.meed.com · checked 29 Oct 2026
CONFIRMEDOFFSHOREEgypt · Subsea
Burullus West Delta Deep Marine: subsea umbilical and 2 km TCP flowline replacement
Oceaneering (integrated transport, installation and commissioning)
- FEED: FEED: done
- Award: EPC award: done, 21 May 2026
- E&P: Engineering & procurement: in progress
- Build: Construction: in progress
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Construction
- Value
- not published
- Workforce
- not published
- Finish
- not published
No open adverts linked today
Client, scope, phases, sources
Client: Burullus Gas Company
Value: not published
Scope
- refurbished subsea umbilical + 2,000 m thermoplastic composite flowline, ROV and survey support [1]
Phase by phase
- FEED · done
- EPC award · done · 21 May 2026 [1]
- Engineering & procurement · in progress
- Construction · in progress
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 worldoil.com · checked 29 Oct 2026
CONFIRMEDLARGEOFFSHORELibya · Offshore platform
Mellitah Complex Expansion & CO2 Management (Structures A & E, NC 41 offshore)
Rosetti Marino (offshore EPC consortium, 33%) · Kerry Project Logistics (offshore EPC consortium) · Gruppo Antonini (offshore EPC consortium)
- FEED: FEED: done
- Award: EPC award: done
- E&P: Engineering & procurement: in progress
- Build: Construction: in progress
- Comm.: Pre-commissioning & commissioning: unknown
- Start: Start-up: unknown
Now: Construction
- Value
- USD 8bn [1]
- Workforce
- not published
- Finish
- not published
No open adverts linked today
Client, scope, phases, sources
Client: Mellitah Oil & Gas (NOC-Eni JV)
Value: about USD 8 billion (project); offshore EPC EUR 1.2 billion (June 2024) [1]
Scope
- wellhead platform A (96 m water) and production platform E (220 m), Sabratha modifications, onshore Mellitah upgrades [1]
- EPIC tender for subsea pipelines (about USD 3 bn): prequalification due 5 Nov 2026 [1]
Phase by phase
- FEED · done
- EPC award · done
- Engineering & procurement · in progress
- Construction · in progress
- Pre-commissioning & commissioning · unknown
- Start-up · unknown
Sources: 1 guest.meed.com · checked 12 Nov 2026
ON THE RADARMEDIUMOFFSHOREMorocco · Terminal & storage
Morocco Nador West Med: FSRU LNG terminal + national gas pipeline corridor (tenders)
Contractors: tenders open; no award published
- FEED: FEED: unknown
- Award: EPC award: not started
- E&P: Engineering & procurement: not started
- Build: Construction: not started
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Before the EPC award
- Value
- about USD 954 million first phase… [1]
- Workforce
- not published
- Finish
- 2027 [1]
No open adverts linked today
Client, scope, phases, sources
Client: Ministry of Energy Transition (Morocco)
Value: about USD 954 million first phase (FSRU about USD 273 m + pipelines about USD 681 m, estimates) [1]
Finish: terminal service target 2027 [1]
Scope
- FSRU lease at Nador West Med connected to the GME pipeline; PPP pipeline to Kenitra and Mohammedia [1]
Phase by phase
- FEED · unknown
- EPC award · not started
- Engineering & procurement · not started
- Construction · not started
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 italpress.com · checked 29 Oct 2026
CONFIRMEDSweden · CCS / BECCS
Stockholm Exergi BECCS, Vartan: 800,000 t/yr CO2 capture
Saipem (design, procurement and construction) · Skanska (ground, foundations and quay, phase 2)
- FEED: FEED: done
- Award: EPC award: done
- E&P: Engineering & procurement: in progress
- Build: Construction: in progress, Apr 2025
- Comm.: Pre-commissioning & commissioning: in progress
- Start: Start-up: not started
Now: Pre-commissioning & commissioning
- Value
- SEK 990m [1]
- Workforce
- not published
- Finish
- 2028 [2]
No open adverts linked today
Client, scope, phases, sources
Client: Stockholm Exergi
Value: about SEK 990 million (Skanska phase 2 groundworks) [1]
Finish: operations planned for 2028 [2]
Scope
- capture up to 800,000 t/yr of biogenic CO2 at the Vartan CHP plant [2]
- Skanska groundworks started April 2025, completion during 2028 [1]
Phase by phase
- FEED · done
- EPC award · done
- Engineering & procurement · in progress
- Construction · in progress · Apr 2025 · groundworks start [1]
- Pre-commissioning & commissioning · in progress
- Start-up · not started
Sources: 1 skanska.com 2 stockholmexergi.se · checked 29 Oct 2026
CONFIRMEDDenmark · CCS / BECCS
Orsted Kalundborg CO2 Hub BECCS (Asnaes + Avedore): 430,000 t/yr
Aker Carbon Capture (five Just Catch capture units (2023 plan))
- FEED: FEED: done
- Award: EPC award: done
- E&P: Engineering & procurement: done
- Build: Construction: in progress, 25 Feb 2025
- Comm.: Pre-commissioning & commissioning: unknown
- Start: Start-up: unknown
Now: Construction
- Value
- not published
- Workforce
- not published
- Finish
- 2026 [2]
No open adverts linked today
Client, scope, phases, sources
Client: Orsted
Value: not published
Finish: expected operational in early 2026 (Orsted, Feb 2025) [2]
Scope
- 430,000 t/yr of biogenic CO2 from Asnaes (wood chips) and Avedore (straw), shipped to Northern Lights [1]
- absorbers, desorbers and coolers lifted in place at both plants, Feb 2025 [2]
Phase by phase
- FEED · done
- EPC award · done
- Engineering & procurement · done
- Construction · in progress · 25 Feb 2025 · key components installed [2]
- Pre-commissioning & commissioning · unknown
- Start-up · unknown
Sources: 1 power-technology.com 2 energy-pedia.com · checked 29 Oct 2026
CONFIRMEDUnited Kingdom · CCS / BECCS
Net Zero Teesside Power: 742 MW gas power plant with carbon capture (2 Mt/yr)
Technip Energies (lead EPC) · GE Vernova (power island) · Balfour Beatty (construction, GBP 833 m)
- FEED: FEED: done
- Award: EPC award: done, Dec 2024
- E&P: Engineering & procurement: in progress
- Build: Construction: in progress
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Construction
- Value
- GBP 833m [1]
- Workforce
- not published
- Finish
- not published
No open adverts linked today
Client, scope, phases, sources
Client: Net Zero Teesside Power (bp-Equinor JV)
Value: GBP 833 million (Balfour Beatty construction contract) [1]
Scope
- 742 MW combined-cycle plant with post-combustion capture of up to 2 Mt CO2 a year, stored by the Northern Endurance Partnership [1]
Phase by phase
- FEED · done
- EPC award · done · Dec 2024 · FID [1]
- Engineering & procurement · in progress
- Construction · in progress
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 theconstructionindex.co.uk · checked 29 Oct 2026
CONFIRMEDMEDIUMOFFSHORENorway · CCS / BECCS
Northern Lights phase 2 (Oygarden): CO2 storage expansion to 5 Mt/yr
Aker Solutions (EPC onshore facilities) · Subsea7 (EPC 5 km CO2 pipeline and subsea)
- FEED: FEED: done
- Award: EPC award: done, 31 Mar 2025
- E&P: Engineering & procurement: in progress
- Build: Construction: in progress
- Comm.: Pre-commissioning & commissioning: in progress
- Start: Start-up: not started
Now: Pre-commissioning & commissioning
- Value
- NOK 7.5bn [1]
- Workforce
- not published
- Finish
- 2028 [1]
No open adverts linked today
Client, scope, phases, sources
Client: Northern Lights JV (Equinor, Shell, TotalEnergies)
Value: NOK 7.5 billion (phase 2 investment) [1]
Finish: commissioning scheduled for 2028 [1]
Scope
- capacity from 1.5 to 5 Mt CO2 a year; new onshore tanks, jetty and a 5 km pipeline [1]
- Aker Solutions works at Stord, Fornebu and Mumbai 2025-2028; Subsea7 offshore work 2026-2027 [1]
Phase by phase
- FEED · done
- EPC award · done · 31 Mar 2025 [1]
- Engineering & procurement · in progress
- Construction · in progress
- Pre-commissioning & commissioning · in progress
- Start-up · not started
Sources: 1 constructionreviewonline.com · checked 29 Oct 2026
CONFIRMEDOFFSHORENetherlands · CCS / BECCS
Porthos CCS, Port of Rotterdam: CO2 compressor station, 30 km pipeline, P18 storage (2.5 Mt/yr)
Bonatti (EPC compressor station)
- FEED: FEED: done
- Award: EPC award: done
- E&P: Engineering & procurement: done
- Build: Construction: in progress, 2024
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Construction
- Value
- not published
- Workforce
- not published
- Finish
- completion planned for 2026 (May… [2]
No open adverts linked today
Client, scope, phases, sources
Client: Porthos (Gasunie, EBN, Port of Rotterdam)
Value: not published
Finish: completion planned for 2026 (May 2024 plan; not reconfirmed in a source read today) [2]
Scope
- 2.5 Mt CO2 a year for 15 years; three compressors up to 130 bar; onshore pipeline sized for 10 Mt [1]
- Bonatti: design, procurement, construction and pre-commissioning of the compressor station [2]
Phase by phase
- FEED · done
- EPC award · done
- Engineering & procurement · done
- Construction · in progress · 2024 · construction start [2]
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 hellenicshippingnews.com 2 iploca.com · checked 29 Oct 2026
CONFIRMEDLARGEOFFSHORESuriname · FPSO
TotalEnergies GranMorgu (Block 58, Suriname): FPSO 220,000 b/d
SBM Offshore (Fast4Ward FPSO hull reserved, with Technip Energies) · Saipem (SURF EPCI, USD 1.9 bn (Nov 2024), in cooperation with TechnipFMC) · TechnipFMC (subsea production system, flexible risers and umbilical equipment)
- FEED: FEED: done
- Award: EPC award: done, 1 Oct 2024
- E&P: Engineering & procurement: done
- Build: Construction: in progress
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Construction
- Value
- USD 10.5bn [1]
- Workforce
- not published
- Finish
- 2028 [2]
No open adverts linked today
Client, scope, phases, sources
Client: TotalEnergies (50%, operator), APA (50%); Staatsolie option up to 20%
Value: USD 10.5 billion (project, at FID) [1]
Finish: first oil 2028 [2]
Scope
- FPSO 220,000 b/d on the Sapakara and Krabdagu fields, subsea wells [1]
- construction advancing; first oil 2028 (Aug 2026) [2]
Phase by phase
- FEED · done
- EPC award · done · 1 Oct 2024 · FID [1]
- Engineering & procurement · done
- Construction · in progress
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 jpt.spe.org 2 worldoil.com 3 worldpipelines.com 4 jpt.spe.org · checked 29 Oct 2026
CONFIRMEDOFFSHOREEquatorial Guinea · Subsea
Chevron Aseng gas monetisation (Equatorial Guinea): subsea tieback to Alen platform
Subsea7 (subsea installation (EPCI))
- FEED: FEED: done
- Award: EPC award: done, 1 Apr 2026
- E&P: Engineering & procurement: in progress
- Build: Construction: unknown
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Engineering & procurement
- Value
- USD 150-300 million… [1]
- Workforce
- not published
- Finish
- offshore operations expected to… [1]
No open adverts linked today
Client, scope, phases, sources
Client: Noble Energy EG (Chevron)
Value: USD 150-300 million ('substantial', Subsea7 band) [1]
Finish: offshore operations expected to start in 2026 [1]
Scope
- single-well tieback: about 19 km rigid flowline and 20 km umbilicals in about 800 m of water [1]
Phase by phase
- FEED · done
- EPC award · done · 1 Apr 2026 [1]
- Engineering & procurement · in progress
- Construction · unknown
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 worldoil.com · checked 29 Oct 2026
CONFIRMEDUganda / Tanzania · Pipeline
East African Crude Oil Pipeline (EACOP), Uganda-Tanzania, + Tilenga/Kingfisher feed station
China Petroleum Pipeline Engineering (CPP) (pipeline, feeder line and above-ground installations contractor (EACOP tender notices)) · Worley (engineering, procurement and construction management (ENR: EPC JV with CPP, 2022)) · contractors not named in the source read today
- FEED: FEED: done
- Award: EPC award: done
- E&P: Engineering & procurement: done
- Build: Construction: in progress
- Comm.: Pre-commissioning & commissioning: in progress
- Start: Start-up: not started
Now:
Pre-commissioning & commissioning ·
91% complete (Aug 2026)
[1]91%
- Value
- not published
- Workforce
- not published
- Finish
- 2026 [1]
No open adverts linked today
Client, scope, phases, sources
Client: EACOP Ltd (TotalEnergies, UNOC, TPDC, CNOOC)
Value: not published
Finish: first oil expected before the end of 2026 [1]
Scope
- pipeline 91% complete; Pump Station One (fed by Tilenga and Kingfisher) 83% complete (Aug 2026) [1]
Phase by phase
Progress: 91% complete (EACOP deputy MD, 5 Aug 2026) [1]
- FEED · done
- EPC award · done
- Engineering & procurement · done
- Construction · in progress
- Pre-commissioning & commissioning · in progress
- Start-up · not started
Sources: 1 monitor.co.ug 2 enr.com 3 eacop.com · checked 29 Oct 2026
CONFIRMEDKenya · Refinery
Dangote Lamu refinery and petrochemical complex (Kenya), 700,000 b/d
Engineers India (EIL) (PMC and EPCM consultant)
- FEED: FEED: unknown
- Award: EPC award: done, 22 Sep 2026
- E&P: Engineering & procurement: in progress
- Build: Construction: not started
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Engineering & procurement
- Value
- USD 450m [1]
- Workforce
- not published
- Finish
- construction to begin… [1]
No open adverts linked today
Client, scope, phases, sources
Client: Dangote Group
Value: more than USD 450 million (EIL PMC/EPCM contract) [1]
Finish: construction to begin end-September 2026; completion in about three years (Dangote) [1]
Scope
- greenfield 700,000 b/d refinery and petrochemical plant at Lamu [1]
Phase by phase
- FEED · unknown
- EPC award · done · 22 Sep 2026 · EIL PMC/EPCM contract [1]
- Engineering & procurement · in progress
- Construction · not started
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 nairametrics.com · checked 29 Oct 2026
ON THE RADARLARGEPapua New Guinea · LNG plant
Papua LNG (Elk-Antelope, Gulf Province): 5.6 Mtpa, pre-FID
JGC (selected as EPC contractor with Hyundai E&C (JGC, Apr 2026); final award after FID) · Hyundai Engineering & Construction (selected as EPC contractor with JGC; final award after FID) · EPC tender complete; award recommendations await partner approval
- FEED: FEED: done
- Award: EPC award: unknown
- E&P: Engineering & procurement: unknown
- Build: Construction: not started
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Last step done: FEED
- Value
- USD 14bn [1]
- Workforce
- EPC Radar estimate est. 9,800-36,400 at peak how?
- Finish
- not published
No open adverts linked today
Client, scope, phases, sources
Client: ExxonMobil (operator, 34.1%), Santos, Kumul/MRDC, TotalEnergies, ENEOS Xplora
Value: about USD 14 billion (capex) [1]
Workforce estimate (low confidence): EPC Radar estimate from 2 published onshore LNG projects in this tracker, 0.7-2.6 workers per USD million of declared value (ng-nlng-train7, Golden Pass LNG), applied to project value: about USD 14,000 m
Scope
- 5.6 Mtpa of LNG from the Elk and Antelope fields [1]
Phase by phase
- FEED · done
- EPC award · unknown
- Engineering & procurement · unknown
- Construction · not started
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 worldoil.com 2 lngprime.com · checked 19 Nov 2026
CONFIRMEDTurkmenistan · Gas processing
Turkmengaz Galkynysh gas field development, phase IV (turnkey)
CNPC Amudarya Petroleum Company (turnkey construction)
- FEED: FEED: unknown
- Award: EPC award: done, 17 Apr 2026
- E&P: Engineering & procurement: in progress
- Build: Construction: unknown
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Engineering & procurement
- Value
- not published
- Workforce
- not published
- Finish
- not published
No open adverts linked today
Client, scope, phases, sources
Client: Turkmengaz
Value: not published
Scope
- turnkey construction contract for phase IV of Galkynysh development, signed 17 Apr 2026 [1]
Phase by phase
- FEED · unknown
- EPC award · done · 17 Apr 2026 [1]
- Engineering & procurement · in progress
- Construction · unknown
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 interfax.kz · checked 29 Oct 2026
CONFIRMEDOFFSHOREBrunei · Subsea
PETRONAS Carigali Brunei: six-well subsea development to a floating production unit + gas export pipeline
McDermott (EPCIC subsea system and export pipeline)
- FEED: FEED: done
- Award: EPC award: done, 9 Dec 2025
- E&P: Engineering & procurement: in progress
- Build: Construction: unknown
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Engineering & procurement
- Value
- not published
- Workforce
- not published
- Finish
- not published
No open adverts linked today
Client, scope, phases, sources
Client: PETRONAS Carigali Brunei
Value: not published
Scope
- umbilicals, risers and flowlines for six wells to a floating production unit; export pipeline to Brunei LNG [1]
Phase by phase
- FEED · done
- EPC award · done · 9 Dec 2025 [1]
- Engineering & procurement · in progress
- Construction · unknown
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 pgjonline.com · checked 29 Oct 2026
CONFIRMEDOFFSHOREIsrael · Offshore platform
Chevron Leviathan expansion (Eastern Mediterranean): new modules on the Leviathan platform
Hanwha Ocean (module fabrication)
- FEED: FEED: done
- Award: EPC award: done, 5 Mar 2026
- E&P: Engineering & procurement: in progress
- Build: Construction: unknown
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Engineering & procurement
- Value
- not published
- Workforce
- not published
- Finish
- not published
No open adverts linked today
Client, scope, phases, sources
Client: Chevron Mediterranean (operator)
Value: not published
Scope
- module fabrication for integration on the existing Leviathan offshore platform [1]
Phase by phase
- FEED · done
- EPC award · done · 5 Mar 2026 · module fabrication contract [1]
- Engineering & procurement · in progress
- Construction · unknown
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 worldoil.com · checked 29 Oct 2026
REPORTEDMEDIUMUAE · Onshore oil field
ADNOC Onshore South East off-plot facilities (AIP5): 150+ well tie-ins, 270+ km flowlines, degassing station upgrades
CPECC (China Petroleum Engineering & Construction Corporation) (main EPC contractor)
- FEED: FEED: unknown
- Award: EPC award: in progress, Mar 2026
- E&P: Engineering & procurement: in progress
- Build: Construction: unknown
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Engineering & procurement
- Value
- USD 1bn [1]
- Workforce
- not published
- Finish
- not published
No open adverts linked today
Client, scope, phases, sources
Client: ADNOC Onshore
Value: more than USD 1bn (MEED, from sources) [1]
Scope
- tie-in of more than 150 wells, upgrade of remote and central degassing stations, over 270 km of flowlines, well digitalisation; part of the USD 2-3bn South East AIP5 development [1]
Phase by phase
- FEED · unknown
- EPC award · in progress · Mar 2026 · EPC works began in March 2026 (MEED, from sources); earlier EPCm (Dec 2024) cancelled in 2025 and moved to full EPC [1]
- Engineering & procurement · in progress
- Construction · unknown
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 guest.meed.com · checked 5 Nov 2026
REPORTEDUAE · Pipeline
ADNOC Gas Habshan-Al Nouf sales gas pipeline: 127 km, 56 inch, for EWEC
Kalpataru Projects International (India) (EPC contractor, per sources)
- FEED: FEED: unknown
- Award: EPC award: done, Oct 2026
- E&P: Engineering & procurement: not started
- Build: Construction: unknown
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Last step done: EPC award
- Value
- not published (Kalpataru calls a… [1]
- Workforce
- not published
- Finish
- 31 months from award of contract [1]
No open adverts linked today
Client, scope, phases, sources
Client: ADNOC Gas (gas for Emirates Water & Electricity Company, EWEC)
Value: not published (Kalpataru calls a "major" order one above INR 40bn, about USD 415m: MEED) [1]
Scope
- 127 km of 56-inch sales gas pipeline from Habshan to Al Nouf with launcher/receiver stations, four block valve stations and a customer receiving station; 600-660 MMscfd for AI data centre phase 2 and 650-715 MMscfd for the Mirfa relocation [1]
Phase by phase
- FEED · unknown
- EPC award · done · Oct 2026 · Kalpataru filed a "major" order on BSE without naming the project; the link to this pipeline is from MEED sources [1]
- Engineering & procurement · not started
- Construction · unknown
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 guest.meed.com · checked 5 Nov 2026
CONFIRMEDMEDIUMKuwait · Terminal & storage
Kuwait Oil Company Jurassic Light Oil export: 6 crude storage tanks of 618,000 barrels, new pipelines, export network upgrade
Larsen & Toubro (L&T Energy Hydrocarbon Onshore) (EPC contractor, full turnkey)
- FEED: FEED: unknown
- Award: EPC award: done, 15 Jul 2026
- E&P: Engineering & procurement: in progress
- Build: Construction: unknown
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Engineering & procurement
- Value
- USD 979.2m [1]
- Workforce
- not published
- Finish
- not published
No open adverts linked today
Client, scope, phases, sources
Client: Kuwait Oil Company (KOC)
Value: KD 303.5m, about USD 979.2m (MEED) [1]
Scope
- EPC on a fixed-price full turnkey basis of six new crude oil storage tanks of 618,000 barrels each, new pipelines and upgrades to the crude loading and export network [1]
Phase by phase
- FEED · unknown
- EPC award · done · 15 Jul 2026 · Awarded 15 Jul 2026; only two bids in Oct 2025: L&T KD 303.5m, Petrofac KD 310.6m (MEED) [1]
- Engineering & procurement · in progress
- Construction · unknown
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 guest.meed.com · checked 5 Nov 2026
CONFIRMEDMEDIUMOman · Gas processing
PDO Budour-Northeast Birba integrated gas project (Dhofar)
Enppi (Egypt) (main EPC contractor)
- FEED: FEED: unknown
- Award: EPC award: done, May 2026
- E&P: Engineering & procurement: in progress
- Build: Construction: unknown
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Engineering & procurement
- Value
- USD 355m [1]
- Workforce
- not published
- Finish
- not published
No open adverts linked today
Client, scope, phases, sources
Client: Petroleum Development Oman (PDO)
Value: USD 355m (MEED headline) [1]
Scope
- main EPC contract for the Budour-Northeast Birba integrated gas project, Dhofar governorate [1]
Phase by phase
- FEED · unknown
- EPC award · done · May 2026 · MEED reported the award in Apr 2026; Enppi confirmed on 22 May 2026 [1]
- Engineering & procurement · in progress
- Construction · unknown
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 meed.com · checked 5 Nov 2026
REPORTEDSMALLChina · Pipeline
Heihe-Daqing and Daqing-Changling natural gas pipeline, Section I: 279 km
Sinopec Oil Engineering and Construction Corporation (Sinopec Oilfield Service unit) (EPC contractor)
- FEED: FEED: unknown
- Award: EPC award: in progress, Jul 2026
- E&P: Engineering & procurement: not started
- Build: Construction: unknown
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: EPC award
- Value
- CNY 1.8bn [1]
- Workforce
- not published
- Finish
- construction expected to take 710… [1]
No open adverts linked today
Client, scope, phases, sources
Client: not stated in the source
Value: RMB 1.772bn, about USD 246m (company disclosure via PGJ) [1]
Finish: construction expected to take 710 days [1]
Scope
- 279 km natural gas pipeline section in north-east China; Sinopec says the contract is not yet formally executed [1]
Phase by phase
- FEED · unknown
- EPC award · in progress · Jul 2026 · Winning bid disclosed Jul 2026; contract not yet formally executed [1]
- Engineering & procurement · not started
- Construction · unknown
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 pgjonline.com · checked 5 Nov 2026
REPORTEDIraq · Onshore oil field
Nahr Bin Umar and Sindbad fields (Basra): integrated field management and EPCM
Halliburton (IFMS and EPCM)
- FEED: FEED: unknown
- Award: EPC award: done, Jul 2026
- E&P: Engineering & procurement: not started
- Build: Construction: unknown
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Last step done: EPC award
- Value
- not published
- Workforce
- not published
- Finish
- not published
No open adverts linked today
Client, scope, phases, sources
Client: Basra Oil Company (BOC)
Value: not published
Scope
- integrated field management services and engineering, procurement and construction management for the two fields in southern Iraq [1]
Phase by phase
- FEED · unknown
- EPC award · done · Jul 2026 · Reported by Iraq Business News, 21 Jul 2026 [1]
- Engineering & procurement · not started
- Construction · unknown
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 iraq-businessnews.com · checked 5 Nov 2026
REPORTEDOFFSHOREChina · Offshore platform
Sinopec Weizhou oilfield expansion (Beibu Gulf): new WZ-CEP central processing platform, 26 km subsea pipeline
Sinopec Petroleum Engineering Design (EPC consortium) · Sinopec Shengli Oil Construction (EPC consortium)
- FEED: FEED: done
- Award: EPC award: done, Nov 2026
- E&P: Engineering & procurement: in progress
- Build: Construction: not started
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Engineering & procurement
- Value
- final value not disclosed; tender… [1]
- Workforce
- not published
- Finish
- 615-day execution period (World… [1]
No open adverts linked today
Client, scope, phases, sources
Client: Sinopec
Value: final value not disclosed; tender estimate RMB 1.04bn (about USD 146m) [1]
Finish: 615-day execution period (World Pipelines) [1]
Scope
- new processing platform with 8-legged jacket, accommodation and workover module; about 26 km subsea pipeline and fibre-optic cable; 28 well slots; WZ11-4 platform modifications [1]
- planned execution period 615 days, completion tied to first oil [1]
Phase by phase
- FEED · done
- EPC award · done · Nov 2026 · World Pipelines, 9 Nov 2026 [1]
- Engineering & procurement · in progress
- Construction · not started
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 worldpipelines.com · checked 12 Nov 2026
REPORTEDKazakhstan · Gas processing
QazaqGaz second Kashagan gas processing plant (2.5 bcm/y), Atyrau region
China National Chemical Engineering Sixth Construction Company - Kazakhstan Branch (EPCC consortium) · China Wuhuan Engineering Corporation (EPCC consortium) · AVC Production LLP (EPCC consortium) · C-NRG (Synergy) LLP (EPCC consortium)
- FEED: FEED: done
- Award: EPC award: done, Nov 2026
- E&P: Engineering & procurement: in progress
- Build: Construction: not started
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Engineering & procurement
- Value
- not published
- Workforce
- not published
- Finish
- not published in the source
No open adverts linked today
Client, scope, phases, sources
Client: QazaqGaz Processing LLP (QazaqGaz)
Value: not published
Scope
- EPCC contract for a gas processing plant with 2.5 billion m3/year capacity at the Kashagan field [1]
Phase by phase
- FEED · done
- EPC award · done · Nov 2026 · EPCC signed (Trend, 6 Nov 2026) [1]
- Engineering & procurement · in progress
- Construction · not started
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 trend.az · checked 12 Nov 2026
REPORTEDSMALLAlgeria · Gas compression
Zarzaitine field (Illizi): gas lift compression unit upgrade
Tianchen Engineering Corporation (EPCC consortium) · Shaanxi Yanchang Petroleum (EPCC consortium)
- FEED: FEED: done
- Award: EPC award: done, May 2026
- E&P: Engineering & procurement: in progress
- Build: Construction: unknown
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Engineering & procurement
- Value
- USD 238.8m [1]
- Workforce
- not published
- Finish
- 45-month term (MEED) [1]
No open adverts linked today
Client, scope, phases, sources
Client: Groupement Sonatrach-Sinopec (GSS)
Value: USD 238.8m (MEED) [1]
Scope
- EPCC upgrade of the gas lift compression unit at Zarzaitine, 45-month term [1]
Phase by phase
- FEED · done
- EPC award · done · May 2026 · MEED, 14 May 2026 [1]
- Engineering & procurement · in progress
- Construction · unknown
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 guest.meed.com · checked 12 Nov 2026
REPORTEDMEDIUMAlgeria · Gas compression
Sonatrach Rourd Ennous gas field (Illizi): new gas compression station and pipeline network upgrade
Jereh Oil & Gas Engineering Group (EPC contractor)
- FEED: FEED: done
- Award: EPC award: done, Jul 2025
- E&P: Engineering & procurement: in progress
- Build: Construction: in progress
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Construction
- Value
- USD 855m [1]
- Workforce
- not published
- Finish
- 2028 [1]
No open adverts linked today
Client, scope, phases, sources
Client: Sonatrach
Value: USD 855m (Algerian press) [1]
Finish: phased development through 2028 (Algerian press) [1]
Scope
- new gas compression station and upgraded field pipeline network; phased works to 2028 [1]
Phase by phase
- FEED · done
- EPC award · done · Jul 2025 · signed July 2025 [1]
- Engineering & procurement · in progress
- Construction · in progress
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 dzair-tube.dz · checked 12 Nov 2026
REPORTEDMEDIUMOFFSHORELibya · Offshore platform
Bouri gas utilisation project (NC-41 offshore)
Saipem (main contractor (awarded Aug 2023))
- FEED: FEED: done
- Award: EPC award: done, Aug 2023
- E&P: Engineering & procurement: done
- Build: Construction: done
- Comm.: Pre-commissioning & commissioning: in progress, Oct 2026
- Start: Start-up: in progress
Now: Start-up
- Value
- USD 1bn [1]
- Workforce
- not published
- Finish
- start-up under way (MEED, 20 Oct… [1]
No open adverts linked today
Client, scope, phases, sources
Client: Mellitah Oil & Gas (NOC-Eni JV)
Value: USD 1bn main contract (MEED) [1]
Finish: start-up under way (MEED, 20 Oct 2026) [1]
Scope
- gas utilisation project on the Bouri offshore field; mechanical completion reported, start-up procedures under way [1]
Phase by phase
- FEED · done
- EPC award · done · Aug 2023 · Saipem [1]
- Engineering & procurement · done
- Construction · done
- Pre-commissioning & commissioning · in progress · Oct 2026 · mechanical completion reported by MEED, 20 Oct 2026 [1]
- Start-up · in progress
Sources: 1 guest.meed.com · checked 12 Nov 2026
REPORTEDUganda · Onshore oil field
CNOOC Kingfisher oilfield (Lake Albert): central processing facility, 40,000 b/d
CNOOC group (built the surface facilities (CGTN); EPC package holders not re-verified on an open source)
- FEED: FEED: done
- Award: EPC award: done
- E&P: Engineering & procurement: done
- Build: Construction: done
- Comm.: Pre-commissioning & commissioning: in progress, Sep 2026
- Start: Start-up: not started
Now: Pre-commissioning & commissioning
- Value
- not published
- Workforce
- not published
- Finish
- first oil date not published
No open adverts linked today
Client, scope, phases, sources
Client: CNOOC Uganda (operator; TotalEnergies, UNOC partners)
Value: not published
Scope
- central processing facility, 2 million t/y; peak 40,000 b/d; mechanical completion accepted Sep 2026 [1]
Phase by phase
- FEED · done
- EPC award · done [1]
- Engineering & procurement · done
- Construction · done
- Pre-commissioning & commissioning · in progress · Sep 2026 · mechanical completion acceptance (CGTN, 10 Sep 2026); commissioning prep 74% in Jun 2026 [1]
- Start-up · not started
Sources: 1 news.cgtn.com 2 kampalapost.com · checked 12 Nov 2026
ON THE RADARGabon · Refinery
SOGARA Port-Gentil refinery: debottlenecking and new modular hydrocracker complex with marine jetty
Technip Energies (two FEED contracts)
- FEED: FEED: in progress, Apr 2026
- Award: EPC award: not started
- E&P: Engineering & procurement: not started
- Build: Construction: not started
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: FEED
- Value
- not published
- Workforce
- not published
- Finish
- not published
No open adverts linked today
Client, scope, phases, sources
Client: Société Gabonaise de Raffinage (SOGARA)
Value: not published
Scope
- FEED 1: debottlenecking, kerosene sweetening unit, four storage facilities; FEED 2: modular hydrocracker complex, SMR hydrogen, marine jetty [1]
Phase by phase
- FEED · in progress · Apr 2026 · two FEED contracts to Technip Energies [1]
- EPC award · not started
- Engineering & procurement · not started
- Construction · not started
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 hydrocarbonprocessing.com · checked 12 Nov 2026
REPORTEDNigeria · Pipeline
Ajaokuta-Kaduna-Kano (AKK) gas pipeline: Ajaokuta-Kaduna section (303 km) and gas treatment facilities
Oilserv (contractor for the 303 km Ajaokuta-Kaduna stretch (other lots not re-verified))
- FEED: FEED: done
- Award: EPC award: done
- E&P: Engineering & procurement: done
- Build: Construction: in progress
- Comm.: Pre-commissioning & commissioning: in progress, Jul 2026
- Start: Start-up: not started
Now: Pre-commissioning & commissioning
- Value
- not published
- Workforce
- not published
- Finish
- remaining works end-2026 to Q1… [1]
No open adverts linked today
Client, scope, phases, sources
Client: NNPC Ltd
Value: not published
Finish: remaining works end-2026 to Q1 2027 (Oilserv chairman) [1]
Scope
- 303 km pipeline mechanically complete per Oilserv; gas treatment facilities at Ajaokuta and Abuja and some block valve stations still under construction [1]
Phase by phase
- FEED · done
- EPC award · done
- Engineering & procurement · done
- Construction · in progress
- Pre-commissioning & commissioning · in progress · Jul 2026 · mechanical completion of the line stated by Oilserv chairman [1]
- Start-up · not started
Sources: 1 billionaires.africa · checked 12 Nov 2026
REPORTEDOFFSHORENigeria · Pipeline
NLNG gas transmission system GTS-1 expansion: shallow-water pipeline to Bonny Island (about 6 km)
Oilserv (pipeline installation contractor)
- FEED: FEED: unknown
- Award: EPC award: done
- E&P: Engineering & procurement: done
- Build: Construction: in progress
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Construction
- Value
- not published
- Workforce
- not published
- Finish
- not published
No open adverts linked today
Client, scope, phases, sources
Client: Nigeria LNG (NLNG) gas supply network
Value: not published
Scope
- about 6 km of shallow-water pipeline to the Bonny Island LNG plant; barge installation, welding, testing and tie-ins [1]
Phase by phase
- FEED · unknown
- EPC award · done
- Engineering & procurement · done
- Construction · in progress
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 gazettengr.com · checked 12 Nov 2026
REPORTEDTanzania · Pipeline
Ntorya-Madimba gas pipeline (Mtwara), feeding the Madimba gas processing plant
China Petroleum Pipeline (EPC contractor) · China Petroleum Technology & Development Corporation (EPC contractor)
- FEED: FEED: done
- Award: EPC award: done, Jul 2025
- E&P: Engineering & procurement: in progress
- Build: Construction: unknown
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Engineering & procurement
- Value
- not published
- Workforce
- not published
- Finish
- not published
No open adverts linked today
Client, scope, phases, sources
Client: Tanzania Petroleum Development Corporation (TPDC)
Value: not published
Scope
- EPC contract for the gas pipeline from the Ntorya field to the Madimba gas processing plant [1]
Phase by phase
- FEED · done
- EPC award · done · Jul 2025 · TPDC award, Jul 2025 [1]
- Engineering & procurement · in progress
- Construction · unknown
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 tanzaniainvest.com · checked 12 Nov 2026
CONFIRMEDOFFSHOREUnited States · Subsea
Kosmos Tiberius (Keathley Canyon 964, US Gulf): 14 km steel catenary riser and flowline to the Lucius spar
Subsea7 (SURF EPCI (fabrication, transport and installation))
- FEED: FEED: unknown
- Award: EPC award: done
- E&P: Engineering & procurement: in progress
- Build: Construction: not started
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Engineering & procurement
- Value
- 'sizeable' contract, USD 50-150 m… [1]
- Workforce
- not published
- Finish
- first oil expected by end of Q3… [2]
No open adverts linked today
Client, scope, phases, sources
Client: Kosmos Energy (operator, 33.34%), Occidental 33.33%, Navitas Petroleum 33.33%
Value: 'sizeable' contract, USD 50-150 m by Subsea7's own definition [1]
Finish: first oil expected by end of Q3 2028 (OGJ) [2]
Scope
- 14 km steel catenary riser and wet-insulated flowline to the Lucius spar [1]
- about 2,200 m water depth [1]
Phase by phase
- FEED · unknown
- EPC award · done · Subsea7 awarded 13 Nov 2026 [1]
- Engineering & procurement · in progress · project management and engineering starting in Houston [1]
- Construction · not started · offshore activities from 2028 [1]
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 investegate.co.uk 2 ogj.com · checked 14 Nov 2026
CONFIRMEDLARGEUnited States · LNG plant
Port Arthur LNG Phase 1 and Phase 2 (Jefferson County, Texas)
Bechtel (EPC, Phase 1 and Phase 2 (full notice to proceed on both))
- FEED: FEED: done
- Award: EPC award: done, Mar 2023
- E&P: Engineering & procurement: in progress
- Build: Construction: in progress
- Comm.: Pre-commissioning & commissioning: unknown
- Start: Start-up: not started
Now: Construction
- Value
- USD 13bn [1]
- Workforce
- an estimated 5,000 construction jobs (Sempra and Bechtel at Phase 1 FID) [1]
- Finish
- 2027 [2]
No open adverts linked today
Client, scope, phases, sources
Client: Sempra Infrastructure (Port Arthur LNG); Phase 2 anchor buyer ConocoPhillips
Value: about USD 13 billion estimated capex for Phase 1 (Sempra at FID, March 2023); Phase 2 about USD 12 billion plus about USD 2 billion for shared facilities [1]
Finish: Train 1 commercial operation expected 2027, Train 2 2028 (Phase 1); Trains 3 and 4 in 2030-2031 (Phase 2) [2]
Scope
- Phase 1: 2 liquefaction trains, 2 storage tanks, about 13 Mtpa [1]
- Phase 2: 2 more trains (Trains 3 and 4) and 1 tank, about 13 Mtpa; FID September 2025 [2]
Phase by phase
- FEED · done
- EPC award · done · Mar 2023 · Phase 1 FID and notice to proceed to Bechtel; Phase 2 in September 2025 [1]
- Engineering & procurement · in progress
- Construction · in progress · Phase 1 under construction; Phase 2 awarded with full notice to proceed [2]
- Pre-commissioning & commissioning · unknown
- Start-up · not started · Train 1 commercial operation expected 2027, Train 2 2028 [1]
Sources: 1 bechtel.com 2 lngindustry.com · checked 19 Nov 2026
CONFIRMEDUnited States · LNG plant
CP2 LNG Phase 1, Phase 2 and CP2 Expansion (Cameron Parish, Louisiana)
Worley (EPC (reimbursable) on Phase 1, Phase 2 and the CP2 Expansion)
- FEED: FEED: done
- Award: EPC award: done, Nov 2026
- E&P: Engineering & procurement: in progress
- Build: Construction: in progress, Mar 2026
- Comm.: Pre-commissioning & commissioning: unknown
- Start: Start-up: not started
Now: Construction
- Value
- EPC value not disclosed; total… [3]
- Workforce
- not published
- Finish
- Expansion FID targeted for early… [1]
No open adverts linked today
Client, scope, phases, sources
Client: Venture Global (CP2 LNG)
Value: EPC value not disclosed; total CP2 project financing USD 20.7 billion after the Phase 2 FID (Venture Global) [3]
Finish: Expansion FID targeted for early 2027 [1]
Scope
- more than 29 Mtpa nameplate once complete (Venture Global) [2]
- Expansion: 6 more liquefaction blocks, a gas-fired power plant and a third berth, about +11.7 Mtpa peak (FERC filing) [2]
Phase by phase
- FEED · done
- EPC award · done · Nov 2026 · Worley EPC on Phase 1 and 2; EPC for the Expansion signed Nov 2026 [1]
- Engineering & procurement · in progress
- Construction · in progress · Mar 2026 · Phase 2 FID 13 Mar 2026 [3]
- Pre-commissioning & commissioning · unknown
- Start-up · not started
Sources: 1 lngindustry.com 2 hydrocarbonprocessing.com 3 worldoil.com · checked 19 Nov 2026
CONFIRMEDUnited States · LNG plant
Corpus Christi LNG Midscale Trains 8 & 9 and debottlenecking (Texas)
Bechtel (EPC, full notice to proceed June 2025)
- FEED: FEED: done
- Award: EPC award: done, Jun 2025
- E&P: Engineering & procurement: in progress
- Build: Construction: in progress
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Construction
- Value
- not published by Cheniere
- Workforce
- not published
- Finish
- later this decade (Cheniere) [1]
No open adverts linked today
Client, scope, phases, sources
Client: Cheniere (Corpus Christi Liquefaction)
Value: not published by Cheniere
Scope
- 2 midscale trains, over 3 Mtpa; with debottlenecking about 5 Mtpa; Corpus Christi over 30 Mtpa later this decade [1]
Phase by phase
- FEED · done
- EPC award · done · Jun 2025 · FID and full notice to proceed to Bechtel [1]
- Engineering & procurement · in progress
- Construction · in progress · built next to the Stage 3 project [1]
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 cheniere.com · checked 19 Nov 2026
CONFIRMEDLARGEUnited States · LNG plant
Golden Pass LNG (Sabine Pass, Texas): Trains 1-3
McDermott (EPC JV partner (revised EPC contract Nov 2025)) · Chiyoda (EPC JV partner (Chiyoda International Corp.)) · Zachry Group, partner of the original 2019 EPC JV, is not a party to the revised EPC contract of November 2025
- FEED: FEED: done
- Award: EPC award: done
- E&P: Engineering & procurement: done
- Build: Construction: in progress
- Comm.: Pre-commissioning & commissioning: in progress
- Start: Start-up: in progress, Mar 2026
Now: Start-up
- Value
- USD 10bn [3]
- Workforce
- more than 7,000 at peak construction (Golden Pass, via Port Arthur News, 2022) [3]
- Finish
- 2027 [2]
No open adverts linked today
Client, scope, phases, sources
Client: Golden Pass LNG (QatarEnergy 70%, ExxonMobil 30%)
Value: the USD 10 billion project (Port Arthur News, 2022) [3]
Finish: Train 3 targeted for H1 2027 [2]
Scope
- 3 trains, 18 Mtpa; Train 1 first LNG 30 March 2026, first cargo 22 April 2026 [2]
- revised EPC contract for Trains 2 and 3 signed by McDermott and Chiyoda in November 2025 [1]
Phase by phase
- FEED · done
- EPC award · done
- Engineering & procurement · done
- Construction · in progress · Trains 2 and 3 [2]
- Pre-commissioning & commissioning · in progress · Train 2 start-up targeted H2 2026 [2]
- Start-up · in progress · Mar 2026 · Train 1 first LNG [2]
Sources: 1 lngindustry.com 2 gasprocessingnews.com 3 panews.com 4 hydrocarbonengineering.com · checked 19 Nov 2026
CONFIRMEDLARGEUnited States · LNG plant
Louisiana LNG (Woodside, Calcasieu Parish): 3-train foundation development
Bechtel (EPC contractor)
- FEED: FEED: done
- Award: EPC award: done, Apr 2025
- E&P: Engineering & procurement: in progress
- Build: Construction: in progress, Jun 2026
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now:
Construction ·
28% complete (Jun 2026)
[1]28%
- Value
- USD 17.5bn [1]
- Workforce
- almost 900 construction personnel in September 2025 (Woodside); peak not published [2]
- Finish
- 2029 [1]
No open adverts linked today
Client, scope, phases, sources
Client: Woodside Energy (Louisiana LNG)
Value: USD 17.5 billion project (OffshoreSource, Aug 2026) [1]
Finish: first cargo targeted for 2029 [1]
Scope
- 3 trains, 16.5 Mtpa; permitted for 27.6 Mtpa with 2 expansion trains [2]
- 2 storage tanks of 235,000 m3 each [1]
Phase by phase
Progress: 28% overall at end of Q2 2026 (Train 1 35%, Train 2 25%, Train 3 18%) [1]
- FEED · done
- EPC award · done · Apr 2025 · FID 29 April 2025 [2]
- Engineering & procurement · in progress
- Construction · in progress · Jun 2026 · 28% overall; Train 1 35%, Train 2 25%, Train 3 18% [1]
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 offshoresource.com 2 hydrocarbonengineering.com · checked 19 Nov 2026
CONFIRMEDUnited States · LNG plant
Commonwealth LNG (Cameron Parish, Louisiana): 6 SnapLNG trains
Technip Energies (EPC, full notice to proceed after FID (May 2026))
- FEED: FEED: done
- Award: EPC award: done, May 2026
- E&P: Engineering & procurement: in progress
- Build: Construction: in progress
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Construction
- Value
- USD 1.2bn [1]
- Workforce
- not published
- Finish
- not published in the source read…
No open adverts linked today
Client, scope, phases, sources
Client: Commonwealth LNG (Caturus)
Value: over USD 1.17 billion in revenue for Technip Energies [1]
Finish: not published in the source read today
Scope
- 6 identical modular liquefaction trains (SnapLNG by T.EN), 9.5 Mtpa [1]
Phase by phase
- FEED · done
- EPC award · done · May 2026 · FID and full notice to proceed [1]
- Engineering & procurement · in progress
- Construction · in progress
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 oedigital.com · checked 19 Nov 2026
ON THE RADARUnited States · LNG plant
Texas LNG (Port of Brownsville, Texas)
Kiewit (lump-sum turnkey EPC, signed March 2026; limited notice to proceed July 2026; modules at Kiewit Offshore Services, Ingleside)
- FEED: FEED: done
- Award: EPC award: done, Mar 2026
- E&P: Engineering & procurement: in progress, Jul 2026
- Build: Construction: not started
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Engineering & procurement
- Value
- not disclosed
- Workforce
- not published
- Finish
- FID not yet announced (checked…
No open adverts linked today
Client, scope, phases, sources
Client: Glenfarne (Texas LNG)
Value: not disclosed
Finish: FID not yet announced (checked today)
Scope
- about 4 Mtpa export project; EPC executed after 14 months of pre-FID engineering [2]
- limited notice to proceed: long-lead orders, EPC engineering and geotechnical work before FID [1]
Phase by phase
- FEED · done
- EPC award · done · Mar 2026 · EPC contract executed [2]
- Engineering & procurement · in progress · Jul 2026 · limited notice to proceed [1]
- Construction · not started
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 lngindustry.com 2 offshore-technology.com · checked 19 Nov 2026
REPORTEDKazakhstan · Gas processing
QazaqGaz new Karachaganak gas processing plant (5 bcm/y), West Kazakhstan Region
Hyundai Engineering Co., Ltd. (EPC consortium (shares not published)) · SICIM Kazakhstan LLP (EPC consortium (shares not published))
- FEED: FEED: done
- Award: EPC award: done, 12 Nov 2026
- E&P: Engineering & procurement: in progress
- Build: Construction: not started
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Engineering & procurement
- Value
- not published
- Workforce
- not published
- Finish
- not published in the source
No open adverts linked today
Client, scope, phases, sources
Client: QazaqGaz Processing LLP (QazaqGaz National Company)
Value: not published
Scope
- 5 bcm/y gas processing plant for raw gas from Karachaganak; products: commercial gas, LPG, sulphur [1]
Phase by phase
- FEED · done
- EPC award · done · 12 Nov 2026 · EPC contract signed with Hyundai Engineering and SICIM Kazakhstan [1]
- Engineering & procurement · in progress
- Construction · not started
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 trend.az · checked 19 Nov 2026
REPORTEDUAE · Onshore oil field
ADNOC Onshore North East Bab (NEB) cluster: facilities upgrade phase 2 (Al Nouf, Rumaitha, Shanayel CPP)
Mannesmann Energy (Abu Dhabi) (EPC, phase 2 facilities upgrade (picked by ADNOC Onshore, MEED))
- FEED: FEED: unknown
- Award: EPC award: done, Nov 2026
- E&P: Engineering & procurement: unknown
- Build: Construction: not started
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Last step done: EPC award
- Value
- not published
- Workforce
- not published
- Finish
- not published in the source
No open adverts linked today
Client, scope, phases, sources
Client: ADNOC Onshore
Value: not published
Scope
- upgrade of existing facilities and production capacity at NEB CPP assets in Al Nouf, Rumaitha and Shanayel [2]
Phase by phase
- FEED · unknown
- EPC award · done · Nov 2026 · ADNOC Onshore picked Mannesmann Energy for phase 2 (MEED) [1]
- Engineering & procurement · unknown
- Construction · not started
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 meed.com 2 wam.ae · checked 19 Nov 2026
CONFIRMEDOFFSHOREMalaysia · Subsea
PETRONAS Limbayong deepwater development, offshore Sabah: full subsea scope
TechnipFMC (FMC Wellhead Equipment Sdn. Bhd.) (iEPCI, entire subsea scope)
- FEED: FEED: done
- Award: EPC award: done, Sep 2026
- E&P: Engineering & procurement: in progress
- Build: Construction: not started
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Engineering & procurement
- Value
- USD 75-250 million (TechnipFMC… [1]
- Workforce
- not published
- Finish
- not published in the source
No open adverts linked today
Client, scope, phases, sources
Client: PETRONAS Carigali Sdn. Bhd.
Value: USD 75-250 million (TechnipFMC 'significant' contract band) [1]
Scope
- greenfield deepwater development; iEPCI with Subsea 2.0 configure-to-order equipment [1]
Phase by phase
- FEED · done
- EPC award · done · Sep 2026 · iEPCI to TechnipFMC [1]
- Engineering & procurement · in progress
- Construction · not started
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 energy-pedia.com · checked 19 Nov 2026
CONFIRMEDJapan · Terminal & storage
Shikoku Electric Sakaide LNG terminal upgrade
JFE Engineering (JV (roles not published)) · Kawasaki Heavy Industries (JV (roles not published))
- FEED: FEED: done
- Award: EPC award: done, Mar 2026
- E&P: Engineering & procurement: in progress
- Build: Construction: not started
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Engineering & procurement
- Value
- not disclosed
- Workforce
- not published
- Finish
- not published in the source
No open adverts linked today
Client, scope, phases, sources
Client: Shikoku Electric Power
Value: not disclosed
Scope
- upgrade of the Sakaide LNG terminal [1]
Phase by phase
- FEED · done
- EPC award · done · Mar 2026 · JFE Engineering and Kawasaki Heavy Industries JV [1]
- Engineering & procurement · in progress
- Construction · not started
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 lngprime.com · checked 19 Nov 2026
CONFIRMEDTaiwan · Terminal & storage
CPC Kaohsiung Intercontinental LNG receiving terminal: regasification facility (1,600 t/h)
CTCI (EPC, regasification facility)
- FEED: FEED: done
- Award: EPC award: done, Aug 2025
- E&P: Engineering & procurement: in progress
- Build: Construction: not started
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Engineering & procurement
- Value
- TWD 29.6bn [1]
- Workforce
- not published
- Finish
- 2030 [1]
No open adverts linked today
Client, scope, phases, sources
Client: CPC Corporation
Value: NT$29.6bn (about USD 968m), EPC contract [1]
Finish: expected to be operational by 2030 (Offshore Technology) [1]
Scope
- regasification facility, output 1,600 t/h; expected operational by 2030 [1]
Phase by phase
- FEED · done
- EPC award · done · Aug 2025 · EPC to CTCI, NT$29.6bn [1]
- Engineering & procurement · in progress
- Construction · not started
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 offshore-technology.com · checked 19 Nov 2026
REPORTEDOFFSHOREAustralia · Offshore platform
Ichthys LNG Phase 2c Part 1: five subsea production wells (Brewster reservoir)
McDermott (subsea EPCI, in consortium with Baker Hughes) · Baker Hughes (subsea EPCI, in consortium with McDermott)
- FEED: FEED: unknown
- Award: EPC award: done, 19 Nov 2026
- E&P: Engineering & procurement: in progress
- Build: Construction: not started
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Engineering & procurement
- Value
- not published
- Workforce
- not published
- Finish
- not published
No open adverts linked today
Client, scope, phases, sources
Client: Ichthys Joint Venture (INPEX, operator)
Value: not published
Scope
- five production wells targeting the Brewster reservoir, using existing drill centres; new subsea infrastructure tied back to the existing offshore system; Browse Basin, about 220 km off Western Australia [1]
Phase by phase
- FEED · unknown
- EPC award · done · 19 Nov 2026 · McDermott and Baker Hughes consortium, EPCI [1]
- Engineering & procurement · in progress
- Construction · not started
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 ogj.com · checked 20 Nov 2026
REPORTEDMEDIUMUAE · Gas processing
ADNOC Onshore Ruwais Diyab unconventional gas development: surface facilities and pipeline network (design-build-operate)
Jereh Group (design, build and operate: 29 months construction, 60 months operations (Jereh filing on the Shenzhen Stock Exchange, via MEED))
- FEED: FEED: done
- Award: EPC award: done, Nov 2026
- E&P: Engineering & procurement: in progress
- Build: Construction: not started
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Engineering & procurement
- Value
- USD 1.7bn [1]
- Workforce
- not published
- Finish
- 2029 [1]
No open adverts linked today
Client, scope, phases, sources
Client: ADNOC Onshore
Value: USD 1.7 billion (Jereh filing, via MEED) [1]
Finish: first gas from 2029 [1]
Scope
- 345 million scf/d of raw gas from 2029 over 25 years, potentially up to 1 billion scf/d; ADNOC FID on 2 Nov 2026 [1]
- ADNOC final investment decision announced at ADIPEC, 2 Nov 2026 [2]
Phase by phase
- FEED · done
- EPC award · done · Nov 2026 · Jereh, design-build-operate (company filing reported by MEED, 13 Nov 2026) [1]
- Engineering & procurement · in progress
- Construction · not started
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 guest.meed.com 2 worldoil.com · checked 26 Nov 2026
REPORTEDMEDIUMUAE · Onshore oil field
ADNOC Onshore Bu Hasa cluster (Bu Hasa, Bida Al-Qemzan, Huwaila): wellhead surface facilities and gathering flowlines
Jereh Group (EPC, framework agreement on call-off basis) · Galfar Emirates (portion of the scope (MEED))
- FEED: FEED: unknown
- Award: EPC award: done, Nov 2026
- E&P: Engineering & procurement: unknown
- Build: Construction: unknown
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Last step done: EPC award
- Value
- USD 392.1m [1]
- Workforce
- not published
- Finish
- 36-month framework with 24-month… [1]
No open adverts linked today
Client, scope, phases, sources
Client: ADNOC Onshore
Value: AED 1.44 billion (USD 392.1 million), Jereh filing via MEED [1]
Finish: 36-month framework with 24-month extension option [1]
Scope
- production well module skids, gas lift skids, wellhead control panels and solar power units; 36 months plus 24-month option [1]
Phase by phase
- FEED · unknown
- EPC award · done · Nov 2026 · framework agreement, 36 months + 24-month option [1]
- Engineering & procurement · unknown
- Construction · unknown
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 guest.meed.com · checked 26 Nov 2026
REPORTEDArgentina · Pipeline
Argentina LNG: twin export pipelines, about 527 km (48-inch gas, 24-inch liquids), Neuquén to Río Negro coast
Pumpco (pipeline construction consortium, best offer (EconoJournal; shares not defined yet)) · Bonatti (pipeline construction consortium, best offer) · Contreras Hermanos (local partner in the construction consortium) · Tenaris (supply: 24-inch liquids pipe (YPF tender, Nov 2026)) · Grupo Cuñado and CPW (supply: 48-inch gas pipe (YPF tender, Nov 2026))
- FEED: FEED: unknown
- Award: EPC award: in progress, 9 Jul 2026
- E&P: Engineering & procurement: not started
- Build: Construction: not started
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: EPC award
- Value
- construction not published; pipe… [2]
- Workforce
- not published
- Finish
- not published
No open adverts linked today
Client, scope, phases, sources
Client: Argentina LNG (YPF with ENI and XRG)
Value: construction not published; pipe tenders about USD 2 billion (Perfil) [2]
Scope
- two parallel pipelines of about 527 km: 48-inch gas and 24-inch liquids [1]
- route from Meseta Buena Esperanza (Neuquén) to Sierra Grande (Río Negro); pipe supply awarded by reverse auction [2]
Phase by phase
- FEED · unknown
- EPC award · in progress · 9 Jul 2026 · Pumpco-Bonatti-Contreras best offer, award not confirmed by an official source; construction subject to FID [1]
- Engineering & procurement · not started
- Construction · not started
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 econojournal.com.ar 2 perfil.com · checked 26 Nov 2026
CONFIRMEDOFFSHORECanada · Pipeline
Prince Rupert Gas Transmission (PRGT): subsea section, about 50 km to Ksi Lisims LNG (Pearse Island)
Allseas (pipelay of the subsea section (Solitaire and Sandpiper))
- FEED: FEED: unknown
- Award: EPC award: done, 28 Jul 2026
- E&P: Engineering & procurement: unknown
- Build: Construction: not started
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Last step done: EPC award
- Value
- not published
- Workforce
- not published
- Finish
- 2029 [1]
No open adverts linked today
Client, scope, phases, sources
Client: Western LNG
Value: not published
Finish: offshore installation planned for 2029 [1]
Scope
- about 50 km of 36 and 48-inch concrete-weight coated pipeline, shoreline to about 450 m water depth; shore crossings, tie-ins, trenching [1]
Phase by phase
- FEED · unknown
- EPC award · done · 28 Jul 2026 · installation contract; Ksi Lisims LNG FID not stated in the source [1]
- Engineering & procurement · unknown
- Construction · not started
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 allseas.com · checked 26 Nov 2026
REPORTEDGermany · Terminal & storage
German LNG Terminal, Brunsbüttel: onshore LNG import terminal (about 10 bcm/year)
Cobra IS (terminal consortium with Sener (client of MT Group)) · Sener (terminal consortium with Cobra IS) · MT Group (balance-of-plant infrastructure)
- FEED: FEED: done
- Award: EPC award: done, 28 Jul 2026
- E&P: Engineering & procurement: in progress
- Build: Construction: in progress
- Comm.: Pre-commissioning & commissioning: not started
- Start: Start-up: not started
Now: Construction
- Value
- not published
- Workforce
- not published
- Finish
- 2027 [1]
No open adverts linked today
Client, scope, phases, sources
Client: German LNG Terminal (Gasunie 40%, RWE 10%, KfW 50%)
Value: not published
Finish: completion scheduled for 2027 (MT Group) [1]
Scope
- onshore LNG import terminal, about 10 bcm/year into the German grid [1]
Phase by phase
- FEED · done
- EPC award · done · 28 Jul 2026 · MT Group balance-of-plant award from the Cobra IS / Sener consortium [1]
- Engineering & procurement · in progress
- Construction · in progress
- Pre-commissioning & commissioning · not started
- Start-up · not started
Sources: 1 lngprime.com · checked 26 Nov 2026